PA: Contractor defaults on Findlay Connecter contract....construction at a pause

Construction on the southern two and a half miles of the Findlay Connector, which will connect US 22 to PA 60 and the Pittsburgh Airport, has ground to a halt recently. The reason, the contractor, Smith and Johnson, was declared in default by the PA Turnpike commission as a result of Smith and Johnson's financial woes. See article in today's Post-Gazette.

Smith and Johnson was awarded the contract to build Section 54C which runs from US 22 near Bavington to just north of Bald Knob Road. The contract included interchanges at US 22 and Bald Knob Road. According to the Post-Gazette article: Section 54C is 65 percent complete while Sections 54A and 54B are 77 and 76 percent complete, respectively. Most of the troubles began in the fall. And although a bridge carrying Candor Road over US 22 was demolished in late January, Smith and Johnson was pulling out from the construction site. On January 18, the Turnpike Commission offered the company a chance to right the ship, but those efforts failed and the Turnpike declared them in default on February 8.

Problems in addition to falling behind schedule include shortpaying or not paying at all their subcontractors and suppliers.

This would be the third major project in two states that Smith and Johnson has pulled out of. In September of 2005, Smith and Johnson halted work on a six mile segment of a 50 mile highway called the O'Bannon Expressway in Southern Indiana. Citing unanticipated $3,000 fuel costs and began a tussle with Indiana over who should pay for the additional costs.

According to this WISH-TV news story from September 15, 2005:

Indiana Department of Transportation officials said the contractor is bound by its contract to complete the job for the price it bid and that the state has no policy for allowing fuel-cost escalations. "This is very unusual. This hasn't happened anywhere else (in the state) this year," said department spokeswoman Afua Anokwa.

The company also stopped work on a US 231 project in Rockport, Indiana at the same time. The company laid of 30 employees.

It appears that this was a ploy to get INDOT's attention. Bob Johnson, general superintendent for S &J, said in a September 16, 2005 issue of Land Line Online that it was standard procedure for other partners to absorb part of the cost.

“There is sort of a standard they’ve used in other states,” he said. “The contractor absorbs the first 20 percent. Then after that, the governing agency or the contracting agency usually helps out with the fuel cost.”

The state ordered them back to work and they obliged.

However, according to today's article...it appears the company has gone out of business.

"As far as we know, they closed down the highway construction side of their business," Mr. Agnello said. "Basically, they're out of business."
As this develops, more will be reported here.




Comments

Popular posts from this blog

North Carolina Continues to Move Forward with Rail

2023 and the first half of 2024 have seen continued growth in North Carolina's passenger rail system.  From increased daily trains from Raleigh to Charlotte, federal funds for studying additional corridors, and receiving a historic grant to begin the construction of high-speed rail between Raleigh and Richmond, the last 18 months have been a flurry of activity at NCDOT's Rail Division.  And that's just the tip of the iceberg. As ridership and routes increase - the engine of North Carolina passenger rail trains will become a more common sight. (Adam Prince) Increased Passenger Train Service: On July 10, 2023, a fourth Piedmont round-trip rail service between Raleigh and Charlotte commenced.  The four Piedmont trains plus the daily Carolinian (to Washington, DC, and New York) bring the total of trains serving the two cities daily to five. The current daily Piedmont and Carolinian schedule between Charlotte and Raleigh (NCDOT) The result was over 641,000 passengers utilized pa

The Midway Palm and Pine of US Route 99

Along modern day California State Route 99 south of Avenue 11 just outside the City limits of Madera one can find the Midway Palm and Pine in the center median of the freeway.  The Midway Palm and Pine denotes the halfway point between the Mexican Border and Oregon State Line on what was US Route 99.  The Midway Palm is intended to represent Southern California whereas the Midway Pine is intended to represent Northern California.  Pictured above the Midway Palm and Pine can be seen from the northbound lanes of the California State Route 99 Freeway.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page The history of the Midway Palm and Pine The true timeframe for when the Midway Palm and Pine (originally a Deadora Cedar Tree) were planted is unknown.  In fact, the origin of the Midway Palm and Pine w

US Route 101 in Benbow, Garberville and Redway

The communities of Benbow, Garberville and Redway can all be found along US Route 101 within southern Humboldt County.  The former surface alignment of US Route 101 in Garberville and Redway once crossed the Garberville Bluffs along what is now Redwood Drive via a corridor constructed as part of the Redwood Highway during the 1910s.  US Route 101 through Benbow, Garberville and Redway was modernized by 1935.  US Route 101 would eventually be upgraded to freeway standards in Benbow, Garberville and Redway by extension of the Redwood Freeway during 1966-68.  As the cover photo the original grade of US Route 101 and the Redwood Highway can be seen at the Garberville Bluffs during 1934.  US Route 101 can be seen in the communities of Benbow, Garberville and Redway on the 1935 Division of Highways Map of Humboldt County .   The history of US Route 101 in Benbow, Garberville and Redway Benbow, Garberville and Redway lie on the banks of the South Fork Eel River of southern Humboldt County.  D