Skip to main content

April I-74/US 311 Freeway Progress Report

Apparently not having seen enough construction on Saturday, I traveled to Winston-Salem and back to check on the progress of building the US 74/US 311 freeways near High Point.

1. High Point 'East Belt'
A. Open Portion
Why did I start in Winston-Salem. Part of the contract for building the 'East Belt' portion of I-74 (from now former Business 311 to I-85) calls for updating signs to include I-74 (the plans indicated full interstate, but it may now be Future) and the placing of I-74 mile markers along the already opened portion of the road to Business 85. I was checking to see if there were any indications this was happening, which would mean the route is closer to opening than NCDOT has announced, by the end of the year. The only change on the existing road I could find though were to the overhead signs at the now former Business 311 interchange heading east (Exit 65). Both signs, except for the exit tab, had been removed:
The sign on the left read 'To NC 68'. It turns out though that these signs were blown down a tornado that passed over a week or so before. Thus NCDOT will have to decide to replace them as they were or replace them by updated signs, such as an East I-74/South US 311 sign with control cities at some future point. The Exit 65 sign before this one, since the removal above was not due to NCDOT, at 1 mile had not been replaced and still referred to Business 311.

B. Under Construction Portion from Business to Interstate 85
Baker Road Bridge-As my last post indicated the bridge had been opened but there was no progress on removing the temporary highway to the north. Well, there has been some progress in the last month:
The pavement has been removed and digging has begun to bring the road down to grade, which has been done just to the north of the bridge. There has been substantial progress south of the bridge, where much of the grading and landscaping needed has been done:
The paved portion where the road curves continues eastbound to the Jackson Lake Road bridge.
Looking from Jackson Lake Road, most of the dirt from the former hill in the westbound lanes has been pushed up the embankment on the right and is being prepared for final landscaping. Looking eastbound toward Kersey Valley Road, it appears most of the work is complete:
Guardrails and drain covers are still needed, but most of the landscaping is done. Here is how the Kersey Valley Road bridge looks from the south:
The roadways appear graded and they have started initial paving toward I-85 along the future eastbound lanes shown on the left side of the photo in the middle. This is a better view of what progress has been made:
They've tied the new pavement on the EB I-85 ramp to the existing pavement. Landscaping though and more paving has to be completed here. The view of the I-85 bridges also shows progress in the last month:
Grading appears almost complete and the asphalt layer in the eastbound lanes continues almost to the bridges. The contractor has been closing lanes and ramps on I-85 in this area for the past 2 weeks to put new lane striping on I-85, for paving the NC 62 exit ramps, and for putting up overhead sign supports:
Whether this means the re-opening of the main I-85 lanes is imminent is not known, the NCDOT construction progress report still says this will happen in June. Work on the exit ramps continues...
The flyover ramp from I-74 East to I-85 North above looks complete, however, it doesn't appear paving has been completed on the section of the ramp from the bridge over I-85 to the flyover ramp...
Presumably, guardrails will be added when the paving project is completed.

2. '311 Bypass' I-85 to US 220
A. First Phase portion-This part of the freeway is being built at the same time by the people doing the remaining East Belt construction. The roadbed near the I-85 interchange appears mostly complete:
Most of the work in this section over the past month seems to be concentrated on the placing of a final asphalt layer on the roads that cross the future freeway. The paving and lane striping of Tuttle Road across its bridge has been finished:
Similar work has been done along Poole Road and on Cedar Square Road. The final non-highway bridge that needed construction has been completed, as can be seen in this photo from the Poole Road bridge:
As can be seen though, little or no further work on paving the freeway has occurred either to the north or south of the bridge:
Approaching Cedar Square Road, Poole Road parallels the freeway on the right. There was progress in re-doing Poole Road where it met the former alignment of Cedar Square Road, the road now curves off to the left on a new alignment. The photo of the Cedar Square Road Bridge below is taken where Poole Road now curves toward Cedar Square:
Work has been done on grading the route where the old alignment of Cedar Square was torn down. There, has not been much work on the interchange ramps, however:
Both Cedar Square Road and current US 311 from just south of the intersection below to just north of the former Cedar Square intersection have received their final coat of asphalt:
The water tower in the background is either being replaced or augmented by a new bigger water tower further south on US 311 which has a big 'Welcome to High Point' logo on it. I suppose they hope people will see it from the new freeway.

