Your May I-74/US 311 Freeway Progress Report

I took a drive Sunday to see what progress had been made in the last month on the I-74/US 311 Freeway from Business 85 in High Point to US 220 near Archdale. It had been a pretty dry month, but I didn't encounter as much progress on paving as I thought there should be. There were though many signs of progress. The post proceeds West to East (or Northwest to Southeast to be more accurate) along the nearly 10 miles of future freeway...
1. High Point East Belt, Business 85 to I-85 High Point
A. Baker Road-They have almost completed removing the old road bed and cutting down to the grade of the surrounding roadway...
Here's what remains of the westbound temporary road. Looking into the roadbed...
There are some rock and soil to remove to bring it down to grade. Looking east/south from the bridge, one can see there has been more progress on grading since April...
But there still needs more work to be done looking back west/north toward the completed road and High Point...
B. Jackson Lake Road-The final layer of asphalt had been put down on the bridge and its approaches in late April:
Some progress had been made in grading and landscaping the westbound lanes to the north/west of the bridge...
The view to the south and east is mostly similar to last month's, with the exception of more landscape vegetation...
C. Kersey Valley Road-The next stop was at the bridge in the distance along Kersey Valley Road. Like with Jackson Lake, the final asphalt layer had been placed on and near the bridge...
The following is a reverse view of the last Jackson Lake photo, looking toward that road's bridge from Kersey Valley...
One gets more of a sense of a near completed freeway from this vantage point, however looking the other way shows that there's more to do:
They are working on some more environmentally friendly run-off structures, like here...
This photo is taken from Dresden Road. Note the rock runoff stream paths and the small containment pond below. An overflow pipe is included to prevent runover from the pond in the background.

D. I-85 Bridges and Ramps-A close look at the bridges and Eastbound off ramp shows orange barrels blocking the ramp. This could mean the ramps and bridges are completed and construction trucks need to exit on a new link to the road seen to the right in front of the barrels...
Through traffic was put back on the original I-85 lanes in mid-April. While there are only two of the 3 lanes available southbound all 3 are open northbound. Traveling south on I-85, the first advanced exit sign is 2 miles away from the exit and covered over...
Though not visible, from the plans the sign should read Exit 133C, B, A I-74/US 311/NC 62 High Point, Asheboro, There's another covered over sign at 1 mile, the signs where the C/D ramps begin had not been put up, but one sign assembly at the future I-74 Westbound ramp has...
Traffic needing to access NC 62 now uses the C/D ramps. But one cannot get back on I-85 for now since the end of the ramps are blocked by Jersey Barriers...
This is a better view of the Exit 113A sign than that was shown in the March posting.
Going northbound at I-85 there is an advance sign at 1 mile covered over, and a sign at the beginning of the C/D ramps They still need to be place though before the separate NC 62 exit...

2. "US 311 Bypass" I-85 to US 220 Randleman
A. Tuttle Road-Nothing new was seen at Tuttle Road, the final coat of asphalt had been placed along the bridge in early April, and the road bed was already landscaped with guard rails installed.

B. Poole Road-On the north/ westbound side of the bridge new asphalt had been placed around the completed creek bridge...
The view south/ eastbound showed more work had been completed on landscaping...
Many of the water runoff drains had been completed, here's a closeup of one from Poole Road halfway toward the Cedar Square Interchange...
C. Cedar Square Road and Interchange-Not as much had been accomplished here as hoped. Though much of the unfinished roadway does not have to be completed until the next segment to US 220 is completed in 2012-
Certainly a lot of construction vehicles available to do the work. To the center middle is the eastbound off ramp to Cedar Square Road which will also temporarily be US 311.
The grading progress under the bridge depends when each roadbed is suppose to open, to the left this year, to the right in two years...
Landscaping is complete, in fact the grass could be mowed. Here's a view of the progress on the Westbound onramp and future eastbound offramp at the intersection of Poole and Cedar Square:
The on ramp curves off to the right, a better view of it and the surrounding landscaping can be seen here...
Looks like between the ramps and the eastbound lanes will be another runoff containment area.

