Skip to main content

Visiting Road Projects in The Neighborhood

Since I've been concentrating efforts to chronicle the building of I-74 in SE NC and the re-signing of the Greensboro Loop over the past year, I have not focused on NCDOT and other road projects basically going on in my back yard. There are three, two if you count by contract number. These are the replacing of bridges along Garrett Road just south of US 15/501. The widening of 15/501 and bridge replacement over the New Hope Creek, and the building of a roundabout at the Durham headquarters for Blue Cross/Blue Shield of NC.

1. Garrett Road Bridge Replacements-This has been going on over the past year. Two temporary bridges and roads connecting them were created so the old bridges could be demolished and new bridges built. The new bridges have opened to traffic over the past few weeks. Here's a look at the construction area heading north on Garrett:
The cleared area on the right was where the temporary road/bridge was located, traffic then went to the left of the other bridge making this part of Garrett more a slalom course than a road.

The trouble with bridge building these days is that they are done with the lowest cost in mind with usually no thoughts of adding distinguishing features:
Is this the first bridge heading northbound or the second? Its the first, but is this also the first?:
The background is the only thing that indicates it's the second. Once they add another asphalt layer this project should be done. As part of the project, they also are re-doing the Garrett Road/15-501 intersection, as this sign warns:
They are demolishing the old intersection of the 15-501 Service Road with Garrett Road and rerouting it behind the Room Store building and back to its old alignment:
This removes traffic delays caused by left turners trying to use the Service Road while cars on Garrett are waiting for a green light, and the many close calls of people driving down 15-501 north not stopping going across Garrett to the Service Road.

2. US 15/501 Widening and Bridge Replacement
As part of the same contract, NCDOT is widening the only remaining 4-lane section of US 15/501 between Garrett and I-40 and replacing the bridge over the New Hope Creek. This is a view of the construction area from 15/501 South:
The southbound lanes have been shifted onto a temporary roadway and bridge while the northbound traffic is using the former southbound lanes while the existing 2-lane northbound bridge is being demolished and replaced with a 3-lane higher span bridge.
This is driving on the temporary southbound lanes past the temporary bridge. The former northbound lanes on the left have been totally demolished and are being expanded and regraded.
The future 3rd southbound lane beyond the jersey barriers for now are currently being used for equipment storage. More progress can be seen heading on 15/501 northbound:
Though hard to see because of the barriers the future third lane is being graded heading down toward the future bridge seen below:
Beyond the crane you can see metal bridge decking is being added to the new bridge and beyond, to help expedite the moving of heavy equipment to the bridge, the road bed has received its first coats of asphalt. The bridge will be higher than the previous one because Durham officials demanded it be constructed to keep an open wildlife corridor along New Hope Creek. Since then they've approved new developments on both sides of the creek making the wildlife corridor even narrower and the bridge design more essential.

3. The Blue Cross/Blue Shield Roundabout
If your a member of BC/BS of NC and wondered where all their surplus money reported in the news has been going, well, at least some has been used at their Durham headquarters. They've built another new building at their University Commons location and, since they're running out of space to place more buildings in that spot, have acquired more office space at the University Place Mall further west on University Drive. So they can keep employee traffic off of University this has led to the construction of a road to connect the two office complexes. The designers felt the intersection of the existing and new roads would be a good place for a roundabout:
This is approaching the roundabout from University Drive a couple blocks west of its intersection with the Martin Luther King Parkway. The new road is off to the right.
The road has not been completed yet. Sidewalks were put in last week. This week could see the first asphalt being placed on the roadbed. The buildings of University Place can be seen at the top right. The roundabout has been open for about two months with only the original road using it.
This is looking at the roundabout from the completed end of the new road which, as of now, does not have a name, just a road sign saying 'To University Place' and an arrow. Beyond is one of the new buildings put up in the last two years. The last photo is the view going west and coming from the University Commons shopping center and my Harris Teeter:
My next entry will be photos taken along the path of the future Triangle Parkway.

Comments

Popular posts from this blog

North Carolina Continues to Move Forward with Rail

2023 and the first half of 2024 have seen continued growth in North Carolina's passenger rail system.  From increased daily trains from Raleigh to Charlotte, federal funds for studying additional corridors, and receiving a historic grant to begin the construction of high-speed rail between Raleigh and Richmond, the last 18 months have been a flurry of activity at NCDOT's Rail Division.  And that's just the tip of the iceberg. As ridership and routes increase - the engine of North Carolina passenger rail trains will become a more common sight. (Adam Prince) Increased Passenger Train Service: On July 10, 2023, a fourth Piedmont round-trip rail service between Raleigh and Charlotte commenced.  The four Piedmont trains plus the daily Carolinian (to Washington, DC, and New York) bring the total of trains serving the two cities daily to five. The current daily Piedmont and Carolinian schedule between Charlotte and Raleigh (NCDOT) The result was over 641,000 passengers utilized pa

US Route 101 in Benbow, Garberville and Redway

The communities of Benbow, Garberville and Redway can all be found along US Route 101 within southern Humboldt County.  The former surface alignment of US Route 101 in Garberville and Redway once crossed the Garberville Bluffs along what is now Redwood Drive via a corridor constructed as part of the Redwood Highway during the 1910s.  US Route 101 through Benbow, Garberville and Redway was modernized by 1935.  US Route 101 would eventually be upgraded to freeway standards in Benbow, Garberville and Redway by extension of the Redwood Freeway during 1966-68.  As the cover photo the original grade of US Route 101 and the Redwood Highway can be seen at the Garberville Bluffs during 1934.  US Route 101 can be seen in the communities of Benbow, Garberville and Redway on the 1935 Division of Highways Map of Humboldt County .   The history of US Route 101 in Benbow, Garberville and Redway Benbow, Garberville and Redway lie on the banks of the South Fork Eel River of southern Humboldt County.  D

The Midway Palm and Pine of US Route 99

Along modern day California State Route 99 south of Avenue 11 just outside the City limits of Madera one can find the Midway Palm and Pine in the center median of the freeway.  The Midway Palm and Pine denotes the halfway point between the Mexican Border and Oregon State Line on what was US Route 99.  The Midway Palm is intended to represent Southern California whereas the Midway Pine is intended to represent Northern California.  Pictured above the Midway Palm and Pine can be seen from the northbound lanes of the California State Route 99 Freeway.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page The history of the Midway Palm and Pine The true timeframe for when the Midway Palm and Pine (originally a Deadora Cedar Tree) were planted is unknown.  In fact, the origin of the Midway Palm and Pine w