Skip to main content

Alaskan Way Viaduct Legacy Part 3; the Alaskan Way Viaduct replacement tunnel


Following the 2001 Nisqually Earthquake the Alaskan Way Viaduct was determined to be in need of replacement due to it not meeting seismic standards.  Ultimately a double-deck tunnel bore structure was selected as a replacement after years of debate in the many political circles in the city of Seattle.  Construction of so-called Alaskan Way Viaduct replacement tunnel began via boring operations during Summer 2013 through Spring 2017.  The completed tolled tunnel would open as the then new alignment of Washington State Route 99 during February 2019.

Part 3 of the Alaskan Way Viaduct Legacy series covers the history of the tunnel which replaced it.  The blog cover photo is from the Alaskan Way Viaduct replacement tunnel approaching the south portal near Royal Brougham Way. 


This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and its three-digit child routes check out the link the below.



Part 1 of the Alaskan Way Viaduct Legacy series featured the history of Railroad Avenue:


Part 2 of the Alaskan Way Viaduct Legacy series features the history of the Alaskan Way Viaduct and alignments of US Route 99 in downtown Seattle:




Part 3A; the Alaskan Way Viaduct replacement tunnel

Following the 2001 Nisqually Earthquake five options regarding the Alaskan Way Viaduct were considered.  All options included rebuilding the seawall along Alaskan Way to mitigate potential liquefaction during a major earthquake:

1. A rebuild of the existing configuration.
2. A new aerial design.
3. A single-level tunnel and a single-level aerial structure with two bored tunnels under Broad Street to Aurora Avenue.
4. A stacked cut-and-cover tunnel with ramps to downtown and a tunnel under Broad Street.
5. A stacked cut-and-cover tunnel with ramps to downtown and a bored tunnel under Belltown.

Initially only the rebuild and aerial options remained after assessment due to being cost effective.  Ultimately five new corridor options were developed which emphasized maintaining the traffic flow of the Alaskan Way Viaduct and mitigate potential earthquake hazards.  An Environmental Impact Report conducted during March 2004 studied the following options:

1. A six-lane, side-by-side, cut-and-cover tunnel with an aerial connection to the Battery Street Tunnel.
2. An aerial structure with improvements along Aurora Avenue north of the Battery Street Tunnel.
3. A four-lane, side-by-side, cut-and-cover tunnel with Aurora Avenue improvements.
4. A new waterfront street with an aerial structure connecting it with the Battery Street Tunnel.
5. A rebuild of the existing structure. 

Following the 2004 Environmental Impact Report debate over a "no viaduct" and "no tunnel" option was considered.  This option was largely dismissed due to the negative impacts it would have on increased traffic in downtown Seattle.  Ultimately during January 2005, the Seattle city council would adopt a resolution favoring replacing the Alaskan Way Viaduct with a tunnel.  This resolution was followed up in March 2006 with a Supplemental Draft Environmental Impact Statement regarding a cut and cover tunnel. 

Debate would persist over a tunnel structure would be four or six lanes.  This led to three new projects options being proposed during December 2008:

1. Turn Alaskan Way and Western Avenue into one-way couplets.  This option included adding dedicated RapidRide bus lanes.  
2. Two two-lane elevated viaduct structures with ramps to Railroad Way and Elliott Avenue.
3. A four-lane tunnel with no exits into downtown along with transit options. 

During 2009 then Seattle Mayor Mike McGinn vetoed a city council resolution which concurred with a State of Washington decision favoring a tunnel option.  The city council was ultimately able to override the veto on February 28, 2011.  During August 2011 the Federal Highway Administration issued a record of decision approving a tolled Deep Bore Tunnel alternative. 

Work on the so-called Alaskan Way Viaduct replacement tunnel began on July 30, 2013.  A tunnel bore machine nick-named "Bertha" was sourced from Hitachi Zosen.  The machine initially only worked until December 6, 2013, due to unexpected damage caused by striking a pipe which had been missed in a survey.  The damage was severe enough that a recovery pit had to be dug to lift the cutterhead for repairs.  

Tunnel bore operations resumed on December 22, 2015.  Work halted in again during winter 2016 due to a sinkhole opening related to a shipping incident in Elliott Bay.  Tunnel boring operations were finally complete on April 4, 2017.  The tunnel bore measured at a length of 9,270 feet. 

A completed segment of the Alaskan Way Viaduct replacement tunnel wall can be seen in a Seattle city council photo dated January 4, 2017.   The boring machine was fully dissembled and removed by August 2017.  


The northbound lanes of the Alaskan Way Viaduct replacement tunnel opened at 11 PM on February 3, 2019.  The southbound lanes opened at 12:15 AM on February 4, 2019.  The project ultimately incurred approximately $223,000,000 in cost overrides.  Tolling did not begin until November 9, 2019.  The initial toll rate for two-axle vehicles was $1.20-$2.70 for Good to Go transponder users and $3.20-$4.70 for pay-by-mail users.  

