Skip to main content

April I-74/US 311 Freeway Progress Report

Apparently not having seen enough construction on Saturday, I traveled to Winston-Salem and back to check on the progress of building the US 74/US 311 freeways near High Point.

1. High Point 'East Belt'
A. Open Portion
Why did I start in Winston-Salem. Part of the contract for building the 'East Belt' portion of I-74 (from now former Business 311 to I-85) calls for updating signs to include I-74 (the plans indicated full interstate, but it may now be Future) and the placing of I-74 mile markers along the already opened portion of the road to Business 85. I was checking to see if there were any indications this was happening, which would mean the route is closer to opening than NCDOT has announced, by the end of the year. The only change on the existing road I could find though were to the overhead signs at the now former Business 311 interchange heading east (Exit 65). Both signs, except for the exit tab, had been removed:
The sign on the left read 'To NC 68'. It turns out though that these signs were blown down a tornado that passed over a week or so before. Thus NCDOT will have to decide to replace them as they were or replace them by updated signs, such as an East I-74/South US 311 sign with control cities at some future point. The Exit 65 sign before this one, since the removal above was not due to NCDOT, at 1 mile had not been replaced and still referred to Business 311.

B. Under Construction Portion from Business to Interstate 85
Baker Road Bridge-As my last post indicated the bridge had been opened but there was no progress on removing the temporary highway to the north. Well, there has been some progress in the last month:
The pavement has been removed and digging has begun to bring the road down to grade, which has been done just to the north of the bridge. There has been substantial progress south of the bridge, where much of the grading and landscaping needed has been done:
The paved portion where the road curves continues eastbound to the Jackson Lake Road bridge.
Looking from Jackson Lake Road, most of the dirt from the former hill in the westbound lanes has been pushed up the embankment on the right and is being prepared for final landscaping. Looking eastbound toward Kersey Valley Road, it appears most of the work is complete:
Guardrails and drain covers are still needed, but most of the landscaping is done. Here is how the Kersey Valley Road bridge looks from the south:
The roadways appear graded and they have started initial paving toward I-85 along the future eastbound lanes shown on the left side of the photo in the middle. This is a better view of what progress has been made:
They've tied the new pavement on the EB I-85 ramp to the existing pavement. Landscaping though and more paving has to be completed here. The view of the I-85 bridges also shows progress in the last month:
Grading appears almost complete and the asphalt layer in the eastbound lanes continues almost to the bridges. The contractor has been closing lanes and ramps on I-85 in this area for the past 2 weeks to put new lane striping on I-85, for paving the NC 62 exit ramps, and for putting up overhead sign supports:
Whether this means the re-opening of the main I-85 lanes is imminent is not known, the NCDOT construction progress report still says this will happen in June. Work on the exit ramps continues...
The flyover ramp from I-74 East to I-85 North above looks complete, however, it doesn't appear paving has been completed on the section of the ramp from the bridge over I-85 to the flyover ramp...
Presumably, guardrails will be added when the paving project is completed.

2. '311 Bypass' I-85 to US 220
A. First Phase portion-This part of the freeway is being built at the same time by the people doing the remaining East Belt construction. The roadbed near the I-85 interchange appears mostly complete:
Most of the work in this section over the past month seems to be concentrated on the placing of a final asphalt layer on the roads that cross the future freeway. The paving and lane striping of Tuttle Road across its bridge has been finished:
Similar work has been done along Poole Road and on Cedar Square Road. The final non-highway bridge that needed construction has been completed, as can be seen in this photo from the Poole Road bridge:
As can be seen though, little or no further work on paving the freeway has occurred either to the north or south of the bridge:
Approaching Cedar Square Road, Poole Road parallels the freeway on the right. There was progress in re-doing Poole Road where it met the former alignment of Cedar Square Road, the road now curves off to the left on a new alignment. The photo of the Cedar Square Road Bridge below is taken where Poole Road now curves toward Cedar Square:
Work has been done on grading the route where the old alignment of Cedar Square was torn down. There, has not been much work on the interchange ramps, however:
Both Cedar Square Road and current US 311 from just south of the intersection below to just north of the former Cedar Square intersection have received their final coat of asphalt:
The water tower in the background is either being replaced or augmented by a new bigger water tower further south on US 311 which has a big 'Welcome to High Point' logo on it. I suppose they hope people will see it from the new freeway.

