Skip to main content

I-73/I-74 Year in Review 2016

While the year ended up on a disappointing note with the news that the plan to open a new segment of I-73 north of Greensboro by the end of 2016, promised by NCDOT last spring, had been postponed, work continued quietly on all existing projects with the promise of further funding for additional work in the soon to be published NC State Transportation Improvement Plan (STIP) for 2018-2027.

I-73

NCDOT announced last spring that it planned to open the new I-73 route from PTI Airport to US 220 near the Haw River by the end of the year. In the summer it was learned there were going to be delays in opening the segment from Bryan Blvd. to NC 68, but the section between NC 68 and US 220 would open in November. Alas, in early December word came that the entire segment would not open until spring, probably May. Work on this segment, as of mid-December is 92% complete and there are segments which appear to be close to completion, as this photo from AA Forum member Strider shows:


However, there are other areas where paving has not quite started yet:

Work near the PTI Airport has recently picked up, so there's optimism the spring completion date will be met. Here's the closest view of the PTI Taxiway bridge now complete over the Future I-73 lanes as seen from Bryan Blvd:

Work is also continuing at the other end with bridge being constructed for Future I-73 over NC 68:

Further north, the work on the segment along US 220 north to NC 68 has also progressed over the past year with the project now 72% complete, as opposed to almost 60% before. However, this segment is behind schedule with an opening date now listed as early 2018. Again, there are sections, such as at the Future I-73/US 220 interchange where work is almost complete:

And other areas where grading has just started, such as the future I-73 South lanes just south of the northern end of the project at NC 68:

Meanwhile, further south in Richmond County, significant progress has been made in upgrading US 220 to interstate standards as part of the I-73/I-74 Rockingham Bypass project. The work is, as of November, now over 60% complete, as compared to 34% a year ago. The project is still behind schedule though and the completion date was pushed back a month to April 2018. Most of the work has been building the service roads paralleling the existing roadway with traffic moved onto them so that the existing US 220 lanes can be improved, as seen in this photo by J. Austin Carter:
Traffic had been moved off the northbound lanes to the service road on the left in the photo above in December. Work also has been started at building the new interchange with Haywood Cemetery Road, here's the supports for the interchange overpass being constructed, also taken by J. Austin Carter:

As for the remainder of the Bypass, the good news is that that project is no longer on hold. It was added to the 2016-2025 STIP in February with construction scheduled to take place between 2022 and 2025. The prospects for completing I-73 in NC still rest with neighboring states with NCDOT not committed to building the northern and southern most segments without commitments by VA and SC to build their proposed routes.

I-74

While no new segment of I-74 started construction in 2016, there was positive news about the expansion of existing projects and new funding for others. Besides work on the Rockingham Bypass with I-73, work continued on the first segment of the Winston-Salem Northern Beltway between Business 40/US 421 and US 158. Progress is still slow, however, with the completion percentage in the past year only going from about 15% to just over 28% by year's end. The NCDOT Project page says the project should be 50.7% complete. Still work could be seen in clearing the path for the future road as seen in these photos from J. Austin Carter, both near Business 40:

And farther north at the project's northern end near US 158:

NCDOT announced that under a change in the state's transportation budget formula, all the remaining Eastern segments of the Beltway, and one segment of the Western Section would be funded under the new STIP with work to be completed by 2024. The STIP also includes funding for bringing US 74 up to interstate standards between Rockingham and Laurinburg. Work is to start on the segment between the two bypasses first with work scheduled to start in 2022. Work to bring the Laurinburg and Maxton Bypasses up to interstates standards should start soon after, as early as 2025.

Work also continues east of I-95 on a piecemeal basis to bring US 74 up to interstate standards. Work was completed this year on an overpass taking US 74 Business traffic over US 74 near Whiteville. Now the US 74 highway is limited access from four miles before the interchange with US 76 and the speed limit has been increased to 70 MPH, this is also the case at the northern end with the 70 MPH speed limit in place over five miles from the official end of I-74 at NC 41. Work is planned at several more intersections to replace them with interchanges, including at NC 130 over the next 10 years. There has been no word, however, as to whether US 74/76 east of Whiteville will be upgraded to interstate standards. NCDOT has, however, revived engineering work on the proposed Carolina Bays Extension project to extend SC 31 to US 17 just over the SC border.

2017 promises some new miles for I-73, and perhaps a few more funded projects when the new 2018-2027 State TIP is announced in January. And there may always be surprises. As always, I will have the latest information on my I-73/I-74 pages which, as of January 1, 2017, are on an new site, MalmeRoads.net.

All the Segment pages can be reached at http://www.malmeroads.net/i7374nc/index.html


Comments

Popular posts from this blog

Former California State Route 1 over Old Pedro Mountain Road

California State Route 1 in western San Mateo County traverses the Montara Mountain spur of the Santa Cruz Mountains.  In modern times California State Route 1 passes through Montara Mountain via the Tom Lantos Tunnels and the highway is traditionally associated with Devils Slide.  Although Devils Slide carries an infamous legacy due it being prone landslides it pales in comparison to the alignment California State Route 1 carried prior to November 1937 over Old Pedro Mountain Road.   Old Pedro Mountain Road opened to traffic in 1915 and is considered one of the first major asphalted highways in California.  Old Pedro Mountain Road clambers over a grade from Montara towards Pacifica via the 922 foot high Saddle Pass.  Pictured above an overlook of Old Pedro Mountain Road facing southward towards Montara as it appears today.  Pictured below it the same view during June 1937 when it was part of the original alignment of California State Route 1.  Today Old Pedro Mountain sits abandoned a

Former US Route 101 and California State Route 1 in San Luis Obispo

Originally US Route 101 upon descending Cuesta Pass southbound entered the City of San Luis Obispo via Monterey Street.  From Monterey Street US Route 101 utilized Santa Rosa Street and Higuera Street southbound through downtown San Luis Obispo.  Upon departing downtown San Luis Obispo US Route 101 would have stayed on Higuera Street southward towards Pismo Beach and Arroyo Grande.  Notably; beginning in 1934 US Route 101 picked up California State Route 1 at the intersection of Monterey Street/Santa Rosa Street where the two would multiplex to Pismo Beach.  Pictured below is the 1 935 Division of Highways Map of San Luis Obispo County depicting the original alignments of US Route 101 and California State Route 1 in the City of San Luis Obispo.   Part 1; the history of US Route 1 and California State Route 1 in San Luis Obispo San Luis Obispo lies at the bottom of the Cuesta Pass (also known as the Cuesta Grade) which has made it favored corridor of travel for centuries.  Cuesta Pass

California State Route 232

This past month I drove the entirety of California State Route 232 in Ventura County. CA 232 is an approximately 4 miles State Highway aligned on Vineland Avenye which begins near Saticoy at CA 118 and traverses southwest to US Route 101 in Oxnard.  The alignment of CA 232 was first adopted into the State Highway System in 1933 as Legislative Route Number 154 according to CAhighways.org. CAhighways.org on LRN 154 As originally defined LRN 154 was aligned from LRN 9 (future CA 118) southwest to LRN 2/US 101 in El Rio.  This configuration of LRN 154 between CA 118/LRN 9 and US 101/LRN 2 can be seen on the 1935 California Division of Highways Map of Ventura County. 1935 Ventura County Highway Map According to CAhighways.org the route of LRN 154 was extended west from US 101/LRN 2 to US 101A/LRN 60 in 1951.  Unfortunately State Highway Maps do not show this extension due to it being extremely small. During the 1964 State Highway Renumbering LRN 154 was assigned CA 232.  Of n