Skip to main content

Closing the Gap - How Interstate 77 in North Carolina and Virginia Came To Be

Interstate 77 through the Virginias and Carolinas was not an original Interstate Highway proposal.  In 1957, Interstate 77 was born as an over 400-mile southwards extension of a previously approved Cleveland to Canton, Ohio Interstate.  The new road would extend through four states before terminating at Interstate 85 near Charlotte, North Carolina.  This extension would bring an additional north-south highway connecting the industrial Midwest to the South.   During the early planning stages of Interstate 77 from the late 1950s through the mid-1960s, North Carolina and Virginia had different plans routing the Interstate that took over five years to settle.

While the new Ohio to Charlotte Interstate would follow the WV Turnpike to its terminus at US 460 near Princeton, its route through the remainder of West Virginia, Virginia, and North Carolina was uncertain.  The route south from Princeton into Virginia and to Interstate 81 near Wytheville consisted of two options.  An eastern option that would turn east along US 460 at the WV Turnpike terminus in Princeton, cross into Virginia at Glen Lyn, turn south at Pearisburg, and roughly follow Virginia Route 100 south to Interstate 81 near Dublin.  From here, Interstate 77 would continue southwest on Interstate 81 before leaving the highway near Fort Chiswell heading due south towards North Carolina.

The Western Route basically took Interstate 77 directly south into Virginia near Bluefield, following US 21 and 52 past Bastain, Bland, before meeting Interstate 81 in Wytheville.  77 then would run east along Interstate 81 North to a point near Fort Chiswell before turning south towards North Carolina.

Virginia Map showing possible alignments for Interstate 77.  There was also an option to route Interstate 64 further south through Lynchburg. (1)

South of Interstate 81, both options would head south to Woodlawn near Hillsville.  Here, the western alignment would bear to the southwest towards Pipers Gap, Galax, crossing into North Carolina near Low Gap.  

The Eastern Option continued the Interstate south paralleling US 52 to Fancy Gap and descending the Blue Ridge to the state line at a point northwest of Mount Airy, NC.

In late 1960, the Virginia Department of Highways selected the western options for both segments north and south of Interstate 81.

When the Canton-to-North Carolina Interstate was approved in 1957, a "tentative" (2) routing for the highway had its southern terminus northeast of Charlotte near Salisbury.   This led to battles between different factions that wanted the new Interstate closer to their cities or even extend it. 

"Tentative" routing of I-77
terminating northeast of  
Charlotte. (5) 
Early battles were over where Interstate 77 would be routed and even where it would connect to the already approved Interstate 85.  Groups from Charlotte, Greensboro, Winston-Salem, and High Point all wished to have the new Interstate benefit their communities.  Greensboro and High Point lobbied to have the road further east between Winston-Salem and Greensboro and connect to Interstate 85 near High Point. (2)  The Triad cities believed that this change would bring the most benefit, and offer the best connections to the existing highway system. (2)

Another group wished to have the highway follow US 52 from Mount Airy to Lexington.  Charlotte interests argued that a route that ran due south would be the most direct and cost-effective.  A wild card was that Greensboro and other Triad communities also lobbied for the new Interstate to continue further to the south and east to Wilmington. (3)
 
Highway officials, led by Director of Highways Bill Babcock, quickly stopped any extension talk by reminding boosters that the highway must remain within the 431-mile allocation between four states, and it must be routed to Charlotte. (3)

With this in mind, North Carolina would narrow Interstate 77's future route through Elkin and Statesville.  And in August 1959, the State Highway Commission approved Interstate 77's route from Interstate 85 west of the Statesville Road Interchange in Charlotte northwards to a point east of Elkin.  The route north of Elkin to the Virginia state line remained under study. (4)

Interstate 77's routing North of Elkin would be in doubt for over five years.

How Interstate 77 would run North of Elkin and into Virginia would be the highway's sticking point for the next five years.

The gap between Virginia's I-77 
and North Carolina's I-77 would 
take over five years to resolve. (9)  
North of Elkin, North Carolina considered three options.   Each option would carry the Interstate over the Blue Ridge at different locations.  The first would parallel US 21 as much as possible and traverse the mountains at Roaring Gap.  A second option would continue north Elkin towards Dobson before turning northwest towards Low Gap.  This route would cross into Virginia near NC 89 and the Blue Ridge Parkway.  The final easternmost option would parallel US 601 west of Dobson and continue northwards and climb the mountain in Virginia to Fancy Gap. (6)  

The Roaring Gap option would be eliminated - leaving the western Low Gap route vs. the eastern route towards Fancy Gap. (7)   Again, local community and business leaders lobbied for their preferred route.   Leaders from Allegany, Ashe, and Watauga Counties argued that the Low Gap route would serve the most local traffic and provide economic benefits to those counties.   Leaders from Mount Airy and the Triad preferred the eastern route, arguing that it was the most direct and gave better north-south access to greater amounts of the population. (7)

In 1960, the North Carolina Highway Commission approved the eastern route that would take Interstate 77 closer to Mount Airy and onto Fancy Gap.   As a compromise, the Commission agreed to a study of an East-West Corridor that would connect the western communities directly to the Interstate. (8)  This would result in the upgraded US 421 highway from Boone to Interstate 77 and eastwards to Winston-Salem.

Going into 1961, North Carolina had their I-77 route set, and Virginia did as well.  One sticking point - a twelve-mile gap on where the Interstate would cross the state line.

