Unless you are native to the mountains of Western North Carolina, the incomplete North Shore Road around Fontana Lake is easily overlooked and forgotten.  But to a number of the descendants of families displaced from the creation of the lake, it is a daily reminder of broken promises and years of legal battles over their former land.
 
The story of the North Shore Road begins in the early 1940's when Congress appropriated funding for the building of Fontana Dam by the Tennessee Valley Authority (TVA).  The damming of the Little Tennessee River created what is now known as Fontana Lake.  The 11,685 acre lake would displace over 1300 families in addition to submerging many parts of NC Highway 288, an unpaved road that ran from Bryson City to Deals Gap. (1)  In addition, the lake left nearly 44,000 acres of land between it and what was then the boundary of Great Smoky Mountain National Park. 
 
With the National Park Service wanting to include the 44,000 acres into GSMNP and the TVA claiming the cost to replace NC 288 as being to high, an agreement between the two government agencies and the State of North Carolina along with Swain County was met in 1943.  The agreement would allow the National Park Service to purchase the 44,000 acres at an average cost of $37.76 per acre (1).  In addition, the NPS was to build a replacement for NC 288 along the northern shore of the newly created lake.  The road would be built as Congress allocated money to the project.  In addition, a clause stating “failure on the part of Congress for any reason to make such appropriations shall not constitute a breach or violation of this agreement.” was included. (1)  The level of compensation for their land still angers the families and descendants of those displaced to this day.
 
Not long after the 1943 agreement was signed, the first of six decades of lawsuits (from landowners to environmental groups) were filed.  Six property owners filed suit to keep their land.  Their argument was that because none of their land would become part of the man-made lake; the government did not need their land.  After local and district courts sided with the property owners, a 1946 U.S. Supreme Court decision reversed the lower courts' rulings and the government was now legally permitted to seize the land.  By that Spring, all of the former families in the area affected by the creation of Fontana lake and the expansion of GSMNP had moved from the area.
 
After the conclusion of the World War II, some money was allocated to the construction of the North Shore Road.  A one mile section at Fontana Dam would be built.  In 1958, the State of North Carolina builds three miles of the North Shore Road outside of the park's boundary.  In 1960, the first construction of the road within the park in over a decade would begin.  The 2.3 mile project was near completion when a landslide would expose the environmental and cost concerns in building the highway.  Located within a 1962 report of a National Park Service committee that was in charge of inspection of the roadway's construction had this ominous quote "The committee is of the opinion that continuation of  such damage to natural park values is indefensible from either the standpoint of conservation or visitor use." (2)
 
While another four miles of the road would be built between 1962 and 1970, the concerns over the roadway's effect on the environment became center issue.  Anakeesta rock, which are rocks that when exposed to the elements release a mild sulfuric acid (3), was found during construction of the highway.  It was first noticed when snowfall instantly melted on exposed rock and produced a strong sulfur odor. (4)  The environmental concerns over the Anakeesta is that the acid that is leaked through rainfall would enter nearby streams and damage plants, fish, and other wildlife.
 
The addition of nearly four miles of the North Shore Road (known within the park as Lake View Road) in 1970 would be the last new portion of highway built to this day.  This segment includes a tunnel which is the current end of the highway. 
 
Since 1970, the question over whether or not to build the North Shore Road has become an almost annual discussion in Western NC and on Capitol Hill.  After years of congressional hearings, failed motions, and other legal battles, the North Shore Road project in 2000 received $16 million in federal funding towards building the highway.  The money thus far has been used for studies in determining the eventual final outcome of the project.
 
Over the past two decades, the debate over the North Shore Road concerns three groups - the families and their descendants that want to see the road built, "A promise made is a promise kept.", environmental groups that do not want to see any more of the road built, and Swain County Commissioners that would like to see a cash settlement to improve the finances of the county.  For years, politicians from the local, state, and national levels would offer a compromise funding proposal to the residents displaced by Lake Fontana and to Swain County.  It wasn't until 2010 when North Carolina Congressman Heath Shuler put together a settlement that would pay Swain County $52 million. (5)  The settlement officially ended the saga of the North Shore Road.

All photos taken by Lyndon Young in 2007.

