Skip to main content

Final(?) I-74/US 311 High Point East Belt Progress Report

NCDOT's Construction Progress Report produced a new estimate of completion for the I-74/US 311 freeway between Business 85 and Cedar Square Road on September 20, about 10 days earlier than usual. The report indicated the project was 94.2% complete. Assuming, even with the rainy weather, that this completion percentage was approaching 95% by the first Sunday in October, I took, what I hoped would be, a final trip to the corridor to confirm progress on building the freeway hoping it appeared almost completed (and hopefully to be opened before November, more on that later). What I found was most of the work on the road itself had been completed, with a few exceptions, all that's left to do is some final landscaping, placing covers on the remaining open median water drains, the placement of signs, both overhead and at ground level, and the putting down of lane markings (much of which had been preliminarily marked along the roadway). Here's a summary heading west to east or north to south, depending on whether you prefer to use I-74 or US 311 cardinal directions.

A. The Business 85 interchange
The ramps and roadway leading from the open freeway up to Baker Road have largely been cleaned off, though no interchange signage or lane markings have appeared. Here's the view for where traffic must exit now esatbound:
Here's the view looking at the future on ramp to I-74 East from the 'volleyball interchange'. They still need to work on the traffic signals and clean the roadway near the intersection:
B. Baker Road
The final coat of asphalt for Baker Road has still not been placed, but the landscaping around the bridge appears complete:
Looking southward, one can see the roadway is almost complete with a few landscaping and drain cover issues still needing to be addressed:
A closer look at the westbound roadway reveals an initial marking of where the shoulder and lane markings will be placed:
Note there is nothing for the left shoulder, this is the case on most of the freeway that's marked, though in some areas only the left and right shoulders are indicated.

C. Jackson Lake Road
This area appears near completion, sign structures are up and lanes are marked for striping, some landscaping and drainage covers still need work, both looking west/north:
And south/east toward Kersey Valley Road:
D. Kersey Valley Road
A similar story can be said here. More sign structures have been put up, but the recent rain hasn't helped with the large hill landscaping. First here's a view of the bridge:
A few more posts for the guardrails also need to be installed, after the construction road is no longer needed. Here's a similar view but including the signage structure for the future 2 mile advance sign for the Business 85 exit:
Notice also completion of the median guide wires. Here's the landscaping problem I mentioned:
While the drainage system seems to have worked well, most of the top soil put on the embankment has washed away, and will need to be replaced.

E. I-85 Interchange
The interchange as seen from Dresden Road appears completed, or close to being so:
A truck ramp to the eastbound exit off ramp will have to be closed. Meanwhile an overhead sign structure at the splitting of the I-85 north (flyover) and south ramps has been put up. On I-85 itself all the signage has been put up with the I-74/US 311 signs remaining covered:
The covered sign marks one mile before the beginning of the I-74 interchange C/D ramps. Below is the final sign covered over at the beginning of the C/D ramps northbound:
Photo taken from the NC 62 off ramp. There have been no additional signs or sign posts put up yet at the I-85 north on ramp from NC 62 which uses the C/D lanes.

F. NC 62 and Tuttle Road
With the exception of markings demarking future traffic lanes, nothing new was seen at these locations, both seemingly near completion. The landscaping has filled in nicely as seen from both directions on the Tuttle Road Bridge. First, north:
yes, those are bikers heading southbound, and looking to the south:
Hard, to spot but you can see median guide wires have been placed here as well. The sign structure seen last month around the corner is still the last one along the freeway heading south.

F. Poole Road
The only change is the completion of the bridge over a creek to the north, it also looks like they repaved this section:
Landscaping also may still be an issue to the north of these bridges. Looking south from the Poole Road bridge shows a scene similar to last month, no pavement markings, or sign structures for the Cedar Square exit seen here, though more guardrails have been installed:
Looking along the freeway that parallels Poole Road, the only real change is the absence of machinery:
The truck access route from Poole has been closed, so trucks are using the median to turn around to get off the freeway at the Cedar Square interchange.

