I-74/US 311 Freeway Progress for August, Part 1

I traveled Sunday 8/29 to view the latest progress on the I-74/US 311 Freeway between Business 85 in High Point and US 220 in Randleman, plus check up on the new construction project along 220 in Asheboro. During the visit from Cedar Square Road south I followed along with Bill Travers, a local resident who has been helping me keep up to date on area construction projects. Part 1 will describe progress on Phase 1 of the project from Business 85 to Spencer Road, while Part 2 will describe progress and new locations to view Phase 2 to US 220 and remark about changes in plans for this part of highway since the Design-Build section was let.

Part 1 - Business 85 to Spencer Road
A. Baker Road
As seen in the photo below, the last grading of the temporary road has been completed, the ground now needs seeding and wet weather for something to grow on it:
The views to the south and north actually look less complete than last month due to landscaping work covering up the completed asphalt roadway. Here's a view to the north:
They also seem to be laying cable along the side of the roadway. The view to the south:
shows the need for more landscaping toward the bridge and covers for the median catch basins.

B. Jackson Lake Road Bridge
Some changes here, beginning with the landscaping around the bridge. The former truck entry road has been graded over and become a grassy area:
This is a definite sign construction is wrapping up in this area, another sign are signs, or structures to hold them placed in both directions west of the bridge:
The left gantry is for the I-85 exit, the one on the left Business 85. Remaining landscaping has to be completed as well as sign placement. Looking east also shows some landscaping work remains...
Plus catch basin work. Though there is an addition of shoulder guard rails and median guide wires.

C. Kersey Valley Road Bridge
Major progress in this area on guard rails, as one can see in the photo below:
The truck access road, seen in the foreground, is still being used. Looking south reveals more guardrail progress as well as successful landscaping that almost needs to be mowed...
They also need to put up another sign gantry, I assume this is the 2 mile sign for the Business 85 Exit. Successful landscaping along the eastbound roadway has been mixed:
You would think more effort would be made to get the slope to look good, because the Blythe Construction contractor offices are located at the top of the hill. Looking at the I-85 interchange from Dresden Road...
It appears most of the work has been completed, though this is from some distance away.

D. NC 62, Tuttle Road, and Poole Road showed little change with similar need for completing some landscaping, adding some guardrails, and completing catch basins.

E. Cedar Square Valley Bridge and Interchange
Most of the remaining paving needed to open the road has been completed, as seen looking north from the Cedar Square Road Bridge back toward the Poole Road bridge...
The eastbound off ramp is completed as well as the westbound lanes back to the Cedar Square on ramp. The view below is of the completed on ramp intersection with Cedar Square Rd...
The construction equipment in the distance is grading the remaining roadbed toward Spencer Road. This is what it looks like from the bridge:
The paving of this section has been transferred to the Barnhill Construction, the firm doing the design/build phase 2 of the project. The contractor for Phase 1, Blythe Construction was having trouble this spring purchasing enough asphalt for its many projects. The equipment seen in the distance is actually on the other side of Spencer Road. Construction from there to US 220 will be the subject of the second part of this report.

Comments

Bob Malme said…
An update as to completion progress. According to the NCDOT Construction Progress Report, the Business 85 to Spencer Road portion was 93.56% complete as of the end of August.

Popular posts from this blog

West Canyon Road (Snow Canyon State Park)

West Canyon Road is an approximately four-mile dirt service road located in Snow Canyon State Park.  West Canyon Road follows Snow Canyon from the Whiptail Trail to the northern State Park boundary and intersects numerous trailheads.   West Canyon Road was the original main road through Snow Canyon after it was designated as a Utah State Park in 1957 and opened to the public in 1962. Part 1; the history of West Canyon Road Snow Canyon is located in the Red Mountains north of the city of Ivins in Washington County, Utah.  Snow Canyon is one of many sandstone canyons located in the Red Mountains.  Part of the extinct Santa Clara Volcano punctured the Red Mountains via lava tubes. From approximately the year 200 to 1,250 the area around Snow Canyon was inhabited by the Ancestral Puebloans.  Mormon pioneers established Santa Clara south of Snow Canyon in 1854.  Local legend has it that the settlers discovered Snow Canyon in the 1850s while searching for m...

Indian Gulch Extension and the Indian Gulch ghost town site

Indian Gulch Extension is an approximately 6-mile-long rural highway corridor in the Sierra Nevada foothills of western Mariposa County.  Indian Gulch Extension begins at Indian Gulch Road near the namesake ghost town of Indian Gulch.  From the ghost town site Indian Gulch Extension extends southwesterly to the Merced County line where it becomes Waltz Road.   The former Gold Rush era community of Indian Gulch which was settled near Santa Cruz Mountain in 1849 and had standing structures until the early 1970s.  What is now Indian Gulch Extension was approved for construction by the Mariposa County Commissioners in 1862.  The purpose of the corridor was to provide Indian Gulch with a direct connection westward with the greater Stockton-Los Angeles Road.  The Stockton-Los Angeles Road would go onto define much of the Mariposa County and Merced County line.  Part 1; the history of Indian Gulch and Indian Gulch Extension Indian Gulch Road is named aft...

The reemergence of US Route 99 at the Ventura Freeway/Golden State Freeway interchange

During April 2023 a portion of the sign gantry on the eastbound Ventura Freeway (California State Route 134) approaching the Golden State Freeway (Interstate 5) fell.  The fallen portion of the sign gantry revealed a once covered US Route 99 shield.  The uncovered US Route 99 sign (blog cover courtesy Ian Ligget) is a 1956-63 era freeway specification US Route shield.  This blog will explore in brief how the Golden State Freeway was developed as US Route 99 and US Route 6 before becoming solely Interstate 5.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page Part 1; visiting the US Route 99 shield at the Ventura Freeway/Golden State Freeway Interchange As noted in the introduction the US Route 99 shield can be seen on the eastbound Ventura Freeway (California Sta...