Skip to main content

Final(?) I-74/US 311 High Point East Belt Progress Report

NCDOT's Construction Progress Report produced a new estimate of completion for the I-74/US 311 freeway between Business 85 and Cedar Square Road on September 20, about 10 days earlier than usual. The report indicated the project was 94.2% complete. Assuming, even with the rainy weather, that this completion percentage was approaching 95% by the first Sunday in October, I took, what I hoped would be, a final trip to the corridor to confirm progress on building the freeway hoping it appeared almost completed (and hopefully to be opened before November, more on that later). What I found was most of the work on the road itself had been completed, with a few exceptions, all that's left to do is some final landscaping, placing covers on the remaining open median water drains, the placement of signs, both overhead and at ground level, and the putting down of lane markings (much of which had been preliminarily marked along the roadway). Here's a summary heading west to east or north to south, depending on whether you prefer to use I-74 or US 311 cardinal directions.

A. The Business 85 interchange
The ramps and roadway leading from the open freeway up to Baker Road have largely been cleaned off, though no interchange signage or lane markings have appeared. Here's the view for where traffic must exit now esatbound:
Here's the view looking at the future on ramp to I-74 East from the 'volleyball interchange'. They still need to work on the traffic signals and clean the roadway near the intersection:
B. Baker Road
The final coat of asphalt for Baker Road has still not been placed, but the landscaping around the bridge appears complete:
Looking southward, one can see the roadway is almost complete with a few landscaping and drain cover issues still needing to be addressed:
A closer look at the westbound roadway reveals an initial marking of where the shoulder and lane markings will be placed:
Note there is nothing for the left shoulder, this is the case on most of the freeway that's marked, though in some areas only the left and right shoulders are indicated.

C. Jackson Lake Road
This area appears near completion, sign structures are up and lanes are marked for striping, some landscaping and drainage covers still need work, both looking west/north:
And south/east toward Kersey Valley Road:
D. Kersey Valley Road
A similar story can be said here. More sign structures have been put up, but the recent rain hasn't helped with the large hill landscaping. First here's a view of the bridge:
A few more posts for the guardrails also need to be installed, after the construction road is no longer needed. Here's a similar view but including the signage structure for the future 2 mile advance sign for the Business 85 exit:
Notice also completion of the median guide wires. Here's the landscaping problem I mentioned:
While the drainage system seems to have worked well, most of the top soil put on the embankment has washed away, and will need to be replaced.

E. I-85 Interchange
The interchange as seen from Dresden Road appears completed, or close to being so:
A truck ramp to the eastbound exit off ramp will have to be closed. Meanwhile an overhead sign structure at the splitting of the I-85 north (flyover) and south ramps has been put up. On I-85 itself all the signage has been put up with the I-74/US 311 signs remaining covered:
The covered sign marks one mile before the beginning of the I-74 interchange C/D ramps. Below is the final sign covered over at the beginning of the C/D ramps northbound:
Photo taken from the NC 62 off ramp. There have been no additional signs or sign posts put up yet at the I-85 north on ramp from NC 62 which uses the C/D lanes.

F. NC 62 and Tuttle Road
With the exception of markings demarking future traffic lanes, nothing new was seen at these locations, both seemingly near completion. The landscaping has filled in nicely as seen from both directions on the Tuttle Road Bridge. First, north:
yes, those are bikers heading southbound, and looking to the south:
Hard, to spot but you can see median guide wires have been placed here as well. The sign structure seen last month around the corner is still the last one along the freeway heading south.

F. Poole Road
The only change is the completion of the bridge over a creek to the north, it also looks like they repaved this section:
Landscaping also may still be an issue to the north of these bridges. Looking south from the Poole Road bridge shows a scene similar to last month, no pavement markings, or sign structures for the Cedar Square exit seen here, though more guardrails have been installed:
Looking along the freeway that parallels Poole Road, the only real change is the absence of machinery:
The truck access route from Poole has been closed, so trucks are using the median to turn around to get off the freeway at the Cedar Square interchange.

