Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

West Canyon Road (Snow Canyon State Park)

West Canyon Road is an approximately four-mile dirt service road located in Snow Canyon State Park.  West Canyon Road follows Snow Canyon from the Whiptail Trail to the northern State Park boundary and intersects numerous trailheads.   West Canyon Road was the original main road through Snow Canyon after it was designated as a Utah State Park in 1957 and opened to the public in 1962. Part 1; the history of West Canyon Road Snow Canyon is located in the Red Mountains north of the city of Ivins in Washington County, Utah.  Snow Canyon is one of many sandstone canyons located in the Red Mountains.  Part of the extinct Santa Clara Volcano punctured the Red Mountains via lava tubes. From approximately the year 200 to 1,250 the area around Snow Canyon was inhabited by the Ancestral Puebloans.  Mormon pioneers established Santa Clara south of Snow Canyon in 1854.  Local legend has it that the settlers discovered Snow Canyon in the 1850s while searching for m...

Indian Gulch Extension and the Indian Gulch ghost town site

Indian Gulch Extension is an approximately 6-mile-long rural highway corridor in the Sierra Nevada foothills of western Mariposa County.  Indian Gulch Extension begins at Indian Gulch Road near the namesake ghost town of Indian Gulch.  From the ghost town site Indian Gulch Extension extends southwesterly to the Merced County line where it becomes Waltz Road.   The former Gold Rush era community of Indian Gulch which was settled near Santa Cruz Mountain in 1849 and had standing structures until the early 1970s.  What is now Indian Gulch Extension was approved for construction by the Mariposa County Commissioners in 1862.  The purpose of the corridor was to provide Indian Gulch with a direct connection westward with the greater Stockton-Los Angeles Road.  The Stockton-Los Angeles Road would go onto define much of the Mariposa County and Merced County line.  Part 1; the history of Indian Gulch and Indian Gulch Extension Indian Gulch Road is named aft...

The reemergence of US Route 99 at the Ventura Freeway/Golden State Freeway interchange

During April 2023 a portion of the sign gantry on the eastbound Ventura Freeway (California State Route 134) approaching the Golden State Freeway (Interstate 5) fell.  The fallen portion of the sign gantry revealed a once covered US Route 99 shield.  The uncovered US Route 99 sign (blog cover courtesy Ian Ligget) is a 1956-63 era freeway specification US Route shield.  This blog will explore in brief how the Golden State Freeway was developed as US Route 99 and US Route 6 before becoming solely Interstate 5.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page Part 1; visiting the US Route 99 shield at the Ventura Freeway/Golden State Freeway Interchange As noted in the introduction the US Route 99 shield can be seen on the eastbound Ventura Freeway (California Sta...