A detailed look at the King Coal Highway

A few weeks ago, I received a packet from the West Virginia Division of Highways. I had requested maps on their proposed routings for the King Coal, Coalfields, and Tolsia Highways. King Coal and Tolsia are designated to be a part of the fun and exciting I-73/74 project.

The reason why I requested these maps is that these three routes are widely discussed but no one (that I know of) really has any clue on what the routings of these three highways are to/or could be.

So let's take a closer look at the King Coal Highway (Future I-73/74):

WVDOH has broken down the route into segments similar to what they have done with Corridor H. In total, there are ten segments and two connector routes that are to be built for the King Coal.

I will be heading South to North starting at the US 52 interchange with US 460 (just west of I-77 exit 1) to US 119 near Belo and where US 119 intersects WV 65.

Segment 1: Bluefield (US 52/460) to Mercer County Airport (WV 123). Length 2.3 miles.

The status for this section is that the US 52/460 interchange has been built and partially open while the King Coal waits to be extended northward. Currently, construction is underway to extend the highway from the US 52/460 interchange northward. A $16.3 million project is extending the highway over US 19 to Stoney Ridge. That project is about 34% complete.

Mercer County officials hope to see about $53 million in new funding to complete this segment of highway to the Mercer County Airport.

Segment 2: Mercer County Airport (WV 123) to Littlesburg (WV 20). Length 3 miles.

Mercer officials hope that this section will receive funding soon in addition to or part of the $53 million request they have made.

Segment 3: Littlesburg (WV 20) to Montcalm . Length 2.7 miles.

This segment crosses over WV 71 and over the Bluestone River.

Segment 4: Montcalm to Northfork. Length 16 miles.

The King Coal remains north of US 52 and pretty much will hover along the Wyoming/McDowell County Line. The Shawnee Parkway will also intersect the King Coal within this segment.

Segment 5: Northfork to Coalfields Expressway Interchange. Length 8 miles.

King Coal will continue to hover the Wyoming/McDowell County line to the interchange with the Coalfields Expressway north of Welch. The Coalfields/King Coal interchange has been completed but sits empty and unused until the two highways finally reach the three level interchange.

Segment 6: Coalfields Expressway Interchange to US 52 at the Wyoming/McDowell County Line. Length 17 miles.

This will be the first time since Bluefield that the King Coal will intersect the current route of US 52.

Segment 7: US 52 at the Wyoming/McDowell County line to Mingo/Wyoming/McDowell County Lines (County Route 13). Length 5 Miles.

The King Coal now running to the south and west of US 52 continues to hug the McDowell/Wyoming County line until it nears the tri-point of Mingo/Wyoming/McDowell south of Gilbert.

Segment 8: Mingo/Wyoming/McDowell County Line (CR 13) to Mountain View (WV 44 connector). Length 11 miles.

Now entirely in Mingo County. This segment will end at the WV 44 Connector a few miles south of Mountain View and where WV 44 currently ends at US 52.

The WV 44 connector will run about 1-2 miles north from the King Coal to where WV 44 meets US 52.

Segment 9: Mountain View (WV 44 Connector) to Delbarton (US 52). Length 15 miles.

This segment ends at US 52 between WV 65/Delbarton and US 119 in Williamston. From here it appears that the King Coal will use a brief segment of US 52 before splitting in two.

Segment 10: Delbarton (US 52) to Belo (US 119) Length 6.8 miles.

This segment will run from US 52 to where WV 65 North meets US 119 near Belo. From here there will be a brief routing along US 119 before the continuation of I-73/74 northwards along the Tolsia Highway.

Segment 10A: Williamson Connector - Delbarton (US 52) to Goodman (US 52/119). Length 5.7 miles.

The connector will branch off of the King Coal west of Delbarton and cross over US 52 north of Williamson before meeting current US 52/119 near Chattaroy.

So that's it, and about all I know on it. The maps painted a much clearer picture of what the planned route of this highway will be. (Now if I can get there to take photos) When I work on my WV updates later this summer, I will include this on a new page and also try to scan the large King Coal Highway (Build Alternatives) map that I received.

Comments

Unknown said…
Is their a projected date for the interchange of king coal and coalfields expressway? I literally live on the McDowell/ Wyoming county line.
Unknown said…
Is their a projected date for the interchange of king coal and coalfields expressway? I literally live on the McDowell/ Wyoming county line.

Popular posts from this blog

The case to move Interstate 73 in Southern Ohio onto US 33

Every decade or so, Ohio pushes to revisit the proposed Interstate 73 that would connect Michigan to Myrtle Beach, South Carolina.  It's been happening since Congress legislated the route in 1991.  Within Ohio, Interstate 73 generally follows the US 23 corridor from Portsmouth through Columbus to Toledo, and into Michigan. Since High Priority Corridor Five was created , Ohio has really done nothing to move forward with Interstate 73.  Sure, there have been feasibility studies here and there.  But actual dollars and construction just haven't occurred. The US 33 Nelsonville Bypass appears to have been built to Interstate standards. However, Ohio has been slowly upgrading US 33 to a full freeway through Southeastern Ohio.  Bypasses of Lancaster and Nelsonville opened in 2004 and 2013, respectively.  Other sections of two-lane road are being twinned, some to freeway or, at a minimum, to expressway standards.  Currently, a $274 million widening project in...

Rep. Sue Myrick's letter to Gov. Easley and Sect. Tippett published in Charlotte Observer

US. Representative Sue Myrick's (R-Charlotte) letter to North Carolina's Governor Mike Easley and NC Transportation Secretary Lyndo Tippett was published in the Friday, November 30th edition of the Charlotte Observer . Why are we delaying the completion of 1-485 in Charlotte again? I read in The Charlotte Observer how rising prices of materials are leading to the delay. Why didn't these same rising costs delay the loops in Fayetteville and Wilmington? Why are we building loops in Fayetteville and Wilmington before we complete the one in Charlotte? We were working on the one in Charlotte back when I was mayor. That was 20 years ago! ... Last I looked Charlotte was the largest city in the state. There seems to be no recognition of that fact in Raleigh. No recognition that we are at a standstill with traffic. No recognition that we have a traffic problem. Nor is there any recognition of the fact that the state DOT utterly botched up the southern leg of our yet to be completed ...

I-90 in Albany, New York and the Berkshire Spur

Today's Albany Times Union has a segment in their weekly Getting There? column that explains some of the history behind how I-90 is designated in the Albany, NY area as well as the Berkshire Spur. The long and short of the article was that I-90 was originally designated on the unsigned portion of the Berkshire Spur, but as free I-90 was built, the designation was moved onto the free portion of road. Additionally, there were talks in 1999 between state and federal officials about the possibility of moving I-90 back onto the unsigned portion of the Berkshire Spur, while extending I-88 onto what we know as free I-90. There would have also had been an I-88/I-90 multiplex between Rotterdam and Albany as a result. http://www.timesunion.com/AspStories/story.asp?storyID=916307