Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

Morgan Territory Road

Morgan Territory Road is an approximately 14.7-mile-long roadway mostly located in the Diablo Range of Contra Costa County, California.  The roadway is named after settler Jerimah Morgan who established a ranch in the Diablo Range in 1857.  Morgan Territory Road was one of several facilities constructed during the Gold Rush era to serve the ranch holdings.   The East Bay Regional Park District would acquire 930 acres of Morgan Territory in 1975 in an effort to establish a preserve east of Mount Diablo. The preserve has since been expanded to 5,324 acres. The preserve functionally stunts the development along roadway allowing it to remain surprisingly primitive in a major urban area. Part 1; the history of Morgan Territory Road During the period of early period of American Statehood much of the Diablo Range of Contra Costa County was sparsely developed.   Jerimah Morgan acquired 2,000 acres of land east of Mount Diablo in 1856 and established a ranch in 1857. Morgan Territory Road is

The 1915 Fine Gold Creek Bridge (Madera County)

The 1915 Fine Gold Creek Bridge is an early era arch concrete structure found alongside modern Madera County Road 200.  The structure was modeled as a smaller scale of the 1905 Pollasky Bridge (still in ruins at the San Joaquin River) and was one of many early twentieth century improvements to what was then known as the Fresno-Fresno Flats Road.  The 1915-era bridge was replaced with a modernized concrete span during 1947 but was never demolished.  The original concrete structure can be still found sitting in the brush north of the 2023 Fine Gold Creek Bridge.     Part 1; the history of the 1915 Fine Gold Creek Bridge The 1915 Fine Gold Creek Bridge lies near the site of the former mining community of Fine Gold.   Mining claims were staked at Fine Gold during the Mariposa War during 1850. The community was never very large but became a stopping point on the stage road between the original Fresno County seat at Millerton and Fresno Flats (now Oakhurst). The stage road eventually bypas

San Francisco's Broadway Tunnel

The Broadway Tunnel in San Francisco is a structure at Russian Hill which connects the neighborhood Chinatown to North Beach. The tunnel was included in the 1948 San Francisco Trafficways Plan as a connector between the Central Freeway and Embarcadero Freeway. The structure was completed in December 1952 and spans 1,616 feet through Russian Hill. The Broadway Tunnel was designated as the Robert C. Levy Tunnel in 1986. Part 1; the history of the Broadway Tunnel Following the discovery of gold at Sutter's Mill in 1848 San Francisco would see a major population boom.  The city would expand from the shores of San Francisco Bay inland towards the many steep hills.  The hills of San Francisco would prove to be a major hinderance towards the expansion of city.  Roads were generally plotted over the tops of hillsides and had steep grades.  Russian Hill in particular was one of the steepest and contained numerous streets with grades in excess of twenty percent.  Broadway can be seen cros