This graphic depicts the two-level structure of the Alaskan Way Viaduct replacement tunnel.  To-date the tunnel has no designated name and is generally referred to as the "State Route 99 Tunnel" in Washington State Department of Transportation documents. 


Demolition of the Alaskan Way Viaduct began on February 15, 2019.  The partially demolished structure can be seen in the vicinity of Columbia Street during April 2019 (source SounderBruce). 


Demolition of the Alaskan Way Viaduct was completed on November 21, 2019.  The debris from the viaduct were used to backfill the now redundant Battery Street Tunnel.  The so-called Overlook Walk was installed as a Seattle Waterfront park above Alaskan Way during 2021. 



Part 3B; a drive through the Alaskan Way Viaduct replacement tunnel

This Washington State Department of Transportation graphic depicts the current alignment of Washington State Route 99 through the Alaskan Way Viaduct replacement tunnel.


Traffic on southbound Washington State Route 99 along Aurora Avenue is now advised of the tolled nature of the Alaskan Way Viaduct replacement tunnel.  Denny Way is signed as the last exit before tolls.  Hazardous cargo is required exit onto Denny Way and not enter the tunnel. 









There are no exits in the Alaskan Way Viaduct replacement tunnel.  Southbound traffic can exit onto Royal Brougham Way towards Lumen Field and T-Mobile Park after emerging from the tunnel.  The current toll rates are displayed upon exiting the south tunnel portal. 






















Part 3C; the Overlook Walk above Alaskan Way

These photos were taken from the Overlook Walk during July 2025 by Gribblenation's Tom.  This first photo faces south down Alaskan Way.


This view faces north along Elliott Way towards where the Alaskan Way Viaduct once entered the Battery Street Tunnel.  The Battery Street Tunnel portal is now blocked as it has been filled with debris from the viaduct structure.  


Comments

Popular posts from this blog

West Canyon Road (Snow Canyon State Park)

West Canyon Road is an approximately four-mile dirt service road located in Snow Canyon State Park.  West Canyon Road follows Snow Canyon from the Whiptail Trail to the northern State Park boundary and intersects numerous trailheads.   West Canyon Road was the original main road through Snow Canyon after it was designated as a Utah State Park in 1957 and opened to the public in 1962. Part 1; the history of West Canyon Road Snow Canyon is located in the Red Mountains north of the city of Ivins in Washington County, Utah.  Snow Canyon is one of many sandstone canyons located in the Red Mountains.  Part of the extinct Santa Clara Volcano punctured the Red Mountains via lava tubes. From approximately the year 200 to 1,250 the area around Snow Canyon was inhabited by the Ancestral Puebloans.  Mormon pioneers established Santa Clara south of Snow Canyon in 1854.  Local legend has it that the settlers discovered Snow Canyon in the 1850s while searching for m...

Indian Gulch Extension and the Indian Gulch ghost town site

Indian Gulch Extension is an approximately 6-mile-long rural highway corridor in the Sierra Nevada foothills of western Mariposa County.  Indian Gulch Extension begins at Indian Gulch Road near the namesake ghost town of Indian Gulch.  From the ghost town site Indian Gulch Extension extends southwesterly to the Merced County line where it becomes Waltz Road.   The former Gold Rush era community of Indian Gulch which was settled near Santa Cruz Mountain in 1849 and had standing structures until the early 1970s.  What is now Indian Gulch Extension was approved for construction by the Mariposa County Commissioners in 1862.  The purpose of the corridor was to provide Indian Gulch with a direct connection westward with the greater Stockton-Los Angeles Road.  The Stockton-Los Angeles Road would go onto define much of the Mariposa County and Merced County line.  Part 1; the history of Indian Gulch and Indian Gulch Extension Indian Gulch Road is named aft...

The alignment history of US Route 50 in Dayton, Nevada

Dayton is located in Lyon County and is the second oldest community in Nevada having been founded near mining claims in Gold Canyon circa 1850.  The community of Dayton historically has been part of the California Trail, Pony Express and Pioneer Route of the Lincoln Highway.  Since November 1926 the community has been served by US Route 50.  Originally US Route 50 passed through Dayton along what is now Old US Route 50, Pike Street, Main Street, River Street and Daney Canyon.  Modernization of US Route 50 would begin during the early 1930s when Daney Canyon was bypassed and would continue into the 1940s Federal Aid Program era when the downtown bypass was developed.  This blog will serve as history of US Route 50 in Dayton and exploration of the original alignment in the community.   US Route 50 can be seen below bypassing downtown Dayton on the 1956 United States Geological Survey map. Part 1; the history of US Route 50 in Dayton Dayton is the second ...