Skip to main content

Perdue offers I-485 financing plan, but many questions need to be answered first

Earlier today, Governor Perdue announced her plan to complete the Interstate 485 loop in the next five years. The plan is something called a design-build-finance plan, and it has yet to be used within North Carolina. However, there are a number of hurdles and loopholes within the plan

The term 'design-build' is familiar within North Carolina transportation projects. Design-build projects are where the builder also designs the overall project- often while the project is ongoing. One of North Carolina's first design-build projects was the Interstate 85 widening between miles 40-48.

'Design-build-finance' is where the contractor pays for some or all of the construction and then gets reimbursed by the state within a specified period of time. This method has been used elsewhere in the country including an Interstate 69 reconstruction project in Michigan.

The projected cost to complete the remaining five miles of I-485 is now roughly $340 million.

Under this plan, construction for I-485 will start next year and be completed by 2015. Plus, the governor's office emphasizes that money will not come from or delay other projects.

Sounds too good to be true right? The contractor pays for some of the construction, gets paid back by the state, no other projects get delayed.

Well, I need that Lee Corso photo again...because "Not so fast, my friend!"

First, the financing method. The contractor would pay $50 million of the $340 million to construct the highway. Well, first you have to find a construction firm that has $50 million in cash to finance the highway. And with troubles NCDOT has had with various construction companies over the past decade, that's not a guarantee.

Adam Froehlig, in a post to a national transportation forum, notes that this approach was tried for Minnesota's Crosstown Commons project but no construction firm placed a bid.

The $50 million that the construction company puts down for the highway would be paid back by the state over a 10 year period. Questions come from that too. What will the interest rate be...will the money owed to the construction company, somewhere between $5-6 million a year, impact financing other projects? With the state and the DOT in the red, will the state be able to pay it back over that period?

If the contractor is only paying $50 million or 14.7% of the costs, where is the other money coming from? The Governor's office says that no other project will be delayed. Well, according to the Charlotte Observer, the DOT's chief financial officer, Mark L. Foster, admits that the DOT is 'prioritizing' projects statewide, including I-485. If this is the case, then aren't other projects going to be delayed? Plus, when the missing five miles cost only $220 to construct - the state said they had no money to complete it. Now, they need to come up with $290 million - that's $70 million more than the original estimated cost - and suddenly NCDOT has the money.

The highway that most likely will be delayed is Interstate 295 in Fayetteville, which has the whipping boy for every other city in the state who has seen delays in their planned freeway loops.

Personally, I'd like to see where this $290 million will come from. Will the controversial equity formula be repealed? Will they try to sneak in tolls? Something just doesn't add up here.

There are other hurdles for the highway - specifically environmental concerns. Charlotte has had a growing ozone (ground level) issue and has been under the careful eye of the US Environmental Protection Agency. In fact, highway funding for Charlotte has been threatened to be cutoff if the metro area didn't improve air quality. Groups like the Southern Environmental Law Center will be certain to keep a close eye on this process.

Now what if this works?

Well, as the economy improves, more construction companies will be able to assist in financing similar projects. This could possibly speed up delayed projects and also eliminate future projects becoming toll roads.

So there could be a new opportunity for the future of North Carolina highways. However, this is a big test, and a lot of interested parties will be keeping their eye on how the final five miles of Interstate 485 eventually gets built. There is a lot riding on this project - not only politically for Governor Perdue - but on how other highway projects in North Carolina are built short and long term. It will be an interesting few months and years to see how this all unfolds.

Story Links:
I-485 plan: Tap builder cash ---Charlotte Observer
Gov. says work to finish I-485 will start in 2010 ---WBTV-TV
Governor says I-485 will be completed in five years ---WCNC-TV
Perdue unveils plan to complete Interstate 485 ---News14Carolina

Comments

This comment has been removed by a blog administrator.
Anonymous said…
This comment has been removed by a blog administrator.

Popular posts from this blog

Interstate 40's Tumultuous Ride Through the Pigeon River Gorge

In the nearly 60 years Interstate 40 has been open to traffic through the Pigeon River Gorge in the mountains of Western North Carolina, it has been troubled by frequent rockslides and damaging flooding, which has seen the over 30-mile stretch through North Carolina and Tennessee closed for months at a time. Most recently, excessive rainfall from Hurricane Helene in September 2024 saw sections of Interstate 40 wash away into a raging Pigeon River. While the physical troubles of Interstate 40 are well known, how I-40 came to be through the area is a tale of its own. Interstate 40 West through Haywood County near mile marker 10. I-40's route through the Pigeon River Gorge dates to local political squabbles in the 1940s and a state highway law written in 1921. A small note appeared in the July 28, 1945, Asheville Times. It read that the North Carolina State Highway Commission had authorized a feasibility study of a "...water-level road down [the] Pigeon River to the Tennessee l...

Ghost Town Tuesday; Mannfield, FL and the stairway to Hell

Back in 2015 I went searching the Lecanto Sand Hills for the original Citrus County Seat known as Mannfield.  Unlike Centrailia in Hernando County and Fivay in Pasco County I did find something worth seeing. Mannfield is located in the Lecanto Sand Hill section of Withlacoochee State Forest somewhat east of the intersection of Citrus County Route 491 and Mansfield Road. Mannfield was named after Austin Mann and founded in Hernando County in 1884 before Citrus County Split away.  In 1887 Citrus County was split from northern Hernando County while Pasco County was spun off to the south.  Mannfield was selected as the new Citrus County seat due to it being near the county geographic center.  Reportedly Mannfield had as many as 250 people when it was the County Seat.  The town included various businesses one might include at the time, even a sawmill which was common for the area.  In 1891 Citrus County voted to move it's seat to Inverness which set the s...

The mystery of Hawaii Route 144 and temporary Hawaii Route 11

The 1959 Gousha Road map of Hawaii features two largely unknown references in the form of Hawaii Route 144 and Temporary Hawaii Route 11.  Both corridors are shown running from the boundary of Hawaii Volcanoes National Park east to Glenwood via Volcano Village.  At the time Hawaii Route 11 was using the so-called "Volcano Road" which was constructed as a modernization of Mamalahoa Highway during 1927-1928.  This blog will examine the two map references and will attempt to determine what they might indicate.  The mystery of Hawaii Route 144 and Temporary Hawaii Route 11 Hawaii Route 11 is part of Mamalahoa Highway (the Hawaii Belt Road) and is the longest Hawaiian State Route at 121.97 miles.  The highway begins at the mutual junction of Hawaii Route 19 and Hawaii Route 190 in Kailua-Kona.  From Kailua-Kona the routing of Hawaii Route 11 crosses the volcanic landscapes of southern side of the Big Island.  Hawaii Route 11 terminates at Hawaii Route 19/Ka...