I-74 Construction November Road Trip Report

So I wouldn't stew over Duke's loss to UNC, or the lastest Canes loss, and with the forecast for sunny skies and a high of 74, I decided Sunday morning would be a good time to check out I-74 construction progress from High Point to Randleman, plus some extra points of interest.

Construction Progress since early October-
My first stop was Baker Road. It appears the underlying structure for the bridge is complete and all that is needed is for cement to be poured:
After the bridge is completed, the existing road will have to be widened and tied to the bridge, but that should not take long to do. Another sign of progress is the excavating of the freeway:
Further toward Baker Road, so that the existing temporary road can quickly be demolished once the bridge is completed. Another sign of progress can be seen in the distance, the first overhead sign gantry to be put up, this for the Business 85 exit (My y I-74 page will have a better photo).

Jackson Lake Bridge-
There's more work to be done here. While the eastbound lanes look almost ready, there remains much to be excavated along the westbound lanes:
There is still some utility work going on in this area and completion of the grading of the road may have to wait to be completed. There's much more progress seen when looking the other direction toward Kersey Valley Road:
The nearly completed roadbed continues up past the Kersey Valley Road bridge, where again, there still remains work to be done:
As you see, there's much excavation still needed to be done, but most has been deposited along a slope next to the eastbound lanes, which is now being seeded:
They are, however, starting to grade the rest of the roadbed from before the I-85 interchange back toward the bridge:
This is a view of the I-85 interchange bridges from the cut-off end of Dresden Road:
Most of the work on the flyover ramp from I-74 East to I-85 North is complete, you'll notice there's not much change from earlier images:
Progress, however, can be seen just south of the bridge where the pieces of support structures for overhead signs has been placed on the original northbound I-85 lanes now being detoured:
As for the flyover itself, there's still some work to do, with connection to the roadway and the construction of walls still needed to be finished:
The metal containers are on the future I-85 on-ramp to I-74 East. There are some signs of near completion not much further down the road, with gurdrail being installed. Such as can be seen in this photo from the Tuttle Road Bridge, also notice the grass medians:
Also close to completion is the Cedar Square Road bridge and new connection to US 311. The view going west on Cedar Square shows only minor work is needed to tie the existing road in to the new one:
On the opposite side the connection to the bridge is complete and traffic signals have been installed and turned on in yellow flashing mode:
The remainder of work needed here is to remove the existing Cedar Square roadway and excavate and grade the future freeway road surface once the new bridge is open:
Notice the recent layer of asphalt on the westbound lanes next to Poole Road. The left hand side is the beginning of the exit ramp, which can't be completed until the existing road is gone.

They are also making quick progress along US 220 on the next segment of construction, including the first piers for the flyover ramps:
And further clearing of the land for the interchange and I-74 freeway heading west:
I drove further south to see the progress of the new rest areas built on I-73/74 in Seagrove. According to the last Board of Transportation meeting minutes. These rest areas are suppose to open on January 2. There seems to be more progress on the northbound rest area than the south. Going south you are still restricted to one lane. The rest area building is behind trees up a hill, so I could not get a photo. But here's the view approaching the southbound off-ramp:
Sorry for the sun glare. The northbound rest area looks almost ready. All lanes are open going by northbound, here ia view with the rest area in the distance:
Here's the best image I could get of the building:
This building is closer to the highway. I should get better photos when it's open and I'm not going by at 70 mph.

Part of the reason for taking the trip was that I had heard from several contacts that work had been nearly completed in several areas, and maybe the route could open before the end of the year. From my observations and the photos there was some confirmation that parts are near completion, but as you saw, there is still much work needed in other places. Thus my optimistic guess is, if the winter is fairly dry, that the I-74 freeway from Business 85 to Cedar Square Road could open by late spring. Which means another visit to observe progress in December or January.

Comments

Anonymous said…
boy, they are surely building the flyover ramps quicker at the I-73 and I-74 interchange.. (it was nothing when i last went through 2 months ago).

I'm excited about how the I-73/I-74 projects have been going.
digger derricks said…
digger derricks I agree I go that way on the way to work, and they might as well not even be there!

Popular posts from this blog

Memphis & Arkansas Bridge (Memphis, TN)

  Like the expansion of the railroads the previous century, the modernization of the country’s highway infrastructure in the early and mid 20th Century required the construction of new landmark bridges along the lower Mississippi River (and nation-wide for that matter) that would facilitate the expected growth in overall traffic demand in ensuing decades. While this new movement had been anticipated to some extent in the Memphis area with the design of the Harahan Bridge, neither it nor its neighbor the older Frisco Bridge were capable of accommodating the sharp rise in the popularity and demand of the automobile as a mode of cross-river transportation during the Great Depression. As was the case 30 years prior, the solution in the 1940s was to construct a new bridge in the same general location as its predecessors, only this time the bridge would be the first built exclusively for vehicle traffic. This bridge, the Memphis & Arkansas Bridge, was completed in 1949 and was the third

Old River Lock & Control Structure (Lettsworth, LA)

  The Old River Control Structure (ORCS) and its connecting satellite facilities combine to form one of the most impressive flood control complexes in North America. Located along the west bank of the Mississippi River near the confluence with the Red River and Atchafalaya River nearby, this structure system was fundamentally made possible by the Flood Control Act of 1928 that was passed by the United States Congress in the aftermath of the Great Mississippi River Flood of 1927 however a second, less obvious motivation influenced the construction here. The Mississippi River’s channel has gradually elongated and meandered in the area over the centuries, creating new oxbows and sandbars that made navigation of the river challenging and time-consuming through the steamboat era of the 1800s. This treacherous area of the river known as “Turnbull’s Bend” was where the mouth of the Red River was located that the upriver end of the bend and the Atchafalaya River, then effectively an outflow

California State Route 203 the proposed Minaret Summit Highway

California State Route 203 is an approximately nine-mile State Highway located near Mammoth Lakes in the Sierra Nevada Mountains of Mono County.  California State Route 203 as presently configured begins at US Route 395, passes through Mammoth Lakes and terminates at the Madera County line at Minaret Summit.  What is now California State Route 203 was added to the State Highway System in 1933 as Legislative Route Number 112.  The original Mammoth Lakes State Highway ended at Lake Mary near the site of Old Mammoth and was renumbered to California State Route 203 in 1964.  The modern alignment of the highway to Minaret Summit was adopted during 1967.   The corridor of Minaret Summit and Mammoth Pass have been subject to numerous proposed Trans-Sierra Highways.  The first corridor was proposed over Mammoth Pass following a Southern Pacific Railroad survey in 1901.  In 1931 a corridor between the Minarets Wilderness and High Sierra Peaks Wilderness was reserved by the Forest Service for po