Virginia looked at the costs.  The cost to complete the western Low Gap route in Virginia was estimated to be $9 million less than the eastern Fancy Gap route.  Conversely, the western Low Gap route for North Carolina was about $4.5 million and 2.3 miles longer than their approved eastern route. (9)

The impasse would continue for another five years.  Meanwhile, North Carolina had begun to construct sections of the Interstate south of Elkin.   They would also apply for and receive approval for a two-mile spur south of I-77's terminus at I-85 into Charlotte.  Later in 1968, Interstate 77 received an authorized extension to Columbia, South Carolina. (10)

Finally, in 1965, Virginia agreed to follow the eastern route.  Though it did cost more, officials from both states agreed that the eastern route would give "superior traffic service." (11)  North Carolina would also authorize a request for federal funding to build a spur from Interstate 77 to Mount Airy.  This spur would eventually become part of Interstate 74.  Over the next decade, North Carolina would continue constructing Interstate 77 northwards towards the state line.  

By 1976, I-77 was complete from Charlotte northward to Dobson.   Just in time for the July 4th holiday on July 1, 1977, over 30 miles of Interstate 77 was opened between the two states stretching from Dobson across the state line and up the Blue Ridge to Fancy Gap. (12)  

Over the next eighteen months, Virginia would complete Interstate 77 northwards to Interstate 81 in Fort Chiswell - finally completing the connection in 1978. (13)

Interstate 77 would be completed to Interstate 20 in Columbia by 1988.  Finally, in 1995, Interstate 77 would be completed to Interstate 26 southeast of Columbia, ending over three decades of construction.

Sources & Links:
  1. Johnson, Bill. "Ambitious Va. Highway Program Aims For Vast Network By 1975." Newport News Daily Press. 14A.  December 11, 1960.
  2. "New Highway Route Battle On Today." The Charlotte News. 1B.  January 6, 1958.
  3.  Jenkins, Jay. "Highway Chief Says Charlotte Will Get Ohio Superhighway." Charlotte Observer. 4A.  November 27, 1957.
  4. Gardner, John. "Superhighway's Route Approved." Charlotte Observer. 1B. August 5, 1959.
  5. American Automobile Association. "National System of Interstate and Defense Highways as of June, 1958."
  6. Munn, Porter. "Speakers Give Views On Super-Road Route." Charlotte Observer. 1B. January 7, 1958.
  7. "Decision Delayed On Interstate 77." The Charlotte News. 5A. August 26, 1960.
  8. "Fancy Gap Makes Case." The High Point Enterprise. 4A. October 7, 1960.
  9. "2 States Can't Make Road's Ends Meet." Charlotte Observer. 11C. February 24, 1961.
  10. Roberson, Michael. "I-77" NCRoads.com Annex.
  11. Shires, Michael A. "Agreement Finally Reached On I-77 Routing." The Charlotte News. 4B. May 10, 1965.
  12. "Fancy Gap of I-77 Opens." Danville Register. 3A. July 2, 1977.
  13. Roberson, Michael. "I-77." Virginia Highways Page.


Comments

Popular posts from this blog

Abandoned US Route 40 in the Truckee River Canyon

Within the Truckee River Canyon in the Sierra Nevada range numerous abandoned portions of US Route 40 can be found alongside modern Interstate 80.   This segment of highway was opened during 1926 as a bypass of the Dog Valley Grade which carried the early North Lincoln Highway and Victory Highway. The corridor of the Truckee River Canyon State Highway would be assigned as US Route 40 when the US Route System was commissioned during November 1926. During 1958 the segment of Interstate 80 between Boca, California and the Nevada state line was complete. When Interstate 80 opened east of Boca numerous obsolete portions of US Route 40 were abandoned. Some of these abandoned segments have been incorporated into the Tahoe-Pyramid Trail.  Part 1; the history of US Route 40 in the Truckee River Canyon The Truckee River Canyon for centuries has been an established corridor of travel known to native tribes crossing the Sierra Nevada range.  The first documented wagon crossi...

Former US Route 50 and the Pioneer Route Lincoln Highway on Johnson's Pass Road

Johnson's Pass Road is one of the oldest highway corridors in California.  Johnson's Pass was part of the Lake Tahoe Wagon Road as it was completed during 1856 over the Sierra Nevada.  The pass would later be incorporated into the Pioneer Branch of the Lincoln Highway in 1913 and US Route 50 in 1926.  Johnson's Pass Road would be bypassed by a new alignment of US Route 50 over Echo Summit in 1938.  A replacement of the Meyers Grade east of Johnson's Pass would be opened to traffic in 1947.   Johnson's Pass Road remains accessible to traffic and is still signed by the Lincoln Highway Association.  Pictured as the blog cover is the view from the top of Johnson's Pass Road overlooking modern US Route 50 and Lake Tahoe.   Part 1; the history of Johnson's Pass Much of the history of what become the Lake Tahoe Wagon Road is discussed in the  September 1950 California Highways & Public Works  during its Centennial Edition.  The or...

Former California State Route 41 past Bates Station

When California State Route 41 was commissioned during August 1934 it was aligned along the then existing Fresno-Yosemite Road north of the San Joaquin River.  Within the Sierra Nevada foothills of Madera County, the original highway alignment ran past Bates Station via what is now Madera County Road 209, part of eastern Road 406 and Road 207.   Bates Station was a stage station plotted during the early 1880s at what was the intersection of the Coarsegold Road and Stockton-Los Angeles Road.   The modern alignment bypassing Bates Station to the east would be reopened to traffic during late 1939.   Part 1; the history of California State Route 41 past Bates Station Bates Station was featured as one of the many 1875-1899 Madera County era towns in the May 21, 1968, Madera Tribune .  Post Office Service at Bates Station is noted to have been established on November 23, 1883 and ran continuously until October 31, 1903.  The postal name was sourced...