When the TIGER Discretionary Grants are awarded, there are going to be a lot of unhappy people

Tonight I was curious in knowing what other projects have other state's applied for the $1.5 billion in TIGER Discretionary Funds that will be awarded next month.  My original thinking was that it was only one project per state, and it would be a neat idea to maybe research and blog about them  Bzzzztttt, was I wrong!

The USDOT received 1380, yes 1380, applications from all 50 states, plus Guam, the Virgin Islands, Puerto Rico, and the District of Columbia.  The total amount of requests total $56.5 billion.  That is nearly 38 times the amount that will be awarded!!!!  No wonder why the final decisions have been delayed.

Texas led with 125 applications - followed closely by California (117), and Florida (115).  The least amount of applications came from Hawaii with only 1. New Hampshire, South Dakota, and North Dakota only had two applications.

It appears that any organization could apply for the TIGER Grants - and that would explain why SCDOT encouraged Horry County to put in an application for upgrading SC 22 to Interstate standards a number of months ago.

The amount of money asked for in each applications was varied also. 514 of the 1380 (37.2%) applications were asking for amounts of less than $20 million.  Over 56% (785) were applications for $20-100 million in funds.  The rest, 81 applications, were from $100 billion to the maximum of $300 billion.

Applications came in for highway improvements, transit improvements, rail improvements, and other.  (Most likely pedestrian and bike projects.)

Check out the USDOT's two page summary of the TIGER Grant applications here.

I'm going to start looking into what projects applied for grant money and what they are for.

One of the first ones I did find was an application by NYSDOT for completing the final upgrades for the US 15/I-99 project.  The amount of the application was for $38 million.

Exit question: What are some of the projects being applied for in your state?  And which of them are the most pressing? So leave a comment.

Comments

Unknown said…
Adam,

I linked to this item on my Inside Lane page.

http://www.inside-lane.com/2010/01/28/blog-tiger-grant-applications-1380-requests-totaling-56-5-billion-for-only-1-5-billion-available-colorado-total-requests-1-1-billion/

Kevin Flynn
Adam said…
Kevin,

Thanks! I find it amazing how many applications were made for such few funds. It will be interesting to see what projects are awarded the grants and for how much.

If one project gets the maximum of $300 million, that's 20% of the total money available. It will be interesting to see the reactions.

Here in NC, local leaders near the I-85 Yadkin River Project are not as optimistic as they were a few months ago. And NCDOT is already trying to come up with alternative funding plans based on how much if any grant dollars they receive.
Matt Salek said…
Colorado DOT submitted 7 projects totaling $463M. Here's a list: http://milepost61.wordpress.com/2009/08/20/cdot-pursuing-7-tiger-grants/
Arnold said…
I thought the exact same thing!

Here in Ann Arbor, we applied for $22 million for a Bridge that goes over a train track in conjunction with one that goes over a residential street.

I wrote the Tiger Grant people to inform them that the train is used twice a day - between 10pm and 6am, and that the residential road is typical to many in the city that never - ever have had any discussion about putting up a bridge to avoid a stoplight.

Instead of replacing the current bridges, I asked the Tiger Group to reject the application due to the waste. Ann Arbor could put in at grade roads at a cost less than $10 million. They just don't want to.

The interesting part in my discussions with the Tiger Group is there seems to be little puclic input. Nor does there appear to be much investigation into the need / honesty of the applications.

I hope they - The Tiger Grant people - can weed out the pork and give the money to the truly needy.

www.theannarborbridgetonowhere.com
Brian said…
@Arnold:

Unfortunately, there's just no decent way to possibly make Stadium and State at-grade without significantly encroaching upon adjacent property, as the city's letter points out. This is just one of those cases where the original bridges were built to address the traffic issues of that time, development was allowed in the adjacent areas, and thus no good way to just remove the overpasses. And as one of my friends points out, construction is well under way. I admire you for wanting to speak out, though.

Popular posts from this blog

2018 Mojave Road Trip Part 2; The deadly desert highway (California State Route 127 and Nevada State Route 373)

After leaving Barstow via Old Highway 58 my next destination was in Death Valley.  To access Death Valley from rural San Bernardino County required a trek on north on Interstate 15 to California State Route 127 which becomes Nevada State Route 373 at the state line. Along I-15 I encountered the road sign oddity that is Zzyzx Road about eight miles south of Baker.   Zzyzx Road is a four mile road that used to go to the Zzyzx Mineral Springs and Health Spa.   The spa was founded in the 1940s and the owner made up the name "Zzyzx" to claim it was the last word in the English Language.  The spa has been shut down since the 1970s and is now part of a Desert Studies Center for California State University. The southern terminus of CA 127 in Baker is located at I-15 exit 246.  CA 127 is a 91 mile north/south highway which runs to the Nevada State Line in Inyo County.  CA 127 is called Death Valley Road from I-15 northward.  South of CA 127 ...

Finding the Pre-Emption Road of New York State

  The Pre-Emption Road (or rather a series of roads named Pre-Emption Road) follows a survey line called the Pre-Emption Line, drawn in the early days of the United States. The story begins with Massachusetts and New York having competing land claims to modern day Western New York State that have their roots in colonial charters granted by the British. After the Revolutionary War ended, this land became the frontier of the nation and its settlement became a priority for the new American government. During this era, there were a lot of competing land claims that needed to be settled. It was no different with the land claims between New York State and Massachusetts. On November 30, 1786, Massachusetts and New York sent representatives to Hartford, Connecticut to resolve their competing land claims. In less than three weeks, the representatives had reached a compromise. Massachusetts would receive pre-emption rights, meaning the right to sell the land after the Indian title ...

What's In a Name?: When the Roads Really Do Tell a Story

  Our tagline on the Gribblenation blog is "because every road tells a story". Some roads tell different stories than others. Along our travels, we may see historic markers that tell us a little story about the roads we travel or the places we pass by. Some historic markers are more general, as to telling us who lived where or what old trail traversed between two towns. During my travels across New York State and other states or provinces, I pass by many historic markers, some with interesting or amusing references to roads. I wanted to highlight a few of the markers I've seen along my travels around the Empire State and help tell their stories. Those stories may be as specific as explaining the tales of a tree that was used to help measure a distance of eight miles from Bath to Avoca in Steuben County, as referenced on the Eight Mile Tree historical marker above. They may also help point the way along historical roads first used centuries ago, or may help tell a local l...