Skip to main content

DNR rejects SCDOT's I-73 wetland proposal

It didn't take long for the South Carolina Department of Natural Resources' Board to reject the DOT's $450,000 wetland mitigation proposal. Without hesitation, the board accepted DNR director John Frampton's suggestion that he negotiate a better deal with newly named DOT director, Buck Limehouse.

Limehouse has experience working with the DNR on wetland issues before as he helped to broker a deal that allowed the state to purchase 9,167 acres of land on Sandy Island as compensation for lost wetlands during the construction of the Conway Bypass and Carolina Bays Parkway.

27 acres of the Little Pee Dee Heritage Preserve would be impacted by the construction of I-73. Also, another three acres would be impacted by the construction of a new SC 917 bridge. The DNR has stated that they do not want to block the construction of I-73; however, they do expect fair compensation.

The $450,000 mitigation proposal authored by interim DOT Director Tony Chapman suggested that the DNR use the money to purchase additional land in the state and cover increased management costs.

The Heritage Trust Advisory Board also filed a report regarding I-73 and found that "...it might be more practical to cross where an existing road already crosses the preserve, rather than disturb another portion of the Little Pee Dee River corridor."

Their conclusion agrees with the DOT's Environmental Impact Statement that concluded crossing the Little Pee Dee River at SC 917 would have the least possible environmental impact. The findings of the Heritage Trust Advisory Board and the DOT is also shared by 15 other state and federal agencies including the Environmental Protection Agency.

The Heritage board found four direct effects that I-73 would have on the preserve.
  1. Habitat loss in the taken acreage
  2. Habitat fragmentation that could affect wildlife movements. They commented that the fragmentation is one of the more challenging and difficult impacts to measure.
  3. Property management. Including the restrictions of controlled burning.
  4. Impacts on the character of the preserve. Noise, litter, pollutants etc.
The board did not put a monetary value on each of the four impacts.

SCDOT needs the approval of the DNR in order to file for construction permits. The Federal Highway Administration would typically require a special analysis of the crossing; however, if SCDOT gets approval from the DNR that provision would be waived.

Story:
I-73: Offer for preserve crossing rejected ---Myrtle Beach Sun News

See Also:
I-73 wetland proposal delayed to May 18
SCDOT to present I-73 wetland proposal on May 3rd
SC: Heritage Trust Board won't fight I-73 but expects compensation

Commentary:
After the past few months of claims that the DOT and DNR were working together towards a solution to this issue, it sure doesn't seem like much of a joint effort. In fact in interim SCDOT director Tony Chapman's letter to the DNR, it didn't have a feel of cohesion between the two agencies. In it, he wrote that the same taxpayers who allowed the state to purchase the land for the preserve are going to be paying for the construction of I-73 and that the DNR should give the land to the DOT. However because it is a sensitive issue and area, the DOT is going to offer $450,000 for it. Sounds pretty insulting, doesn't it.

So now there's a new leader at the DOT, Buck Limehouse. Limehouse, whose appointing to the position came with much fanfare and respect from SC politicians, has had dealings with the DNR before as the SCDOT Committee Chairman during the 1990s. Frampton's offering to directly negotiate with Limehouse over the compensation is a good step. As I mentioned in the article summary, it was Limehouse who led the way in the purchasing of over 9,000 acres of land on Sandy Island as compensation for wetland impact on both the Carolina Bays Parkway and Conway Bypass.

Another thing to note was Frampton again suggested that outside influences are watching this decision and that the possible solution to the matter will be precedent setting and if done incorrectly would have detrimental consequences to everyone. He's referring to the Southern Environmental Law Center (SELC) who has voiced its concern over the plan to build I-73 through the preserve.

But in the article some more information came out. SCDOT has been maintaining for sometime that their preferred corridor - and its routing through the preserve - has the least overall impact to the environment including the least amount of wetlands destroyed. The Heritage Trust Board seems to agree with stating a crossing further south could have more interruption to wildlife than building the Interstate where a highway already crosses the river. The article also mentions that this theory is shared by 15 other state and federal agencies including the EPA. Will the SELC take that into consideration or legally challenge the route is unknown, of course an agreement between SCDOT and SCDNR has to be reached first.

Finally, the SELC has stated that SCDOT had ignored Section 4(f) of the Federal Transportation Act of 1966. Which basically says newly constructed highways can not damage nature preserves unless there is no other viable alternative. The SELC says that there are - specifically building the route along SC 9 and SC 501. A representative of the SELC has stated that with these requirements SCDOT's I-73 routing proposal would be "very tricky" to meet the legal standards.

But with a member of the Federal Highway Administration, Shane Belcher, telling the DNR's board that their approval will allow a special analysis to be bypassed, the SELC's objections may hit a roadblock.

Comments

Popular posts from this blog

I-40 rockslide uncovers old debates on highway

The Asheville Citizen-Times continues to do a great job covering all the angles of the Interstate 40 Haywood County rock slide. An article in Sunday's edition provides a strong historical perspective on how the Pigeon River routing of Interstate 40 came about. And perhaps most strikingly, in an article that ran just prior to the highway's opening in the fall of 1968, how engineers from both Tennessee and North Carolina warned "...that slides would probably be a major problem along the route for many years." On February 12, 1969, not long after the Interstate opened, the first rock slide that would close I-40 occurred. Like many other Interstates within North Carolina, Interstate 40 through the mountains has a history prior to formation of the Interstate Highway System and was also a heated political battle between local communities. The discussion for a road that would eventually become Interstate 40 dates back to the 1940's as the idea for interregional high

Interstate 210 the Foothill Freeway

The combined Interstate 210/California State Route 210 corridor of the Foothill Freeway is approximately 85.31-miles.  The Interstate 210/California State Route 210 corridor begins at Interstate 5 at the northern outskirts of Los Angeles and travels east to Interstate 10 in Redlands of San Bernardino County.  Interstate 210 is presently signed on the 44.9-mile segment of the Foothill Freeway between Interstate 5 and California State Route 57.  California State Route 210 makes up the remaining 40.41 miles of the Foothill Freeway east to Interstate 10.  Interstate 210 is still classified by the Federal Highway Administration as existing on what is now signed as California State Route 57 from San Dimas south to Interstate 10.  The focus of this blog will mostly be on the history of Interstate 210 segment of the Foothill Freeway.   Part 1; the history of Interstate 210 and California State Route 210 Interstate 210 (I-210) was approved as a chargeable Interstate during September of

Former California State Route 41 past Bates Station

When California State Route 41 was commissioned during August 1934 it was aligned along the then existing Fresno-Yosemite Road north of the San Joaquin River.  Within the Sierra Nevada foothills of Madera County, the original highway alignment ran past Bates Station via what is now Madera County Road 209, part of eastern Road 406 and Road 207.   Bates Station was a stage station plotted during the early 1880s at what was the intersection of the Coarsegold Road and Stockton-Los Angeles Road.   The modern alignment bypassing Bates Station to the east would be reopened to traffic during late 1939.   Part 1; the history of California State Route 41 past Bates Station Bates Station was featured as one of the many 1875-1899 Madera County era towns in the May 21, 1968, Madera Tribune .  Post Office Service at Bates Station is noted to have been established on November 23, 1883 and ran continuously until October 31, 1903.  The postal name was sourced from Bates Station owner/operator George Ba