B. Phase 2
The second phase of construction runs from Spencer Road, 1/2 mile south of Cedar Square, to US 220. This is a design-build contract where work started in late 2008. The major feature of this segment will be an interchange with current US 311 in Sophia and the interchange where I-74 will tie into I-73 (US 220) near Randleman. There is little more than clearing going on at the Sophia interchange so far:
Most of the clearing seems to have been done, seen from US 311 South, the crane indicates the start of some infrastructure construction. There are more interesting things to see on US 220:
Traveling southbound, they are now putting structures in for the I-74 bridges on the right side, the first one is mostly metal and will lead to the I-74 west lanes that are being graded in the vicinity. The second structure is mostly cement and this will take traffic from I-74 east to I-73 north:
This will be a lower bridge, the ramp to I-74 west will be a flyover and go both over US 220 and the other bridge. This requires building a large mound along northbound US 220 for the ramp to the flyover, seen below from the southbound lanes:
One can barely see the top of the future ramp when traveling along in the northbound lanes:
Here's a wider view of the construction scene as viewed going northbound on US 220:
The first phase and East-Belt construction are 86% complete as of the end of March according to NCDOT, the contractors having completed over 3 1/2% of the remaining construction during the month. At this pace the route from Business 85 to Cedar Square Road could be done by the end of July. I will return sometime in May to see if this prediction is still possible.

Comments

Anonymous said…
Signs for 311/Main St in High Point were blown down in last week's tornado. It should be interesting to see what they are replaced with.
Bob Malme said…
Thanks for the information. I have revised the comment regarding the missing Exit 65 signs in light of the new information.

Popular posts from this blog

Rep. Sue Myrick's letter to Gov. Easley and Sect. Tippett published in Charlotte Observer

US. Representative Sue Myrick's (R-Charlotte) letter to North Carolina's Governor Mike Easley and NC Transportation Secretary Lyndo Tippett was published in the Friday, November 30th edition of the Charlotte Observer . Why are we delaying the completion of 1-485 in Charlotte again? I read in The Charlotte Observer how rising prices of materials are leading to the delay. Why didn't these same rising costs delay the loops in Fayetteville and Wilmington? Why are we building loops in Fayetteville and Wilmington before we complete the one in Charlotte? We were working on the one in Charlotte back when I was mayor. That was 20 years ago! ... Last I looked Charlotte was the largest city in the state. There seems to be no recognition of that fact in Raleigh. No recognition that we are at a standstill with traffic. No recognition that we have a traffic problem. Nor is there any recognition of the fact that the state DOT utterly botched up the southern leg of our yet to be completed ...

New River Gorge National Park & Preserve - Sandstone Falls

The New River, which runs through New River Gorge National Park & Preserve, is best known for its dramatic rapids and whitewater adventures.  Those features begin at one of the river's widest points: Sandstone Falls. From the Sandstone Falls Boardwalk a look at just a small part of the falls. Though the vertical drop of roughly 20 feet is less than many other well-known waterfalls in the state, the falls' expanse, where the river approaches 1500 feet wide, makes Sandstone Falls impressive.   The Boardwalk Trail leads to a better vantage point of the overall falls. It is a great spot for photography, fishing, or laying out in the sun. Access to the falls is relatively easy: from Hinton, cross the New River on Highway 20, then turn right onto CR 26 and follow New River Road to the Sandstone Falls Parking Area. The Island Loop Trail is a short detour off the Boardwalk Trail and shows a quieter side of the area. At Sandstone Falls, you will find a variety of activities fr...

I-90 in Albany, New York and the Berkshire Spur

Today's Albany Times Union has a segment in their weekly Getting There? column that explains some of the history behind how I-90 is designated in the Albany, NY area as well as the Berkshire Spur. The long and short of the article was that I-90 was originally designated on the unsigned portion of the Berkshire Spur, but as free I-90 was built, the designation was moved onto the free portion of road. Additionally, there were talks in 1999 between state and federal officials about the possibility of moving I-90 back onto the unsigned portion of the Berkshire Spur, while extending I-88 onto what we know as free I-90. There would have also had been an I-88/I-90 multiplex between Rotterdam and Albany as a result. http://www.timesunion.com/AspStories/story.asp?storyID=916307