I-74 Construction November Road Trip Report

So I wouldn't stew over Duke's loss to UNC, or the lastest Canes loss, and with the forecast for sunny skies and a high of 74, I decided Sunday morning would be a good time to check out I-74 construction progress from High Point to Randleman, plus some extra points of interest.

Construction Progress since early October-
My first stop was Baker Road. It appears the underlying structure for the bridge is complete and all that is needed is for cement to be poured:
After the bridge is completed, the existing road will have to be widened and tied to the bridge, but that should not take long to do. Another sign of progress is the excavating of the freeway:
Further toward Baker Road, so that the existing temporary road can quickly be demolished once the bridge is completed. Another sign of progress can be seen in the distance, the first overhead sign gantry to be put up, this for the Business 85 exit (My y I-74 page will have a better photo).

Jackson Lake Bridge-
There's more work to be done here. While the eastbound lanes look almost ready, there remains much to be excavated along the westbound lanes:
There is still some utility work going on in this area and completion of the grading of the road may have to wait to be completed. There's much more progress seen when looking the other direction toward Kersey Valley Road:
The nearly completed roadbed continues up past the Kersey Valley Road bridge, where again, there still remains work to be done:
As you see, there's much excavation still needed to be done, but most has been deposited along a slope next to the eastbound lanes, which is now being seeded:
They are, however, starting to grade the rest of the roadbed from before the I-85 interchange back toward the bridge:
This is a view of the I-85 interchange bridges from the cut-off end of Dresden Road:
Most of the work on the flyover ramp from I-74 East to I-85 North is complete, you'll notice there's not much change from earlier images:
Progress, however, can be seen just south of the bridge where the pieces of support structures for overhead signs has been placed on the original northbound I-85 lanes now being detoured:
As for the flyover itself, there's still some work to do, with connection to the roadway and the construction of walls still needed to be finished:
The metal containers are on the future I-85 on-ramp to I-74 East. There are some signs of near completion not much further down the road, with gurdrail being installed. Such as can be seen in this photo from the Tuttle Road Bridge, also notice the grass medians:
Also close to completion is the Cedar Square Road bridge and new connection to US 311. The view going west on Cedar Square shows only minor work is needed to tie the existing road in to the new one:
On the opposite side the connection to the bridge is complete and traffic signals have been installed and turned on in yellow flashing mode:
The remainder of work needed here is to remove the existing Cedar Square roadway and excavate and grade the future freeway road surface once the new bridge is open:
Notice the recent layer of asphalt on the westbound lanes next to Poole Road. The left hand side is the beginning of the exit ramp, which can't be completed until the existing road is gone.

They are also making quick progress along US 220 on the next segment of construction, including the first piers for the flyover ramps:
And further clearing of the land for the interchange and I-74 freeway heading west:
I drove further south to see the progress of the new rest areas built on I-73/74 in Seagrove. According to the last Board of Transportation meeting minutes. These rest areas are suppose to open on January 2. There seems to be more progress on the northbound rest area than the south. Going south you are still restricted to one lane. The rest area building is behind trees up a hill, so I could not get a photo. But here's the view approaching the southbound off-ramp:
Sorry for the sun glare. The northbound rest area looks almost ready. All lanes are open going by northbound, here ia view with the rest area in the distance:
Here's the best image I could get of the building:
This building is closer to the highway. I should get better photos when it's open and I'm not going by at 70 mph.

Part of the reason for taking the trip was that I had heard from several contacts that work had been nearly completed in several areas, and maybe the route could open before the end of the year. From my observations and the photos there was some confirmation that parts are near completion, but as you saw, there is still much work needed in other places. Thus my optimistic guess is, if the winter is fairly dry, that the I-74 freeway from Business 85 to Cedar Square Road could open by late spring. Which means another visit to observe progress in December or January.

Comments

Anonymous said…
boy, they are surely building the flyover ramps quicker at the I-73 and I-74 interchange.. (it was nothing when i last went through 2 months ago).

I'm excited about how the I-73/I-74 projects have been going.
digger derricks said…
digger derricks I agree I go that way on the way to work, and they might as well not even be there!

Popular posts from this blog

Paper Highways: The Unbuilt New Orleans Bypass (Proposed I-410)

  There are many examples around the United States of proposed freeway corridors in urban areas that never saw the light of day for one reason or another. They all fall somewhere in between the little-known and the infamous and from the mundane to the spectacular. One of the more obscure and interesting examples of such a project is the short-lived idea to construct a southern beltway for the New Orleans metropolitan area in the 1960s and 70s. Greater New Orleans and its surrounding area grew rapidly in the years after World War II, as suburban sprawl encroached on the historically rural downriver parishes around the city. In response to the development of the region’s Westbank and the emergence of communities in St. Charles and St. John the Baptist Parishes as viable suburban communities during this period, regional planners began to consider concepts for new infrastructure projects to serve this growing population.  The idea for a circular freeway around the southern perimeter of t

Hernando de Soto Bridge (Memphis, TN)

The newest of the bridges that span the lower Mississippi River at Memphis, the Hernando de Soto Bridge was completed in 1973 and carries Interstate 40 between downtown Memphis and West Memphis, AR. The bridge’s signature M-shaped superstructure makes it an instantly recognizable landmark in the city and one of the most visually unique bridges on the Mississippi River. As early as 1953, Memphis city planners recommended the construction of a second highway bridge across the Mississippi River to connect the city with West Memphis, AR. The Memphis & Arkansas Bridge had been completed only four years earlier a couple miles downriver from downtown, however it was expected that long-term growth in the metro area would warrant the construction of an additional bridge, the fourth crossing of the Mississippi River to be built at Memphis, in the not-too-distant future. Unlike the previous three Mississippi River bridges to be built the city, the location chosen for this bridge was about two

Huey P. Long Bridge (New Orleans, LA)

Located on the lower Mississippi River a few miles west of New Orleans, the Huey P. Long Bridge is an enormous steel truss bridge that carries both road and rail traffic on an old-time structure that is a fascinating example of a bridge that has evolved in recent years to meet the traffic and safety demands of modern times. While officially located in suburban Jefferson Parish near the unincorporated community of Bridge City, this bridge’s location is most often associated with New Orleans, given that it’s the largest and most recognizable incorporated population center in the nearby vicinity. For this reason, this blog article considers the bridge’s location to be in New Orleans, even though this isn’t 100% geographically correct. Completed in 1935 as the first bridge across the Mississippi River in Louisiana and the first to be built in the New Orleans area, this bridge is one of two bridges on the Mississippi named for Huey P. Long, a Louisiana politician who served as the 40th Gove