Skip to main content

Final Progress Report on I-74/US 311 Freeway for 2009

Made my last trip of 2009 to check out progress on the construction of the I-74/US 311 freeway from High Point to Randleman during midday today (12/12). Based on the NCDOT's Construction Progress Report there hasn't been much going on along the Business 85 to Cedar Square Road segment the last two months as far as percentage complete goes, now up to about 81% complete at the end of November compared to 78% in September. There has been, however, some noticeable progress on the two remaining bridge projects as well on some of the roadway itself.

Going West to East (or North to South depending on which route you prefer) the first stop is the Baker Road bridge. Work has been completed on the bridge decks as you can see here (yes, they were working on Saturday, making up for bad weather maybe):
The bridge is capable of supporting traffic, as the truck driving across it shows here:
You can see they still have to connect the bridge to the pre-exisiting alignment of Baker Road and build the bridge walls and railings before being open to traffic. This could happen before the end of the year if the weather cooperates.
They are still working on getting the road down to grade south of the bridge and will start north when the bridge is opened and the temporary roadway to the north can be demolished.

Jackson Lake Bridge. Not much progress here west of the bridge, as you can see they still don't have a westbound roadway here, still just piles of dirt:
The roadway to the east toward the Kersey Valley bridge, however, is basically complete and can support contractor traffic as you can see below:
Kersey Valley Road area. Again little progress here. Some more excavation has been done to the roadway west of the bridge:
Notice less construction equipment and machinery present than last month by the graded slopes going eastbound. The view of the roadway between Kersey Valley and I-85 shows more work is needed:
Most of the depressions are filled with water which, due to today's cold temperatures, had turned to ice. They are going to have to wait until this dries up to proceed.

The I-85 interchange. Some progress here, if you look behind the flyover bridge (the farthest) you'll notice the top of an overhead sign structure for the I-85 exit that has been put up. A cantilevered overhead sign structure was also put up just north of the NC 62 bridge.
Another photo of the same area showing progress around the interchange offramp, it appears more grading has been done down toward the future eastbound roadway. And if you didn't notice before, the west wall to the flyover bridge has been completed:
Tuttle Road. There has been more progress in placing guardrails along this section. Looking west you can see there are now guardrails on both directions of the highway:
There is also now guardrail looking east/southbound:
It appears that there is an asphalt layer capable of carrying traffic now from just east of the I-85 interchange heading east almost to Cedar Square Road, with a few exceptions. Notice the truck below is heading the wrong way, but demonstrates it is possible to get to near Cedar Square Road (that would be easiest way off the freeway).
A closer look at the Tuttle Road bridge heading east:
The Cedar Square Road bridge and Interchange. Most of the progress in the last month has been made here. First, the bridge has been opened:
To the right is the old road alignment which will be access to Poole Road. (The connection has been made but the road was blocked by road closed signs, this wasn't preventing locals from making there way around them to access Cedar Square). Now crossing the bridge:
The bridge has 3 lanes, the center reserved for those wanting to make a left turn onto I-74 East, Which occurs just before where this photo was taken looking at the new intersection with US 311:
Second, progress on the on and offramps. For eastbound traffic these are opposite each other while the westbound ramps are on the south side of Cedar Square. Here's the progress being made on the westbound on/off ramps:
Here's a look on the progress of building the eastbound off ramp:
They still need to remove the old alignment of Cedar Square in the freeway's path before final grading and paving can be made.
Meanwhile all the construction equipment is at the end of the current road awaiting construction on the second part to complete the freeway to US 220:
US 311. Some additional clearing in the construction area, and the start of one of the on or offramps, but little else:
US 220. Some progress here in the appearance of a second center support in the median for the other flyover ramp:
Here's progress on the first flyover support, plus clearing on the northbound side:
The wider view of the construction area, heading northbound:
Progress on the future I-74 West Flyover ramp:
They are working also on expanding US 220 to 3 lanes (seen beyond the barrier) between Pineview Street and the existing US 311 exit:
Notice the polls for a new exit sign. These also appear elsewhere along US 220, not just in the I-74 construction area implying another project installing new exit signs, hopefully before the I-74 project is finished and with I-73 mileage based numbers.

My next trip will be after they open the new rest areas/visitor's centers near Seagrove on I-73/74 sometime in January (current completion date is 1/21/10). I'll let everyone know when they are open, in case anyone else wants to come along and tour them.

Comments

Popular posts from this blog

North Carolina Continues to Move Forward with Rail

2023 and the first half of 2024 have seen continued growth in North Carolina's passenger rail system.  From increased daily trains from Raleigh to Charlotte, federal funds for studying additional corridors, and receiving a historic grant to begin the construction of high-speed rail between Raleigh and Richmond, the last 18 months have been a flurry of activity at NCDOT's Rail Division.  And that's just the tip of the iceberg. As ridership and routes increase - the engine of North Carolina passenger rail trains will become a more common sight. (Adam Prince) Increased Passenger Train Service: On July 10, 2023, a fourth Piedmont round-trip rail service between Raleigh and Charlotte commenced.  The four Piedmont trains plus the daily Carolinian (to Washington, DC, and New York) bring the total of trains serving the two cities daily to five. The current daily Piedmont and Carolinian schedule between Charlotte and Raleigh (NCDOT) The result was over 641,000 passengers utilized pa

The Midway Palm and Pine of US Route 99

Along modern day California State Route 99 south of Avenue 11 just outside the City limits of Madera one can find the Midway Palm and Pine in the center median of the freeway.  The Midway Palm and Pine denotes the halfway point between the Mexican Border and Oregon State Line on what was US Route 99.  The Midway Palm is intended to represent Southern California whereas the Midway Pine is intended to represent Northern California.  Pictured above the Midway Palm and Pine can be seen from the northbound lanes of the California State Route 99 Freeway.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page The history of the Midway Palm and Pine The true timeframe for when the Midway Palm and Pine (originally a Deadora Cedar Tree) were planted is unknown.  In fact, the origin of the Midway Palm and Pine w

US Route 101 in Benbow, Garberville and Redway

The communities of Benbow, Garberville and Redway can all be found along US Route 101 within southern Humboldt County.  The former surface alignment of US Route 101 in Garberville and Redway once crossed the Garberville Bluffs along what is now Redwood Drive via a corridor constructed as part of the Redwood Highway during the 1910s.  US Route 101 through Benbow, Garberville and Redway was modernized by 1935.  US Route 101 would eventually be upgraded to freeway standards in Benbow, Garberville and Redway by extension of the Redwood Freeway during 1966-68.  As the cover photo the original grade of US Route 101 and the Redwood Highway can be seen at the Garberville Bluffs during 1934.  US Route 101 can be seen in the communities of Benbow, Garberville and Redway on the 1935 Division of Highways Map of Humboldt County .   The history of US Route 101 in Benbow, Garberville and Redway Benbow, Garberville and Redway lie on the banks of the South Fork Eel River of southern Humboldt County.  D