G. Cedar Square Road Interchange (Temporary End of Freeway)
There has been progress in placing final pavement down for the sections that will be opened to traffic, though as stated before, no signage structures have been put up, nor evidence of signage along Cedar Square at the future I-74 west interchange. Here's a view of the on ramp from the end of Poole Road:
The on ramp is straight ahead. The future off ramp from I-74 East, not paved beyond the cement median, is to the left. Here's a view of the progress in constructing the eastbound off ramp which all traffic will use until late 2012:
Notice they are still working on landscaping and containing water runoff before the ramp. The view of the ramp from Cedar Square Road shows further need for landscaping:
Not to mention replacement of traffic barrels. The view from Poole Road looking south toward the bridge shows the extent of progress in paving the ramps and future westbound I-74 roadway:
While a view from the bridge looking southward, shows the progress of the westbound offramp and the unpaved sections which are now the responsibility of the Poole Rd to US 220 contractor:
A view from the future Eastbound on ramp shows the extent of the ramp and borrow pit construction:
Yes, those are the same bikers again. The official opening date for this segment is still November. Hopefully, though the weather will cooperate, especially when it comes to placing the line markings down. I am moving back to my native Massachusetts at the end of October and it would figure that NCDOT would wait until a couple days into November before opening the road. Especially after all the effort I've made in pointing out their mistakes.

I took photos along the next section of construction from Spencer Road to US 220 and will put those up on another post. I'll certainly have to return someday to take a ride after that section's open. Meanwhile, if there are any others interested in following the progress of the final section of the 311 Bypass, feel free to take rod trips to document it.

Comments

Bob Malme said…
According to the news article here:
http://www.hpe.com/view/full_story/9746266/article-Work-progresses-on-U-S--311?instance=main_article
NCDOT hopes to open this segment of I-74 by Thanksgiving. Given the photos showing major completion and dry weather forecast for the next week, hopefully they can finish earlier.
Commuter Joe said…
Fascinating coverage, thank you.

Popular posts from this blog

Old River Lock & Control Structure (Lettsworth, LA)

  The Old River Control Structure (ORCS) and its connecting satellite facilities combine to form one of the most impressive flood control complexes in North America. Located along the west bank of the Mississippi River near the confluence with the Red River and Atchafalaya River nearby, this structure system was fundamentally made possible by the Flood Control Act of 1928 that was passed by the United States Congress in the aftermath of the Great Mississippi River Flood of 1927 however a second, less obvious motivation influenced the construction here. The Mississippi River’s channel has gradually elongated and meandered in the area over the centuries, creating new oxbows and sandbars that made navigation of the river challenging and time-consuming through the steamboat era of the 1800s. This treacherous area of the river known as “Turnbull’s Bend” was where the mouth of the Red River was located that the upriver end of the bend and the Atchafalaya River, then effectively an outflow

Interstate 10S and the original Interstate 110 in California

Interstate 10S is a short spur of Interstate 10 along San Bernardino Freeway in downtown Los Angeles.  Interstate 10S begins at the Santa Ana Freeway (US Route 101) and extends east to Interstate 5 where it merges into mainline Interstate 10.  Interstate 10S is one of the oldest freeway segments in Los Angeles having been part of US Routes 60, 70 and 99 when it was part of the corridor of the Ramona Expressway.  The current corridor of Interstate 10S was assigned as Chargeable Corridor H following the passage of the 1956 Federal Highway Aid Act.  Interstate 110 was a short-lived designation which comprised the segment San Bernardino Freeway from US Route 101 to Interstate 5 between 1964-1968.  The original Interstate 110 was dropped as a Chargeable Corridor during 1965 and consolidated as Interstate 10S during 1968.   The original Interstate 110 can be seen as the blog cover photo as it was featured on the 1964 Division of Highways Map.  Below the entire 0.65-mile length of Interstate

Vicksburg Bridge (Vicksburg, MS)

  Located a few hundred feet downriver from the Old Vicksburg Bridge, the Vicksburg Bridge, or the “New” Bridge, serves as the city’s vehicular crossing of the Mississippi River on the main highway connecting Vicksburg with northeastern Louisiana to the west and the state capital of Jackson to the east. The completion of the original Vicksburg Bridge in 1930 was seen as a huge success and the bridge proved to be a profitable entity for both road and railroad interests along the path of the Dixie Overland Highway and the subsequent US Highway 80 corridor. In the years after the creation of the National Interstate Highway System, planning commenced on a new bridge at the site that would relieve the congestion on the existing bridge while providing for a more modern crossing of the river that would be safe for all vehicles. The construction of the new bridge at Vicksburg was completed in 1973 and its design intentionally mimics that of its predecessor nearby. This was due in large part