D. 'US 311' Interchange-Much more progress in clearing and moving of dirt can be seen this month. Here's approaching the future interchange along South US 311...
The clearing continues across the road to the south through the gap in the trees in front of the radio towers and to the southeast, I assume toward US 220. Below is a closer look at the interchange area showing the dirt that has been moved to create the future highway roadbed. There are two roads (one with the machinery on it, the other between that and the current roadway), whether this means the route will be divided at this point, or one of the beds is for a ramp is not quite clear:
E. US 220 Interchange-More progress can be seen in building the sides of the future westbound I-74 bridge. Here's what the construction area looks like approaching on 220 south...
The future I-74 East will use the first bridge support, westbound traffic heading north on 220 (I-73 North) will use the bridge in the background. Here's a closer look at that bridge:
On the left you can see the start of building the other side of the bridge, which is better seen here...
The ramp behind leads to the flyover ramp for I-74 west traffic. Here's a view of the construction area from US 220 North:
A closer look at the bridge construction seen in the distance above...
You can see to the left clearing behind the bridge which may lead all the way back to US 311. While not as much progress as I would have thought occurred (the amount of progress for April has not yet been posted by NCDOT), it still looks possible for this road to open this summer and not late in the year as NCDOT schedule currently states.

Comments

Anonymous said…
Obviously the new stretch of highway is going to be name I-74. Is any of the existing US 311 going to be renamed? Say the stretch between Bus 85 and Main St in High Point where the majority of the road is already interstate standard?

Popular posts from this blog

New River Gorge National River Area To Become A National Park

Great news for those that enjoy National Parks, West Virginia's New River Gorge Region, or West Virginia tourism.  Included within the Fiscal Year 2021 Omnibus Appropriations Bill signed by President Trump last night (December 27th) is the New River Gorge Park and Preserve Designation Act.   The act will designate the existing New River National River and over 72,000 acres of land within it as a National Park and Preserve. The New River Gorge Bridge will continue to be the centerpiece of the new New River Gorge National Park and Preserve. (Adam Prince, 2007) The river and surrounding land, which was added to the National Park System in 1978, will be our 63rd National Park.   The designation preserves over 7,000 acres as a National Park.  This area will not allow any hunting.  The remaining 65,000 acres of the existing park will be designated as a preserve allowing hunting and fishing. The main attractions to the New River Gorge - whitewater rafting, camping, hiking, mountain bikin

Douglas Memorial Bridge; the ruins of US Route 101 and the Redwood Highway over the Klamath River

Near the village of Klamath in southern Del Norte County, California sits the ruins of Douglas Memorial Bridge which once carried US Route 101 and the Redwood Highway over the Klamath River.  The Douglas Memorial Bridge was a arch concrete span which once crossed the Klamath River.  The Douglas Memorial Bridge was noted for it's unique grizzly bear statues which still adorn the remains of the structure.  Completed in 1926 the Douglas Memorial Bridge was the original alignment of US Route 101 ("US 101") and stood until it was destroyed by the Christmas Floods of 1964.  The Douglas Memorial Bridge is named in honor of G.H. Douglas who was a Assemblyman of the First District of California.  Below the Douglas Memorial Bridge can be seen during it's prime (courtesy bridgehunter ).  Part 1; the history of the Douglas Memorial Bridge The history of what would become US 101/Redwood Highway begins with the approval of the 1909 First State Highway Bond Act .  The First Stat

The Great PA 48 Clearance Sale

It's not often that any department of transportation sells land it purchased.  They are usually in the business of acquiring land for right-of-way.  But in 1982, the Pennsylvania Department of Transportation did exactly that.  Offering to buyers land it purchased just 15 years earlier for the never-built Route 48 Expressway. Background: The sale was a result of the 1970s cash crunch the PennDOT experienced.  Many projects were cut back, shelved, or eliminated.  The 'New 48', or the North-South Parkway, which was touted for nearly 20 years as a connection from the industrial Mon Valley to the Turnpike and Monroeville was one of the casualties. In the mid-late 1960s, movement to construct the new highway began with targeting a two-mile stretch of highway from the Route 48 intersection at Lincoln Way in White Oak to US 30 in North Versailles.  The plan was then to continue the highway northwards to Monroeville.  Extension south across the Youghiogheny River and to PA 51 would