The furthest you can travel on the North Shore Road.  From this point forward, you can only travel by foot or by bike
The tunnel is just beyond the barricade.

Exiting the tunnel, the road does continue a bit further...

...until this point.  This is the absolute end of the highway that was built in 1970.  Fontana Lake is on the left.

Approaching the tunnel as you head back to the parking area from the road's end.

Exiting the tunnel and returning to the parking area.

  • (1) Ball, Julie.  "Pave or preserve?" Asheville Citizen-Times.
  • (2) National Park Service. "Report of the Technical Committee for the Inspection of the Bryson-Fontana Road Construction, Great Smoky Mountains." (April 12, 1962).
  • (3) "What is Anakeesta Rock?" Asheville Citizen-Times.
  • (4) "The Road to Nowhere." I.Q. The Science, Nature, Technology and the World Around Us Show. UNC-TV. 1996.
  • (5) Williams, Margaret. "Settlement for North Shore Road will bring $52 million to Swain County." Asheville Mount-Express.
  • Lyndon Young
  • Asheville Citizen Times Series - North Shore: The Road To Nowhere.
  • North Shore Road Project Site ---National Park Service
  • North Shore Road Impacts ---Appalachian Trail Conservancy
  • NC 288, Fontana Dam, and the Road to Nowhere ---Joe Kegley, Wildlife South
  • 1943 North Shore Road Association
  • North Shore Road Points ---Southern Appalachian Forest Coalition
  • North Shore Road ---Taxpayers for Common Sense
  • North Shore Road ---Western NC Attractions
  • NC 288 @ NCRoads.com Annex ---Mike Roberson
  •  

    Comments

    Popular posts from this blog

    Paper Highways: The Unbuilt New Orleans Bypass (Proposed I-410)

      There are many examples around the United States of proposed freeway corridors in urban areas that never saw the light of day for one reason or another. They all fall somewhere in between the little-known and the infamous and from the mundane to the spectacular. One of the more obscure and interesting examples of such a project is the short-lived idea to construct a southern beltway for the New Orleans metropolitan area in the 1960s and 70s. Greater New Orleans and its surrounding area grew rapidly in the years after World War II, as suburban sprawl encroached on the historically rural downriver parishes around the city. In response to the development of the region’s Westbank and the emergence of communities in St. Charles and St. John the Baptist Parishes as viable suburban communities during this period, regional planners began to consider concepts for new infrastructure projects to serve this growing population.  The idea for a circular freeway around the southern perimeter of t

    Hernando de Soto Bridge (Memphis, TN)

    The newest of the bridges that span the lower Mississippi River at Memphis, the Hernando de Soto Bridge was completed in 1973 and carries Interstate 40 between downtown Memphis and West Memphis, AR. The bridge’s signature M-shaped superstructure makes it an instantly recognizable landmark in the city and one of the most visually unique bridges on the Mississippi River. As early as 1953, Memphis city planners recommended the construction of a second highway bridge across the Mississippi River to connect the city with West Memphis, AR. The Memphis & Arkansas Bridge had been completed only four years earlier a couple miles downriver from downtown, however it was expected that long-term growth in the metro area would warrant the construction of an additional bridge, the fourth crossing of the Mississippi River to be built at Memphis, in the not-too-distant future. Unlike the previous three Mississippi River bridges to be built the city, the location chosen for this bridge was about two

    Memphis & Arkansas Bridge (Memphis, TN)

      Like the expansion of the railroads the previous century, the modernization of the country’s highway infrastructure in the early and mid 20th Century required the construction of new landmark bridges along the lower Mississippi River (and nation-wide for that matter) that would facilitate the expected growth in overall traffic demand in ensuing decades. While this new movement had been anticipated to some extent in the Memphis area with the design of the Harahan Bridge, neither it nor its neighbor the older Frisco Bridge were capable of accommodating the sharp rise in the popularity and demand of the automobile as a mode of cross-river transportation during the Great Depression. As was the case 30 years prior, the solution in the 1940s was to construct a new bridge in the same general location as its predecessors, only this time the bridge would be the first built exclusively for vehicle traffic. This bridge, the Memphis & Arkansas Bridge, was completed in 1949 and was the third