Skip to main content

Two Day Drive Along I-95

I had a conference to attend on Friday and Saturday in Portsmouth, NH. Since I decided to save some money and not book a room, but commute instead, I had a couple opportunities to check out new signage along I-95 (and parts of I-93 too) both Friday and Saturday.

1. Friday Drive
For the Friday trip up I used I-93 and US 1 to take me to I-95 in Peabody. The only new sign worth taking a photo of along I-93 was the newly placed Exit 15 attractions sign which had been put up blank in February but recently received its logos:
MassDOT has gone recently to brown backgrounds for the site logo, originally these were a darker blue. The placement of the sign makes it hard to see around the light pole. There was nothing else new to report. The contractor still has additional foundations to pour before they can start installing sign supports along this stretch of I-93 from Braintree to Boston.

There is a new sign replacement project to complete the sign updating along I-95 from Peabody to the NH border. Work along the contract area has only recently begun with just 7% of it reported complete according to MassDOT as of early March. The only signs of work were a few overhead sign support foundations, or holes preparing for foundations and new gore signs for Exits 47 and 48 in the Danvers area. Work has begun on on building a new Merrimack River bridge and widening I-95 between Exits 57 and 58. Here's a photo I took Friday of the construction:

The new bridge is being built east of the current bridge, barriers are along both sides of the roadway while the new 4th lane is built north of the bridge in the existing median. Here's a closer look approaching the bridge from Saturday morning:
There were two lanes closed on Saturday morning, only one Friday.

On the way back I decided to take I-95 around Boston to check out new signage going up between Lexington and Newton. This project, again according to MassDOT, is now 54% complete and still scheduled to be completed this fall. Here's a late afternoon shot of the new overhead for MA 4/MA 225 after the US 3 exit in Burlington:
This is to supplant the ground-mounted new signs put up under the Burlington to Reading sign contract completed in 2011:
That's still standing for now. Here's the next new overhead sign with, surprise, an older sign behind it:
The pole in front is for a traffic camera, which first clued me in a new sign had been installed. There area also more sporadic new signage heading south. Here's the one new sign for MA 2A:
The one mile advance sign has been changed out, but the only other is for MA 2A West...
There is only one new sign for the next interchange, MA 2 heading southbound. The 1/2 mile advance sign for MA 2 West:
The only other new sign in the vicinity is an updated version of the ground mounted Waltham exits auxiliary sign:
New signage had been previously placed at the Totten Pond Road exit when the bridge was reconstructed in 2012. The next new signage under the current contract is for US 20.
This 1 mile advance overhead is followed by a new ground-mounted auxiliary sign for MA 117:
And then a new 1/2 mile advance overhead for US 20:
A separate contract is installing new larger 'Best Route to Logan Airport' with a plane logo and arrow pointing in the correct direction. Here is one of these signs approaching the Mass Pike/I-90 exit:
Similar signs have gone up on I-93 North in Braintree and I-95 South in Peabody (the latter telling drivers to use the US 1 exit). The next new signage is just beyond the I-90 interchange:
Quite a lot of info for one overhead assembly. Three different exits and a blue sign for the one remaining service plaza along '128' heading southbound. The new signs remove the MBTA information from the overheads for Exit 22 and put them onto ground-mounted auxiliary signs:
There is also one new overhead sign for the MA 16 East exit, the last new sign under this contract heading south:
There are more new overhead signage heading southbound from the '128 Add-A-Lane' project which is now concentrating efforts between Great Plain Ave and MA 109 in Dedham. Here's the first:
A new 1/2 mile advance sign for Great Plain Ave. put up last fall. There area also a couple other newer sign assemblies put up at the same time further south, here before the off-ramp to Great Plain Ave:
That covers the 1/2 mile advance sign for MA 135 as well, and a couple at the MA 135 exit:
This one missing a future 'Exit Only' banner, while the one at the off-ramp:
Has the banner but needs a lane for it. There is one more new overhead, the one-mile advance for MA 109, the rest of the signs for that exit still need to be replaced.


2. Saturday
On the trip up Saturday, I decided to heed MassDOT's advice and avoid driving I-93 through Boston due to possible congestion from lanes closed for ceiling replacement in the I-90/Mass Pike Prudential Tunnel. This afforded me the opportunity to check out new I-95 construction and signage northbound:
There is now a new lane-split northbound, following that which existed southbound last year, for rebuilding the north I-95 bridge over MA 135. The barriers are protecting the construction zone. Most of the new lanes have been completed. The hold up for this section is the delay in building the bridges for MA 109 which required a design change due to problems with the subsurface rock. Here's a close-up of the lane split approaching MA 135:
Though somewhat obvious, there is no sign saying you need to stay right in order to access the MA 135 off-ramp. The new median barrier ends after the railroad bridge over I-95 after the Great Plain Ave exit:
The final segment of the Add-A-Lane project to MA 9 is supposed to start later this year.

