When the TIGER Discretionary Grants are awarded, there are going to be a lot of unhappy people

Tonight I was curious in knowing what other projects have other state's applied for the $1.5 billion in TIGER Discretionary Funds that will be awarded next month.  My original thinking was that it was only one project per state, and it would be a neat idea to maybe research and blog about them  Bzzzztttt, was I wrong!

The USDOT received 1380, yes 1380, applications from all 50 states, plus Guam, the Virgin Islands, Puerto Rico, and the District of Columbia.  The total amount of requests total $56.5 billion.  That is nearly 38 times the amount that will be awarded!!!!  No wonder why the final decisions have been delayed.

Texas led with 125 applications - followed closely by California (117), and Florida (115).  The least amount of applications came from Hawaii with only 1. New Hampshire, South Dakota, and North Dakota only had two applications.

It appears that any organization could apply for the TIGER Grants - and that would explain why SCDOT encouraged Horry County to put in an application for upgrading SC 22 to Interstate standards a number of months ago.

The amount of money asked for in each applications was varied also. 514 of the 1380 (37.2%) applications were asking for amounts of less than $20 million.  Over 56% (785) were applications for $20-100 million in funds.  The rest, 81 applications, were from $100 billion to the maximum of $300 billion.

Applications came in for highway improvements, transit improvements, rail improvements, and other.  (Most likely pedestrian and bike projects.)

Check out the USDOT's two page summary of the TIGER Grant applications here.

I'm going to start looking into what projects applied for grant money and what they are for.

One of the first ones I did find was an application by NYSDOT for completing the final upgrades for the US 15/I-99 project.  The amount of the application was for $38 million.

Exit question: What are some of the projects being applied for in your state?  And which of them are the most pressing? So leave a comment.

Comments

Unknown said…
Adam,

I linked to this item on my Inside Lane page.

http://www.inside-lane.com/2010/01/28/blog-tiger-grant-applications-1380-requests-totaling-56-5-billion-for-only-1-5-billion-available-colorado-total-requests-1-1-billion/

Kevin Flynn
Adam said…
Kevin,

Thanks! I find it amazing how many applications were made for such few funds. It will be interesting to see what projects are awarded the grants and for how much.

If one project gets the maximum of $300 million, that's 20% of the total money available. It will be interesting to see the reactions.

Here in NC, local leaders near the I-85 Yadkin River Project are not as optimistic as they were a few months ago. And NCDOT is already trying to come up with alternative funding plans based on how much if any grant dollars they receive.
Matt Salek said…
Colorado DOT submitted 7 projects totaling $463M. Here's a list: http://milepost61.wordpress.com/2009/08/20/cdot-pursuing-7-tiger-grants/
Arnold said…
I thought the exact same thing!

Here in Ann Arbor, we applied for $22 million for a Bridge that goes over a train track in conjunction with one that goes over a residential street.

I wrote the Tiger Grant people to inform them that the train is used twice a day - between 10pm and 6am, and that the residential road is typical to many in the city that never - ever have had any discussion about putting up a bridge to avoid a stoplight.

Instead of replacing the current bridges, I asked the Tiger Group to reject the application due to the waste. Ann Arbor could put in at grade roads at a cost less than $10 million. They just don't want to.

The interesting part in my discussions with the Tiger Group is there seems to be little puclic input. Nor does there appear to be much investigation into the need / honesty of the applications.

I hope they - The Tiger Grant people - can weed out the pork and give the money to the truly needy.

www.theannarborbridgetonowhere.com
Brian said…
@Arnold:

Unfortunately, there's just no decent way to possibly make Stadium and State at-grade without significantly encroaching upon adjacent property, as the city's letter points out. This is just one of those cases where the original bridges were built to address the traffic issues of that time, development was allowed in the adjacent areas, and thus no good way to just remove the overpasses. And as one of my friends points out, construction is well under way. I admire you for wanting to speak out, though.

Popular posts from this blog

Rep. Sue Myrick's letter to Gov. Easley and Sect. Tippett published in Charlotte Observer

US. Representative Sue Myrick's (R-Charlotte) letter to North Carolina's Governor Mike Easley and NC Transportation Secretary Lyndo Tippett was published in the Friday, November 30th edition of the Charlotte Observer . Why are we delaying the completion of 1-485 in Charlotte again? I read in The Charlotte Observer how rising prices of materials are leading to the delay. Why didn't these same rising costs delay the loops in Fayetteville and Wilmington? Why are we building loops in Fayetteville and Wilmington before we complete the one in Charlotte? We were working on the one in Charlotte back when I was mayor. That was 20 years ago! ... Last I looked Charlotte was the largest city in the state. There seems to be no recognition of that fact in Raleigh. No recognition that we are at a standstill with traffic. No recognition that we have a traffic problem. Nor is there any recognition of the fact that the state DOT utterly botched up the southern leg of our yet to be completed ...

New River Gorge National Park & Preserve - Sandstone Falls

The New River, which runs through New River Gorge National Park & Preserve, is best known for its dramatic rapids and whitewater adventures.  Those features begin at one of the river's widest points: Sandstone Falls. From the Sandstone Falls Boardwalk a look at just a small part of the falls. Though the vertical drop of roughly 20 feet is less than many other well-known waterfalls in the state, the falls' expanse, where the river approaches 1500 feet wide, makes Sandstone Falls impressive.   The Boardwalk Trail leads to a better vantage point of the overall falls. It is a great spot for photography, fishing, or laying out in the sun. Access to the falls is relatively easy: from Hinton, cross the New River on Highway 20, then turn right onto CR 26 and follow New River Road to the Sandstone Falls Parking Area. The Island Loop Trail is a short detour off the Boardwalk Trail and shows a quieter side of the area. At Sandstone Falls, you will find a variety of activities fr...

I-90 in Albany, New York and the Berkshire Spur

Today's Albany Times Union has a segment in their weekly Getting There? column that explains some of the history behind how I-90 is designated in the Albany, NY area as well as the Berkshire Spur. The long and short of the article was that I-90 was originally designated on the unsigned portion of the Berkshire Spur, but as free I-90 was built, the designation was moved onto the free portion of road. Additionally, there were talks in 1999 between state and federal officials about the possibility of moving I-90 back onto the unsigned portion of the Berkshire Spur, while extending I-88 onto what we know as free I-90. There would have also had been an I-88/I-90 multiplex between Rotterdam and Albany as a result. http://www.timesunion.com/AspStories/story.asp?storyID=916307