Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

Rep. Sue Myrick's letter to Gov. Easley and Sect. Tippett published in Charlotte Observer

US. Representative Sue Myrick's (R-Charlotte) letter to North Carolina's Governor Mike Easley and NC Transportation Secretary Lyndo Tippett was published in the Friday, November 30th edition of the Charlotte Observer . Why are we delaying the completion of 1-485 in Charlotte again? I read in The Charlotte Observer how rising prices of materials are leading to the delay. Why didn't these same rising costs delay the loops in Fayetteville and Wilmington? Why are we building loops in Fayetteville and Wilmington before we complete the one in Charlotte? We were working on the one in Charlotte back when I was mayor. That was 20 years ago! ... Last I looked Charlotte was the largest city in the state. There seems to be no recognition of that fact in Raleigh. No recognition that we are at a standstill with traffic. No recognition that we have a traffic problem. Nor is there any recognition of the fact that the state DOT utterly botched up the southern leg of our yet to be completed ...

New River Gorge National Park & Preserve - Sandstone Falls

The New River, which runs through New River Gorge National Park & Preserve, is best known for its dramatic rapids and whitewater adventures.  Those features begin at one of the river's widest points: Sandstone Falls. From the Sandstone Falls Boardwalk a look at just a small part of the falls. Though the vertical drop of roughly 20 feet is less than many other well-known waterfalls in the state, the falls' expanse, where the river approaches 1500 feet wide, makes Sandstone Falls impressive.   The Boardwalk Trail leads to a better vantage point of the overall falls. It is a great spot for photography, fishing, or laying out in the sun. Access to the falls is relatively easy: from Hinton, cross the New River on Highway 20, then turn right onto CR 26 and follow New River Road to the Sandstone Falls Parking Area. The Island Loop Trail is a short detour off the Boardwalk Trail and shows a quieter side of the area. At Sandstone Falls, you will find a variety of activities fr...

I-785 first "signed" nine years ago Friday.

This is where Google news alerts really come in handy. It appears that nine years ago tomorrow, there was a ceremony 'dedicating' US 29 from Greensboro to Danville as Interstate 785. From the opening of a 1998 Greensboro News & Record Article: "Say goodbye to U.S. 29. Say hello to Interstate 785. In a name change billed as an enhancement of "economic development," Reps. Virgil Goode of Virginia and Richard Burr of North Carolina will speak today at a ceremony marking the designation of U.S. 29 as part of the interstate highway system. It begins at 10:30 a.m. at the Piedmont Triad Visitors..." A few things have changed in the nine years. I'd love to say US 29 has now become fully integrated as Interstate 785, but that's not the item that is different today than nine years ago. Here's the change....North Carolina U.S. Representative Richard Burr is now North Carolina U.S. Senator Richard Burr. Other than that, there are a few ...