Now back to progress of new signage along I-95 from Newton to Lexington. The latest overhead assembly to go up is approaching the MA 16 exit ramp:
The new I-90 signage matches that previously put up at the off-ramp with the yellow toll banner and Mass Pike logo replacing text. The 'missing Exit 22' is handled by separate new signage for that exit and auxiliary MBTA logo signage seen in the distance. The next new overhead sign was in addition to the new Totten Pond Rd overheads put up in 2012 at the interchange itself. This is the 3/4-Mile advance sign:
Like southbound, new signage is sporadic along I-95 in Waltham and Lexington. This is the 1-Mile advance for Trapelo Road:
The next new sign is at the off-ramp westbound:
Unlike southbound, there are no new overheads for the MA 2 Exit, the next new sign is at the ramp for MA 2A (and the only remaining service plaza northbound):
If you can see the mile marker, this one day will be Exit 46. There is one additional new sign for MA 2A on the C/D ramp after the Service Plaza:
This one for MA 2A West. The last remaining new signs for this project are for the MA 4/MA 225 Exit in Lexington:
There is a new 1-Mile Advance, and 1/2 mile advance signage which, unlike Southbound, are not accompanied by older signage:
And the last new sign is at the westbound off-ramp:
The only new section of '128' lacking new signage now is the section between I-93 and US 1 in Peabody. The only other section of I-95 needing a signage update, besides the remainder of the 'Add-A-Lane' project area, is south of I-93, Exit 12 to the RI border.

In the way home I took a quick trip into Maine via the US 1 bridge that was closed for repair the last time I was in Portsmouth in June 2013:
Here's the view looking south toward Portsmouth, and here is the view heading north:

Here's a photo a left-over detour sign for US 1 in Maine:

On the way home I was able to confirm most of the erroneous MA 2A signs along Mass Ave in Boston's South End had been removed following a Feb. TV report which left some Boston transportation officials with egg on their faces. The few remaining signs have had their directional banners removed, replaced by either 'To' or 'Jct' banners. I could not get any decent photos of these remaining signs, that will have to wait until my next trip into Boston.

To see previous photos taken of new signage check out my I-93 Photo Page or I-95 Photo Page .

Comments

Popular posts from this blog

Did Caltrans just kill the G26 cutout US Route shields?

The US Route System was formally created by the American Association of State Highway Officials during November 1926.  Through the history of the system the only state to which has elected to maintain cutout US Route shields has been California.  The G26 series cutout US Route shields have become a favorite in the road enthusiast hobby and are generally considered to be much more visually pleasing than the standard Federal Highway Administration variant.  However, the G26 shield series appears to have been killed off on January 18, 2026, when Caltrans updated their Manual of Uniform Traffic Control Devices.  This blog will examine the history of the US Route shield specifications in California and what is happening with the 2026 changes.  The blog cover photo is facing towards the terminus of California State Route 136 and at a G26-2 specification US Route 395 shield.  In the background Mount Whitney can be seen in the Sierra Nevada range.   ...

May 2023 Ontario Trip (Part 3 of 3)

  Over the years, I have made plenty of trips to Ontario, crisscrossing the southern, central and eastern parts of the province. Living in Upstate New York, it's pretty easy to visit our neighbor to the north, or is that our neighbor to the west? Ottawa is one of my favorite cities to visit anywhere in the world, plus I've discovered the charm of Kingston, the waterfalls of Hamilton (which is on the same Niagara Escarpment that brings us Niagara Falls), the sheer beauty of the Bruce Peninsula, and more. But I hadn't explored much of Cottage Country. So I decided to change that, and what better time to go than over Memorial Day weekend, when the daylight is long and I have an extra day to explore. On the third and final day of my trip, I started in Huntsville and made my way through Muskoka District and Haliburton County, passing by many lakes along the way. I stopped in towns such as Dorset, Haliburton and Bancroft before making a beeline down to Belleville and then over th...

Abandoned Fowler Avenue in Clovis, California

Originally Fowler Avenue in the city of Clovis had a brief discontinuation approaching Herndon Avenue.  Fowler Avenue traffic heading northbound was required to detour briefly onto westbound Herndon Avenue.  During 2001 this discontinuation was removed when Fowler Avenue was reconfigured to access the Sierra Freeway (California State Route 168) via an interchange.  This led to a segment of the original alignment of Fowler Avenue just south of Herndon Avenue to be abandoned.  Despite a shopping center opening over part of the original Fowler Avenue alignment in 2016 much of the abandoned roadway remains.   The history of the abandoned original alignment of Fowler Avenue in Clovis The original alignment of California State Route 168 departed downtown Clovis eastbound along Tollhouse Road.  This original alignment did not interact with Fowler Avenue at the Herndon Avenue intersection.  Fowler Avenue north of Tollhouse Road ran north to Herndon Avenue...