NCDOT - We'll finish the Charlotte Outer Loop by 2012 - Oh wait, we still have to buy land first though - and then there is that funding problem

From the highway that never stops giving us something to write about - Interstate 485 in Charlotte - we have new news.

Earlier this year, newly elected Governor Beverly Perdue proclaimed that the final piece of construction of Interstate 485 would begin this year. This after a number of years of delays on completing the entire loop.

Well recently, NC Secretary of Transportation Gene Conti said that work will still begin on the final pieces of 485 this year and a 2012 completion date is still in the work. Well, not exactly. (It appears I need to bring back the picture of Lee Corso..."Not So Fast, My Friend!)

There are a few hurdles still left - first the state needs to spend $16 million in acquiring property for construction of the freeway. In fact, Conti concedes that actually construction - you know moving earth, clearing trees and what not - most likely won't begin this year.

In fact, he told Al Gardner of WBT-AM in Charlotte, "I don't think that we can start construction in this calendar year, but starting to acquire property is a way of getting going."

Yet, the promise is to have I-485 completed in 2012 - have they not forgotten that two years is almost the same amount of time that the last piece of 485 faced in just construction delays?

And skepticism isn't only found in this blog - Charlotte Mayor Pat McCrory on the latest news on I-485 - "I don't see it in the cards. Actually, I think a promise was made a bit prematurely before a funding source was allowed."

And sooner rather than later - the truth comes out - unless they move funding from another Charlotte area projects - upgrading Independence Blvd. to a freeway, widening I-85 in Cabarrus County or construction of the Monroe Bypass. Which most likely won't happen - so in all honesty - financing won't be available until 2015. (Charlotte.com)

And speaking of funds, Charlotte is in jeopardy of losing federal funding for transportation - the reason? The Metro Charlotte area does not meet air quality standards - specifically ozone. The region may see transportation funding disappear as early as next year. (Charlotte.com)

So what does this mean - will we actually see I-485 completely finished by 2012 - I wouldn't bet the house on it.

For more reading:
$16 mil for land need to complete I-485 -The CLog - Creative Loafing


Comments

Popular posts from this blog

Yes, the color of your nearby fire hydrant matters...

...and here's why. You will find White, Red, Yellow and Violet colored fire hydrants pretty much everywhere.  But there's a reason for this - and it's because of the National Fire Protection Association (NFPA).  This association has issued guidelines for color coding standards for fire hydrants.  These color codes from the body of the hydrant, top of the hydrant, and in some municipalities the outlet caps are designed to allow fire fighters to know what type of system, water flow rate (Gallons Per Minute or GPM), and level of water pressure.  This guideline is known as NFPA 291 and is intended to be used universally throughout the United States. The NFPA guidelines are specific to the body and the top cap of the hydrant.  If a hydrant is WHITE or YELLOW - it means that it is connected to a public/municipal water system.  If a hydrant is RED - the hydrant is connected to a private system, typically a well.  These are most common in rural or unincorporated areas

Phase 1 of the California State Route 132 West Expressway (in the making since 1947)

On September 15, 2022, the Phase 1 of the California State Route 132 West Expressway opened in the city of Modesto from California State Route 99 west to North Dakota Avenue.  Phase 1 of the California State Route 132 West Expressway was built upon a corridor which was tentatively to designated to become the branching point for Interstate 5W in the 1947 concept of the Interstate Highway System.  The present California State Route 132 West Expressway corridor was adopted by the California Highway Commission on June 20, 1956.  Despite almost being rescinded during the 1970s the concept of the California State Route 132 West Expressway corridor lingered on for over half a century and became likely the oldest undeveloped right-of-way owned by California Transportation Commission.  Pictured above is the planned California State Route 132 freeway west of US Route 99 in Modesto as featured in the May/June 1962 California Highways & Public Works.   The history of the California State Route

Aptos Creek Road to the Loma Prieta ghost town site

Aptos Creek Road is a roadway in Santa Cruz County, California which connects the community of Aptos north to The Forest of Nisene Marks State Parks.  Aptos Creek Road north of Aptos is largely unpaved and is where the town site of Loma Prieta can be located.  Loma Prieta was a sawmill community which operated from 1883-1923 and reached a peak population of approximately three hundred.  Loma Prieta included a railroad which is now occupied by Aptos Creek Road along with a spur to Bridge Creek which now the Loma Prieta Grade Trail.  The site of the Loma Prieta Mill and company town burned in 1942.   Part 1; the history of Aptos Creek Road and the Loma Prieta town site Modern Aptos traces its origin to Mexican Rancho Aptos.  Rancho Aptos was granted by the Mexican Government in 1833 Rafael Castro.  Rancho Aptos took its name from Aptos Creek which coursed through from the Santa Cruz Mountains to Monterey Bay.  Castro initially used Rancho Aptos to raise cattle for their hides.  Following