B. Phase 2
The second phase of construction runs from Spencer Road, 1/2 mile south of Cedar Square, to US 220. This is a design-build contract where work started in late 2008. The major feature of this segment will be an interchange with current US 311 in Sophia and the interchange where I-74 will tie into I-73 (US 220) near Randleman. There is little more than clearing going on at the Sophia interchange so far:
Most of the clearing seems to have been done, seen from US 311 South, the crane indicates the start of some infrastructure construction. There are more interesting things to see on US 220:
Traveling southbound, they are now putting structures in for the I-74 bridges on the right side, the first one is mostly metal and will lead to the I-74 west lanes that are being graded in the vicinity. The second structure is mostly cement and this will take traffic from I-74 east to I-73 north:
This will be a lower bridge, the ramp to I-74 west will be a flyover and go both over US 220 and the other bridge. This requires building a large mound along northbound US 220 for the ramp to the flyover, seen below from the southbound lanes:
One can barely see the top of the future ramp when traveling along in the northbound lanes:
Here's a wider view of the construction scene as viewed going northbound on US 220:
The first phase and East-Belt construction are 86% complete as of the end of March according to NCDOT, the contractors having completed over 3 1/2% of the remaining construction during the month. At this pace the route from Business 85 to Cedar Square Road could be done by the end of July. I will return sometime in May to see if this prediction is still possible.

Comments

Anonymous said…
Signs for 311/Main St in High Point were blown down in last week's tornado. It should be interesting to see what they are replaced with.
Bob Malme said…
Thanks for the information. I have revised the comment regarding the missing Exit 65 signs in light of the new information.

Popular posts from this blog

2018 Mojave Road Trip Part 2; The deadly desert highway (California State Route 127 and Nevada State Route 373)

After leaving Barstow via Old Highway 58 my next destination was in Death Valley.  To access Death Valley from rural San Bernardino County required a trek on north on Interstate 15 to California State Route 127 which becomes Nevada State Route 373 at the state line. Along I-15 I encountered the road sign oddity that is Zzyzx Road about eight miles south of Baker.   Zzyzx Road is a four mile road that used to go to the Zzyzx Mineral Springs and Health Spa.   The spa was founded in the 1940s and the owner made up the name "Zzyzx" to claim it was the last word in the English Language.  The spa has been shut down since the 1970s and is now part of a Desert Studies Center for California State University. The southern terminus of CA 127 in Baker is located at I-15 exit 246.  CA 127 is a 91 mile north/south highway which runs to the Nevada State Line in Inyo County.  CA 127 is called Death Valley Road from I-15 northward.  South of CA 127 ...

Finding the Pre-Emption Road of New York State

  The Pre-Emption Road (or rather a series of roads named Pre-Emption Road) follows a survey line called the Pre-Emption Line, drawn in the early days of the United States. The story begins with Massachusetts and New York having competing land claims to modern day Western New York State that have their roots in colonial charters granted by the British. After the Revolutionary War ended, this land became the frontier of the nation and its settlement became a priority for the new American government. During this era, there were a lot of competing land claims that needed to be settled. It was no different with the land claims between New York State and Massachusetts. On November 30, 1786, Massachusetts and New York sent representatives to Hartford, Connecticut to resolve their competing land claims. In less than three weeks, the representatives had reached a compromise. Massachusetts would receive pre-emption rights, meaning the right to sell the land after the Indian title ...

What's In a Name?: When the Roads Really Do Tell a Story

  Our tagline on the Gribblenation blog is "because every road tells a story". Some roads tell different stories than others. Along our travels, we may see historic markers that tell us a little story about the roads we travel or the places we pass by. Some historic markers are more general, as to telling us who lived where or what old trail traversed between two towns. During my travels across New York State and other states or provinces, I pass by many historic markers, some with interesting or amusing references to roads. I wanted to highlight a few of the markers I've seen along my travels around the Empire State and help tell their stories. Those stories may be as specific as explaining the tales of a tree that was used to help measure a distance of eight miles from Bath to Avoca in Steuben County, as referenced on the Eight Mile Tree historical marker above. They may also help point the way along historical roads first used centuries ago, or may help tell a local l...