Skip to main content

Lynchburg, VA's College Lake Dam Removal Project Approaches Significant Milestone

 

It's not often that you hear about the planned removal of a dam in an urban area, but that's exactly the kind of project that the independent city of Lynchburg, VA has embarked on. The city and the University of Lynchburg are nearing the midway point of a lengthy project intended to reimagine the Blackwater Creek watershed in the area of the nearby University, while also replacing a structurally-problematic earthen dam and creating a newer, safer alignment for the local highway that currently crosses it.

The existing College Lake Dam was built in 1934 and impounds Blackwater Creek to form College Lake, which has a surface area of about 17 acres along the western periphery of the University campus. The dam additionally serves as the embankment that carries Lakeside Drive (US Route 221) across College Lake and the Blackwater Creek. The dam itself was built of compacted clay and stands 35 ft tall and is about 300 ft long. At the east end of the dam is a spillway for Blackwater Creek that is bridged by a single-span concrete & stone masonry arch. Severe flooding of College Lake due to record rainfall in August 2018 overtopped the dam and nearly caused its collapse; this incident prompted local and state officials to consider the dam’s removal as part of a larger restoration of Blackwater Creek and updating of the Lakeside Drive corridor.


Above: The College Lake Dam is an earthen embankment that impounds Blackwater Creek near the University of Lynchburg to form College Lake
Below: The new four-way roundabout intersection at the main entrance to the University nears substantial completion

With the City and University in agreement that the safety and ecology of the College Lake area needed to be addressed, the first step in the construction process (which began in 2021 and is not expected to wrap up until 2024) is the construction of a four-lane bypass bridge to carry Lakeside Drive across Blackwater Creek a short distance downstream (north) of the dam site. As part of the bridge project, a new four-way roundabout intersection is being constructed at the east end of the new bridge in order to better and more efficiently serve access to the University of Lynchburg’s main entrance. Upon completion of the bridge in Summer 2022, work will begin on the removal of the College Lake Dam and the restoration of the surrounding ecosystem and wetlands to what local officials hope will be pre-dam conditions. Local officials are optimistic that this urban wetland restoration effort (which has a price tag of about $18 million) will not only provide ecological uplift and water quality benefits for the Blackwater Creek watershed, but will additionally serve as a model for future urban wildlife restoration efforts to be considered by municipalities nationwide.

The following pictures (from June 2022) of the old alignment of Lakeside Drive (US Route 221) were taken by the author of this post. Click on each photo to see a larger version.


The following ground-level pictures (from June 2022) of the new alignment of Lakeside Drive (US Route 221) were taken by the author of this post. Click on each photo to see a larger version.

The following aerial pictures of the construction site (from June 2022) were taken by the author of this post using a DJI quadcopter drone. Always use proper judgment and situational awareness when flying in areas such as this. Click on each photo to see a larger version.



How to Get There:


Comments

Popular posts from this blog

The case to move Interstate 73 in Southern Ohio onto US 33

Every decade or so, Ohio pushes to revisit the proposed Interstate 73 that would connect Michigan to Myrtle Beach, South Carolina.  It's been happening since Congress legislated the route in 1991.  Within Ohio, Interstate 73 generally follows the US 23 corridor from Portsmouth through Columbus to Toledo, and into Michigan. Since High Priority Corridor Five was created , Ohio has really done nothing to move forward with Interstate 73.  Sure, there have been feasibility studies here and there.  But actual dollars and construction just haven't occurred. The US 33 Nelsonville Bypass appears to have been built to Interstate standards. However, Ohio has been slowly upgrading US 33 to a full freeway through Southeastern Ohio.  Bypasses of Lancaster and Nelsonville opened in 2004 and 2013, respectively.  Other sections of two-lane road are being twinned, some to freeway or, at a minimum, to expressway standards.  Currently, a $274 million widening project in...

SCDOT to present I-73 wetland replacement proposal on May 3rd

It looks like SCDOT may soon clear an environmental hurdle when they present a plan to replace 27 acres of wetlands on May 3rd. If approved, the plan will replace 27 acres of wetlands in the Little Pee Dee Heritage Preserve that will be impacted by construction of Interstate 73 through the area. Approval of the wetland replacement proposal is necessary for SCDOT to get federal permits that will allow them to build the new highway. The DOT and the Department of Natural Resources (DNR) are working together on the plan. Recently, the SC Legislature made two attempts to allow recent wetland gains by the state as compensation for the affected 27 acres. Both attempts failed. The DNR has stated it would not oppose I-73 even though some environmental-oriented groups have been vocal against it. The Southern Environmental Law Center , based in Chapel Hill, is one of the groups hoping that the routing through the preserve can still be changed. They point to federal law that prohibits buildi...

Local Sign Find - The last remnant of Business Interstate 95 between Kenly and Rocky Mount , NC

As you head north on Interstate 95 at Exit 107 for Kenly and US 301, you'll notice something odd about the overhead sign for the exit.  Peeling off the sign for all that can see is the word 'NORTH' off-center from the US 301.  This old sign (probably close to original from when this section of I-95 opened - more on that in a little bit) gives a hint to a short-lived Business Interstate Route that ran from here to Rocky Mount. The last hint of the Kenly-Wilson-Rocky Mount Business I-95 (Shaun White - August 2020) Interstate 95 in North Carolina has a unique history.  But one of the overlooked and forgotten pieces of Interstate 95 in North Carolina is the 38 mile section between Kenly and Rocky Mount.  When opened to traffic in late 1978, it was the next to last piece of Interstate 95 in North Carolina to open replacing a four lane US 301 from Battleboro through Rocky Mount and Wilson to eventually tying back into the Interstate in Kenly. Though it was not delayed in l...