I-74/US 311 Freeway Progress for August, Part 1

I traveled Sunday 8/29 to view the latest progress on the I-74/US 311 Freeway between Business 85 in High Point and US 220 in Randleman, plus check up on the new construction project along 220 in Asheboro. During the visit from Cedar Square Road south I followed along with Bill Travers, a local resident who has been helping me keep up to date on area construction projects. Part 1 will describe progress on Phase 1 of the project from Business 85 to Spencer Road, while Part 2 will describe progress and new locations to view Phase 2 to US 220 and remark about changes in plans for this part of highway since the Design-Build section was let.

Part 1 - Business 85 to Spencer Road
A. Baker Road
As seen in the photo below, the last grading of the temporary road has been completed, the ground now needs seeding and wet weather for something to grow on it:
The views to the south and north actually look less complete than last month due to landscaping work covering up the completed asphalt roadway. Here's a view to the north:
They also seem to be laying cable along the side of the roadway. The view to the south:
shows the need for more landscaping toward the bridge and covers for the median catch basins.

B. Jackson Lake Road Bridge
Some changes here, beginning with the landscaping around the bridge. The former truck entry road has been graded over and become a grassy area:
This is a definite sign construction is wrapping up in this area, another sign are signs, or structures to hold them placed in both directions west of the bridge:
The left gantry is for the I-85 exit, the one on the left Business 85. Remaining landscaping has to be completed as well as sign placement. Looking east also shows some landscaping work remains...
Plus catch basin work. Though there is an addition of shoulder guard rails and median guide wires.

C. Kersey Valley Road Bridge
Major progress in this area on guard rails, as one can see in the photo below:
The truck access road, seen in the foreground, is still being used. Looking south reveals more guardrail progress as well as successful landscaping that almost needs to be mowed...
They also need to put up another sign gantry, I assume this is the 2 mile sign for the Business 85 Exit. Successful landscaping along the eastbound roadway has been mixed:
You would think more effort would be made to get the slope to look good, because the Blythe Construction contractor offices are located at the top of the hill. Looking at the I-85 interchange from Dresden Road...
It appears most of the work has been completed, though this is from some distance away.

D. NC 62, Tuttle Road, and Poole Road showed little change with similar need for completing some landscaping, adding some guardrails, and completing catch basins.

E. Cedar Square Valley Bridge and Interchange
Most of the remaining paving needed to open the road has been completed, as seen looking north from the Cedar Square Road Bridge back toward the Poole Road bridge...
The eastbound off ramp is completed as well as the westbound lanes back to the Cedar Square on ramp. The view below is of the completed on ramp intersection with Cedar Square Rd...
The construction equipment in the distance is grading the remaining roadbed toward Spencer Road. This is what it looks like from the bridge:
The paving of this section has been transferred to the Barnhill Construction, the firm doing the design/build phase 2 of the project. The contractor for Phase 1, Blythe Construction was having trouble this spring purchasing enough asphalt for its many projects. The equipment seen in the distance is actually on the other side of Spencer Road. Construction from there to US 220 will be the subject of the second part of this report.

Comments

Bob Malme said…
An update as to completion progress. According to the NCDOT Construction Progress Report, the Business 85 to Spencer Road portion was 93.56% complete as of the end of August.

Popular posts from this blog

Route 75 Tunnel - Ironton, Ohio

In the Ohio River community of Ironton, Ohio, there is a former road tunnel that has a haunted legend to it. This tunnel was formerly numbered OH 75 (hence the name Route 75 Tunnel), which was renumbered as OH 93 due to I-75 being built in the state. Built in 1866, it is 165 feet long and once served as the northern entrance into Ironton, originally for horses and buggies and later for cars. As the tunnel predated the motor vehicle era, it was too narrow for cars to be traveling in both directions. But once US 52 was built in the area, OH 93 was realigned to go around the tunnel instead of through the tunnel, so the tunnel was closed to traffic in 1960. The legend of the haunted tunnel states that since there were so many accidents that took place inside the tunnel's narrow walls, the tunnel was cursed. The haunted legend states that there was an accident between a tanker truck and a school bus coming home after a high school football game on a cold, foggy Halloween night in 1

Porter-Parsonsfield Covered Bridge - Maine

  Spanning over the Ossipee River on the border between Porter in Oxford County, Maine and Parsonsfield in York County, Maine is the 152 foot long Porter-Parsonsfield Covered Bridge. The Porter-Parsonsfield Bridge is built in a Paddleford truss design, which is commonly found among covered bridges in the New England states. The covered bridge is the third bridge located at this site, with the first two bridges built in 1800 and 1808. However, there seems to be some dispute for when the covered bridge was built. There is a plaque on the bridge that states that the bridge may have been built in 1876, but in my research, I have found that this bridge may have been built in 1859 instead. That may check out since a number of covered bridges in northern New England were built or replaced around 1859 after a really icy winter. The year that the Porter-Parsonsfield Covered Bridge was built was not the only controversy surrounding its construction. There was a dispute over building and maintain

US Route 299 and modern California State Route 299

US Route 299 connected US Route 101 near Arcata of Humboldt County east across the northern mountain ranges of California to US Route 395 in Alturas of Modoc County.  US Route 299 was the longest child route of US Route 99 and is the only major east/west highway across the northern counties of California.  US Route 299 was conceptualized as the earliest iteration of what is known as the Winnemucca-to-the-Sea Highway.  The legacy of US Route 299 lives on today in the form of the 307 mile long California State Route 299.   Featured as the cover of this blog is the interchange of US Route 101 and US Route 299 north of Arcata which was completed as a segment of the Burns Freeway during 1956.   Part 1; the history of US Route 299 and California State Route 299 The development of the State Highways which comprised US Route 299 ("US 299") and later California State Route 299 ("CA 299") began with 1903 Legislative Chapter 366 which defined the general corridor of the Trinit