Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

North Carolina Continues to Move Forward with Rail

2023 and the first half of 2024 have seen continued growth in North Carolina's passenger rail system.  From increased daily trains from Raleigh to Charlotte, federal funds for studying additional corridors, and receiving a historic grant to begin the construction of high-speed rail between Raleigh and Richmond, the last 18 months have been a flurry of activity at NCDOT's Rail Division.  And that's just the tip of the iceberg. As ridership and routes increase - the engine of North Carolina passenger rail trains will become a more common sight. (Adam Prince) Increased Passenger Train Service: On July 10, 2023, a fourth Piedmont round-trip rail service between Raleigh and Charlotte commenced.  The four Piedmont trains plus the daily Carolinian (to Washington, DC, and New York) bring the total of trains serving the two cities daily to five. The current daily Piedmont and Carolinian schedule between Charlotte and Raleigh (NCDOT) The result was over 641,000 passengers utilized pa

US Route 101 in Benbow, Garberville and Redway

The communities of Benbow, Garberville and Redway can all be found along US Route 101 within southern Humboldt County.  The former surface alignment of US Route 101 in Garberville and Redway once crossed the Garberville Bluffs along what is now Redwood Drive via a corridor constructed as part of the Redwood Highway during the 1910s.  US Route 101 through Benbow, Garberville and Redway was modernized by 1935.  US Route 101 would eventually be upgraded to freeway standards in Benbow, Garberville and Redway by extension of the Redwood Freeway during 1966-68.  As the cover photo the original grade of US Route 101 and the Redwood Highway can be seen at the Garberville Bluffs during 1934.  US Route 101 can be seen in the communities of Benbow, Garberville and Redway on the 1935 Division of Highways Map of Humboldt County .   The history of US Route 101 in Benbow, Garberville and Redway Benbow, Garberville and Redway lie on the banks of the South Fork Eel River of southern Humboldt County.  D

The Midway Palm and Pine of US Route 99

Along modern day California State Route 99 south of Avenue 11 just outside the City limits of Madera one can find the Midway Palm and Pine in the center median of the freeway.  The Midway Palm and Pine denotes the halfway point between the Mexican Border and Oregon State Line on what was US Route 99.  The Midway Palm is intended to represent Southern California whereas the Midway Pine is intended to represent Northern California.  Pictured above the Midway Palm and Pine can be seen from the northbound lanes of the California State Route 99 Freeway.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page The history of the Midway Palm and Pine The true timeframe for when the Midway Palm and Pine (originally a Deadora Cedar Tree) were planted is unknown.  In fact, the origin of the Midway Palm and Pine w