When the TIGER Discretionary Grants are awarded, there are going to be a lot of unhappy people

Tonight I was curious in knowing what other projects have other state's applied for the $1.5 billion in TIGER Discretionary Funds that will be awarded next month.  My original thinking was that it was only one project per state, and it would be a neat idea to maybe research and blog about them  Bzzzztttt, was I wrong!

The USDOT received 1380, yes 1380, applications from all 50 states, plus Guam, the Virgin Islands, Puerto Rico, and the District of Columbia.  The total amount of requests total $56.5 billion.  That is nearly 38 times the amount that will be awarded!!!!  No wonder why the final decisions have been delayed.

Texas led with 125 applications - followed closely by California (117), and Florida (115).  The least amount of applications came from Hawaii with only 1. New Hampshire, South Dakota, and North Dakota only had two applications.

It appears that any organization could apply for the TIGER Grants - and that would explain why SCDOT encouraged Horry County to put in an application for upgrading SC 22 to Interstate standards a number of months ago.

The amount of money asked for in each applications was varied also. 514 of the 1380 (37.2%) applications were asking for amounts of less than $20 million.  Over 56% (785) were applications for $20-100 million in funds.  The rest, 81 applications, were from $100 billion to the maximum of $300 billion.

Applications came in for highway improvements, transit improvements, rail improvements, and other.  (Most likely pedestrian and bike projects.)

Check out the USDOT's two page summary of the TIGER Grant applications here.

I'm going to start looking into what projects applied for grant money and what they are for.

One of the first ones I did find was an application by NYSDOT for completing the final upgrades for the US 15/I-99 project.  The amount of the application was for $38 million.

Exit question: What are some of the projects being applied for in your state?  And which of them are the most pressing? So leave a comment.

Comments

Unknown said…
Adam,

I linked to this item on my Inside Lane page.

http://www.inside-lane.com/2010/01/28/blog-tiger-grant-applications-1380-requests-totaling-56-5-billion-for-only-1-5-billion-available-colorado-total-requests-1-1-billion/

Kevin Flynn
Adam said…
Kevin,

Thanks! I find it amazing how many applications were made for such few funds. It will be interesting to see what projects are awarded the grants and for how much.

If one project gets the maximum of $300 million, that's 20% of the total money available. It will be interesting to see the reactions.

Here in NC, local leaders near the I-85 Yadkin River Project are not as optimistic as they were a few months ago. And NCDOT is already trying to come up with alternative funding plans based on how much if any grant dollars they receive.
Matt Salek said…
Colorado DOT submitted 7 projects totaling $463M. Here's a list: http://milepost61.wordpress.com/2009/08/20/cdot-pursuing-7-tiger-grants/
Arnold said…
I thought the exact same thing!

Here in Ann Arbor, we applied for $22 million for a Bridge that goes over a train track in conjunction with one that goes over a residential street.

I wrote the Tiger Grant people to inform them that the train is used twice a day - between 10pm and 6am, and that the residential road is typical to many in the city that never - ever have had any discussion about putting up a bridge to avoid a stoplight.

Instead of replacing the current bridges, I asked the Tiger Group to reject the application due to the waste. Ann Arbor could put in at grade roads at a cost less than $10 million. They just don't want to.

The interesting part in my discussions with the Tiger Group is there seems to be little puclic input. Nor does there appear to be much investigation into the need / honesty of the applications.

I hope they - The Tiger Grant people - can weed out the pork and give the money to the truly needy.

www.theannarborbridgetonowhere.com
Brian said…
@Arnold:

Unfortunately, there's just no decent way to possibly make Stadium and State at-grade without significantly encroaching upon adjacent property, as the city's letter points out. This is just one of those cases where the original bridges were built to address the traffic issues of that time, development was allowed in the adjacent areas, and thus no good way to just remove the overpasses. And as one of my friends points out, construction is well under way. I admire you for wanting to speak out, though.

Popular posts from this blog

Paper Highways: The Unbuilt New Orleans Bypass (Proposed I-410)

  There are many examples around the United States of proposed freeway corridors in urban areas that never saw the light of day for one reason or another. They all fall somewhere in between the little-known and the infamous and from the mundane to the spectacular. One of the more obscure and interesting examples of such a project is the short-lived idea to construct a southern beltway for the New Orleans metropolitan area in the 1960s and 70s. Greater New Orleans and its surrounding area grew rapidly in the years after World War II, as suburban sprawl encroached on the historically rural downriver parishes around the city. In response to the development of the region’s Westbank and the emergence of communities in St. Charles and St. John the Baptist Parishes as viable suburban communities during this period, regional planners began to consider concepts for new infrastructure projects to serve this growing population.  The idea for a circular freeway around the southern perimeter of t

Hernando de Soto Bridge (Memphis, TN)

The newest of the bridges that span the lower Mississippi River at Memphis, the Hernando de Soto Bridge was completed in 1973 and carries Interstate 40 between downtown Memphis and West Memphis, AR. The bridge’s signature M-shaped superstructure makes it an instantly recognizable landmark in the city and one of the most visually unique bridges on the Mississippi River. As early as 1953, Memphis city planners recommended the construction of a second highway bridge across the Mississippi River to connect the city with West Memphis, AR. The Memphis & Arkansas Bridge had been completed only four years earlier a couple miles downriver from downtown, however it was expected that long-term growth in the metro area would warrant the construction of an additional bridge, the fourth crossing of the Mississippi River to be built at Memphis, in the not-too-distant future. Unlike the previous three Mississippi River bridges to be built the city, the location chosen for this bridge was about two

Memphis & Arkansas Bridge (Memphis, TN)

  Like the expansion of the railroads the previous century, the modernization of the country’s highway infrastructure in the early and mid 20th Century required the construction of new landmark bridges along the lower Mississippi River (and nation-wide for that matter) that would facilitate the expected growth in overall traffic demand in ensuing decades. While this new movement had been anticipated to some extent in the Memphis area with the design of the Harahan Bridge, neither it nor its neighbor the older Frisco Bridge were capable of accommodating the sharp rise in the popularity and demand of the automobile as a mode of cross-river transportation during the Great Depression. As was the case 30 years prior, the solution in the 1940s was to construct a new bridge in the same general location as its predecessors, only this time the bridge would be the first built exclusively for vehicle traffic. This bridge, the Memphis & Arkansas Bridge, was completed in 1949 and was the third