G. Cedar Square Road Interchange (Temporary End of Freeway)
There has been progress in placing final pavement down for the sections that will be opened to traffic, though as stated before, no signage structures have been put up, nor evidence of signage along Cedar Square at the future I-74 west interchange. Here's a view of the on ramp from the end of Poole Road:
The on ramp is straight ahead. The future off ramp from I-74 East, not paved beyond the cement median, is to the left. Here's a view of the progress in constructing the eastbound off ramp which all traffic will use until late 2012:
Notice they are still working on landscaping and containing water runoff before the ramp. The view of the ramp from Cedar Square Road shows further need for landscaping:
Not to mention replacement of traffic barrels. The view from Poole Road looking south toward the bridge shows the extent of progress in paving the ramps and future westbound I-74 roadway:
While a view from the bridge looking southward, shows the progress of the westbound offramp and the unpaved sections which are now the responsibility of the Poole Rd to US 220 contractor:
A view from the future Eastbound on ramp shows the extent of the ramp and borrow pit construction:
Yes, those are the same bikers again. The official opening date for this segment is still November. Hopefully, though the weather will cooperate, especially when it comes to placing the line markings down. I am moving back to my native Massachusetts at the end of October and it would figure that NCDOT would wait until a couple days into November before opening the road. Especially after all the effort I've made in pointing out their mistakes.

I took photos along the next section of construction from Spencer Road to US 220 and will put those up on another post. I'll certainly have to return someday to take a ride after that section's open. Meanwhile, if there are any others interested in following the progress of the final section of the 311 Bypass, feel free to take rod trips to document it.

Comments

Bob Malme said…
According to the news article here:
http://www.hpe.com/view/full_story/9746266/article-Work-progresses-on-U-S--311?instance=main_article
NCDOT hopes to open this segment of I-74 by Thanksgiving. Given the photos showing major completion and dry weather forecast for the next week, hopefully they can finish earlier.
Commuter Joe said…
Fascinating coverage, thank you.

Popular posts from this blog

Bridgeport Covered Bridge

The Bridgeport Covered Bridge is a historic crossing of the South Fork Yuba River located in Nevada County, California near Nevada City.  The Bridgeport Covered Bridge opened as a tolled crossing during 1862 as part of the larger Henness Pass Road.  The Bridgeport Covered Bridge closed to vehicle traffic during 1972 and was recently restored during 2021.  The Bridgeport Covered Bridge is historically California's longest covered span is thought to likely be the longest such structure surviving in the world.  Featured as the blog cover is the Bridgeport Covered Bridge during 1950 when it was an active part of Pleasant Valley Road.   The history of the Bridgeport Covered Bridge The history of Bridgeport Covered Bridge was featured in the  September 1950 California Highways & Public Works .  Bridgeport Covered Bridge was constructed during 1862 over the South Fork Yuba River.  The Bridgeport Covered Bridge served as part of the Virginia Turnpike Company maintained Henness Pass Roa

Former California State Route 215

  California State Route 215 was a short-lived state highway which existed in the Los Angeles Metropolitain area after the 1964 State Highway Renumbering.  California State Route 215 was aligned from US Route 60 at 5th Street in Pomona north to US Route 66 near Claremont via Garey Avenue.  California State Route 215 came to be after California State Route 71 was bisected in Pomona due to relinquishment of a portion of Garey Avenue due to the opening of a portion of the Corona Freeway (now Chino Valley Freeway) during 1958.  California State Route 215 was deleted by the Legislature during 1965. The history of California State Route 215 The initial segment of what was to become California State Route 215 was added to the State Highway System as part of the 1909 First State Highway Bond Act.  The First State Highway Bond Act defined what would become  Legislative Route Number 19  (LRN 19) as running from Claremont to Riverside.  The segment of LRN 19 between Claremont and Pomona would in

US Route 70 over San Augustin Pass

San Augustin Pass is a gap in the Organ Mountains, San Augustin Mountains and San Andres in Dona Ana County east of Las Cruces.  San Augustin Pass lies an elevation of approximately 5,600 feet above sea level and was originally traversed by New Mexico State Route 3.  US Route 70 would be realigned over San Augustin Pass during 1934 when it was extended to Los Angeles, California.  During 1963 US Route 82 would be extended through San Augustin Pass to Las Cruces.  Since the early the early 1990s signage of US Route 82 has been withdrawn to Alamogordo.  San Augustin Pass and US Route 70 are largely known for the numerous closures due to test firings originating from the White Sands Missile Range.   Part 1; the history of highway designations over San Augustin Pass San Augustin Pass traditionally has been the easiest from the Rio Grande in Las Cruces east to the Tularosa Basin.  The terrain conditions at San Augustin Pass allowed for an easy crossing in the gap between the Organ Mountains