Skip to main content

I-74 Construction November Road Trip Report

So I wouldn't stew over Duke's loss to UNC, or the lastest Canes loss, and with the forecast for sunny skies and a high of 74, I decided Sunday morning would be a good time to check out I-74 construction progress from High Point to Randleman, plus some extra points of interest.

Construction Progress since early October-
My first stop was Baker Road. It appears the underlying structure for the bridge is complete and all that is needed is for cement to be poured:
After the bridge is completed, the existing road will have to be widened and tied to the bridge, but that should not take long to do. Another sign of progress is the excavating of the freeway:
Further toward Baker Road, so that the existing temporary road can quickly be demolished once the bridge is completed. Another sign of progress can be seen in the distance, the first overhead sign gantry to be put up, this for the Business 85 exit (My y I-74 page will have a better photo).

Jackson Lake Bridge-
There's more work to be done here. While the eastbound lanes look almost ready, there remains much to be excavated along the westbound lanes:
There is still some utility work going on in this area and completion of the grading of the road may have to wait to be completed. There's much more progress seen when looking the other direction toward Kersey Valley Road:
The nearly completed roadbed continues up past the Kersey Valley Road bridge, where again, there still remains work to be done:
As you see, there's much excavation still needed to be done, but most has been deposited along a slope next to the eastbound lanes, which is now being seeded:
They are, however, starting to grade the rest of the roadbed from before the I-85 interchange back toward the bridge:
This is a view of the I-85 interchange bridges from the cut-off end of Dresden Road:
Most of the work on the flyover ramp from I-74 East to I-85 North is complete, you'll notice there's not much change from earlier images:
Progress, however, can be seen just south of the bridge where the pieces of support structures for overhead signs has been placed on the original northbound I-85 lanes now being detoured:
As for the flyover itself, there's still some work to do, with connection to the roadway and the construction of walls still needed to be finished:
The metal containers are on the future I-85 on-ramp to I-74 East. There are some signs of near completion not much further down the road, with gurdrail being installed. Such as can be seen in this photo from the Tuttle Road Bridge, also notice the grass medians:
Also close to completion is the Cedar Square Road bridge and new connection to US 311. The view going west on Cedar Square shows only minor work is needed to tie the existing road in to the new one:
On the opposite side the connection to the bridge is complete and traffic signals have been installed and turned on in yellow flashing mode:
The remainder of work needed here is to remove the existing Cedar Square roadway and excavate and grade the future freeway road surface once the new bridge is open:
Notice the recent layer of asphalt on the westbound lanes next to Poole Road. The left hand side is the beginning of the exit ramp, which can't be completed until the existing road is gone.

They are also making quick progress along US 220 on the next segment of construction, including the first piers for the flyover ramps:
And further clearing of the land for the interchange and I-74 freeway heading west:
I drove further south to see the progress of the new rest areas built on I-73/74 in Seagrove. According to the last Board of Transportation meeting minutes. These rest areas are suppose to open on January 2. There seems to be more progress on the northbound rest area than the south. Going south you are still restricted to one lane. The rest area building is behind trees up a hill, so I could not get a photo. But here's the view approaching the southbound off-ramp:
Sorry for the sun glare. The northbound rest area looks almost ready. All lanes are open going by northbound, here ia view with the rest area in the distance:
Here's the best image I could get of the building:
This building is closer to the highway. I should get better photos when it's open and I'm not going by at 70 mph.

Part of the reason for taking the trip was that I had heard from several contacts that work had been nearly completed in several areas, and maybe the route could open before the end of the year. From my observations and the photos there was some confirmation that parts are near completion, but as you saw, there is still much work needed in other places. Thus my optimistic guess is, if the winter is fairly dry, that the I-74 freeway from Business 85 to Cedar Square Road could open by late spring. Which means another visit to observe progress in December or January.

Comments

Anonymous said…
boy, they are surely building the flyover ramps quicker at the I-73 and I-74 interchange.. (it was nothing when i last went through 2 months ago).

I'm excited about how the I-73/I-74 projects have been going.
digger derricks said…
digger derricks I agree I go that way on the way to work, and they might as well not even be there!

Popular posts from this blog

I-40 rockslide uncovers old debates on highway

The Asheville Citizen-Times continues to do a great job covering all the angles of the Interstate 40 Haywood County rock slide. An article in Sunday's edition provides a strong historical perspective on how the Pigeon River routing of Interstate 40 came about. And perhaps most strikingly, in an article that ran just prior to the highway's opening in the fall of 1968, how engineers from both Tennessee and North Carolina warned "...that slides would probably be a major problem along the route for many years." On February 12, 1969, not long after the Interstate opened, the first rock slide that would close I-40 occurred. Like many other Interstates within North Carolina, Interstate 40 through the mountains has a history prior to formation of the Interstate Highway System and was also a heated political battle between local communities. The discussion for a road that would eventually become Interstate 40 dates back to the 1940's as the idea for interregional high

Interstate 210 the Foothill Freeway

The combined Interstate 210/California State Route 210 corridor of the Foothill Freeway is approximately 85.31-miles.  The Interstate 210/California State Route 210 corridor begins at Interstate 5 at the northern outskirts of Los Angeles and travels east to Interstate 10 in Redlands of San Bernardino County.  Interstate 210 is presently signed on the 44.9-mile segment of the Foothill Freeway between Interstate 5 and California State Route 57.  California State Route 210 makes up the remaining 40.41 miles of the Foothill Freeway east to Interstate 10.  Interstate 210 is still classified by the Federal Highway Administration as existing on what is now signed as California State Route 57 from San Dimas south to Interstate 10.  The focus of this blog will mostly be on the history of Interstate 210 segment of the Foothill Freeway.   Part 1; the history of Interstate 210 and California State Route 210 Interstate 210 (I-210) was approved as a chargeable Interstate during September of

Former California State Route 41 past Bates Station

When California State Route 41 was commissioned during August 1934 it was aligned along the then existing Fresno-Yosemite Road north of the San Joaquin River.  Within the Sierra Nevada foothills of Madera County, the original highway alignment ran past Bates Station via what is now Madera County Road 209, part of eastern Road 406 and Road 207.   Bates Station was a stage station plotted during the early 1880s at what was the intersection of the Coarsegold Road and Stockton-Los Angeles Road.   The modern alignment bypassing Bates Station to the east would be reopened to traffic during late 1939.   Part 1; the history of California State Route 41 past Bates Station Bates Station was featured as one of the many 1875-1899 Madera County era towns in the May 21, 1968, Madera Tribune .  Post Office Service at Bates Station is noted to have been established on November 23, 1883 and ran continuously until October 31, 1903.  The postal name was sourced from Bates Station owner/operator George Ba