The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

This abrupt end to US 40 east of Brownsville was the norm for nearly forty years. (Brian Reynolds)
For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville.

Brownsville in September 1967.  US 40 crosses over the new Lane Bane Bridge and a trumpet interchange with PA 88 sits in Washington County.  The Intercounty Bridge sits just south of the Lane Bane Bridge.  Construction on the US 40 four lane extension to Grindstone Road doesn't appear to be underway yet. (Penn Pilot)

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What was unknown (at least to me) is that what was supposed to have continued southeast or east from Grindstone Road.  Was it a separate US 40 that would have continued towards Uniontown? Or part of the original Mon Valley Expressway?  Or something else? Official PennDot maps of Fayette County (above at right) would never show any proposed or planned route beyond the interchange.

Fortunately since this article was originally written in June 2017, new information has come into light.  From a blog comment below - the highway was to continue southeast paralleling US 40 to the US 119 bypass of Uniontown.  Plans to extend the four lane US 40 to Uniontown existed to at least 1975; however, it appears that any further extension of the road would fall victim of PennDOT's troubled financial problems of the 1970s.  What is still unknown is what was the planned alignment of the road - would it be a full limited access highway or include driveways and intersections.  Where it would have tied into the US 119 freeway is also unknown. Finally, does the current PA Turnpike 43 follow any of the proposed highway's path.

Regardless, nothing would happen here until the later half of the 2000s.  It was then, that this old unused piece of expressway would be converted to a two lane at-grade roadway connecting US 40 and Brownsville to the Mon-Fayette Expressway.

Personally, I first came across this stub end in the early 1990s when going to watch my high school football team play Brownsville Area High School.  We came upon it via Grindstone Road.  Grindstone Road would briefly turn into a four lane boulevard type road and crossover the never completed highway.  During the 1990s, I would drive out to explore this area to search for any clues on what was never built here.  I've included some photos of how it looked in 2002 when a number of us toured this oddity.

Grading for the never built highway was still evident even with the overgrowth.  (Bee Family)
This overpass carried Grindstone Road over the unbuilt highway.

Right of way and clearing was done beyond the overpass to what would have been the eastern end of the ramps for the diamond interchange. (Bee Family)

(Bee Family)
Not long after those photos were taken, the Pennsylvania Turnpike Commission would begin construction to finally extend this route southeastwards towards Uniontown.  Known as the Redstone Connector, the roadway was built as a two lane highway that is served to connect US 40 and Brownsville to the Mon-Fayette Expressway.  The highway, though built as two lanes with a center turning lane, can be expanded to a four lane road keeping the center turn lane if traffic volumes and development warrant.  The diamond interchange with Grindstone Road would not survive the construction.  It was eliminated and changed to a normal signalized intersection.  A return visit in December 2006 showed construction well underway on the Redstone Connector and the new roadway would open one year later in December 2007.

Grading of Redstone Way in December 2006 (Adam Prince)

A view of the under construction Redstone Connector (Redstone Way) from the former Grindstone Road overpass.  THough it looks like the diamond interchange ramps would remain in this photo, they would be removed as the interchange was replaced with a traditional signalized intersection (Adam Prince)
The eventual construction of Redstone Way is a rare case in Western Pennsylvania and actually throughout Pennsylvania of long shelved highway plans coming to life and completion.  Although it is unknown what the original plan for US 40 east of Brownsville was, the stub ends of a highway that would go nowhere for nearly forty years found a new purpose and an ultimate destination.  If you have any background information on what any of the proposed plans for US 40 in Brownsville were to be, please shoot me an email or leave a comment.

Sources & Links:

Comments

FiliumBonus said…
According to the 25 Mar 1975 The Evening Standard (Uniontown PA):

Proposed construction of a four-lane roadway (Route 40) from the Grindstone Rd. to Uniontown has been held up due to an Environmental Impact Statement and changes necessitated by the Brier Hill "new town" project falling through. A public hearing should be held within the next two months but construction is at least three years away. The project includes a 6.9-mile section from the interchange at the Grindstone Rd. to Rocks Works at a cost of $14 million and another section from Rocks Works to the Uniontown by-pass, four miles at an estimated cost of $15 million.

That is the last reference to this project that I can find in local papers.
Adam said…
Thank you so much for the additional information!
Ken Harasty said…
The contractor on the 1968 section from Brownsville's Northside to Grindstone Rd. was the Frank Bozzo Construction Co. of Bridgeville, PA. I worked for them, but not at this job site. My dad and brother worked at the Brownsville location.

Popular posts from this blog

The Dummy Lights of New York

  A relic of the early days of motoring, dummy lights were traffic lights  that  were  placed  in the middle of a street intersection. In those early days, traffic shuffled through busy intersections with the help of a police officer who stood on top of a pedestal. As technology improved and electric traffic signals became commonplace, they were also  originally  positioned on a platform at the center of the intersection. Those traffic signals became known as  " dummy lights "  and were common until  traffic lights were moved  onto wires and poles that crossed above the intersection.  In New York State, only a handful of these dummy lights exist. The dummy lights  are found  in the Hudson Valley towns of Beacon and Croton-on-Hudson, plus there is an ongoing tug of war in Canajoharie in the Mohawk Valley, where their dummy light has been knocked down and replaced a few times. The dummy light in Canajoharie is currently out of commission, but popular demand has caused the dummy

Colorado Road (Fresno County)

Colorado Road is a rural highway located in San Joaquin Valley of western Fresno County.  Colorado Road services the city of San Joaquin in addition the unincorporated communities of Helm and Tranquility.  Colorado Road was constructed between 1910 and 1912 as a frontage road of the Hanford & Summit Lake Railway.  The roadway begins at California State Route 145 near Helm and terminates to the west at James Road in Tranquility.   Part 1; the history of Colorado Road Colorado Road was constructed as frontage road connecting the sidings of the Hanford & Summit Lake Railway.  The Hanford & Summit Lake Railway spanned from South Pacific Railroad West Side Line at Ingle junction southeast to the Coalinga Branch at Armona.  The Hanford & Summit Lake Railway broke ground during August 1910 and was complete by April 1912. The Hanford & Summit Lake Railway established numerous new sidings.  From Ingle the sidings of the line were Tranquility, Graham, San Joaquin, Caldwell, H

Madera County Road 400 and the 1882-1886 Yosemite Stage Road

Madera County Road 400 is an approximately twenty-four-mile roadway following the course of the Fresno River in the Sierra Nevada Mountains.  Road 400 begins at California State Route 145 near Madera and terminates to the north at Road 415 near Coarsegold.  Traditionally Road 400 was known as "River Road" prior to Madera County dropping naming conventions on county highways.  Road 400 was part of the original Yosemite Stage Route by the Washburn Brothers which began in 1882.  The Yosemite Stage Route would be realigned to the west in 1886 along what is now Road 600 to a rail terminus in Raymond.  Parts of Road 400 were realigned in 1974 to make way for the Hensley Lake Reservoir.  Part 1; the history of Madera County Road 400 Road 400 is historically tied to the Wawona Road and Hotel.  The Wawona Hotel is located near the Mariposa Grove in the modern southern extent of Yosemite National Park.   The origins of the Wawona Road are tied to the Wawona Hotel but it does predate th