Skip to main content

Final Progress Report on I-74/US 311 Freeway for 2009

Made my last trip of 2009 to check out progress on the construction of the I-74/US 311 freeway from High Point to Randleman during midday today (12/12). Based on the NCDOT's Construction Progress Report there hasn't been much going on along the Business 85 to Cedar Square Road segment the last two months as far as percentage complete goes, now up to about 81% complete at the end of November compared to 78% in September. There has been, however, some noticeable progress on the two remaining bridge projects as well on some of the roadway itself.

Going West to East (or North to South depending on which route you prefer) the first stop is the Baker Road bridge. Work has been completed on the bridge decks as you can see here (yes, they were working on Saturday, making up for bad weather maybe):
The bridge is capable of supporting traffic, as the truck driving across it shows here:
You can see they still have to connect the bridge to the pre-exisiting alignment of Baker Road and build the bridge walls and railings before being open to traffic. This could happen before the end of the year if the weather cooperates.
They are still working on getting the road down to grade south of the bridge and will start north when the bridge is opened and the temporary roadway to the north can be demolished.

Jackson Lake Bridge. Not much progress here west of the bridge, as you can see they still don't have a westbound roadway here, still just piles of dirt:
The roadway to the east toward the Kersey Valley bridge, however, is basically complete and can support contractor traffic as you can see below:
Kersey Valley Road area. Again little progress here. Some more excavation has been done to the roadway west of the bridge:
Notice less construction equipment and machinery present than last month by the graded slopes going eastbound. The view of the roadway between Kersey Valley and I-85 shows more work is needed:
Most of the depressions are filled with water which, due to today's cold temperatures, had turned to ice. They are going to have to wait until this dries up to proceed.

The I-85 interchange. Some progress here, if you look behind the flyover bridge (the farthest) you'll notice the top of an overhead sign structure for the I-85 exit that has been put up. A cantilevered overhead sign structure was also put up just north of the NC 62 bridge.
Another photo of the same area showing progress around the interchange offramp, it appears more grading has been done down toward the future eastbound roadway. And if you didn't notice before, the west wall to the flyover bridge has been completed:
Tuttle Road. There has been more progress in placing guardrails along this section. Looking west you can see there are now guardrails on both directions of the highway:
There is also now guardrail looking east/southbound:
It appears that there is an asphalt layer capable of carrying traffic now from just east of the I-85 interchange heading east almost to Cedar Square Road, with a few exceptions. Notice the truck below is heading the wrong way, but demonstrates it is possible to get to near Cedar Square Road (that would be easiest way off the freeway).
A closer look at the Tuttle Road bridge heading east:
The Cedar Square Road bridge and Interchange. Most of the progress in the last month has been made here. First, the bridge has been opened:
To the right is the old road alignment which will be access to Poole Road. (The connection has been made but the road was blocked by road closed signs, this wasn't preventing locals from making there way around them to access Cedar Square). Now crossing the bridge:
The bridge has 3 lanes, the center reserved for those wanting to make a left turn onto I-74 East, Which occurs just before where this photo was taken looking at the new intersection with US 311:
Second, progress on the on and offramps. For eastbound traffic these are opposite each other while the westbound ramps are on the south side of Cedar Square. Here's the progress being made on the westbound on/off ramps:
Here's a look on the progress of building the eastbound off ramp:
They still need to remove the old alignment of Cedar Square in the freeway's path before final grading and paving can be made.
Meanwhile all the construction equipment is at the end of the current road awaiting construction on the second part to complete the freeway to US 220:
US 311. Some additional clearing in the construction area, and the start of one of the on or offramps, but little else:
US 220. Some progress here in the appearance of a second center support in the median for the other flyover ramp:
Here's progress on the first flyover support, plus clearing on the northbound side:
The wider view of the construction area, heading northbound:
Progress on the future I-74 West Flyover ramp:
They are working also on expanding US 220 to 3 lanes (seen beyond the barrier) between Pineview Street and the existing US 311 exit:
Notice the polls for a new exit sign. These also appear elsewhere along US 220, not just in the I-74 construction area implying another project installing new exit signs, hopefully before the I-74 project is finished and with I-73 mileage based numbers.

My next trip will be after they open the new rest areas/visitor's centers near Seagrove on I-73/74 sometime in January (current completion date is 1/21/10). I'll let everyone know when they are open, in case anyone else wants to come along and tour them.

Comments

Popular posts from this blog

Former US Route 101 through Sargent

  Sargent is a ghost town and siding of the Southern Pacific Railroad located in southern Santa Clara County.  The original alignment of US Route 101 was aligned through Sargent via what is now known as Old Monterey Road.  Sargent was bypassed gradually due to shifts of the alignment of US Route 101 which occurred during 1941 and 1950.  Pictured as the blog cover is a view on Old Monterey Road which is now no longer accessible to the general public.  Below is a scan of the 1935 Division of Highways Map of Santa Clara County which depicts the original alignment US Route 101 through Sargent.   Part 1; the history of US Route 101 in Sargent Sargent lies on land which was once part of Rancho Juristac.  During 1856 James P. Sargent purchased Rancho Juristac and plotted what was known as Sargent Ranch.  By 1869 the Southern Pacific Railroad coast line reached the relocated town site of Gilroy.  The Southern Pacific Railroad coast line would be constructed through Chittenden Pass by 1871 whic

Tulare Lake returns

During the winter of 2023 California experienced one of the wettest seasons in recent decades.  Enough snow and water were deposited into the Sierra Nevada Mountains that the runoff was enough to partially reform Tulare Lake within San Joaquin Valley.  Tulare Lake was once the largest lake west of the Mississippi River by surface area.  Tulare Lake has been largely dried for the past century due to irrigation divisions and upstream impoundments.  This blog will examine the history of Tulare Lake and its recent return.  Pictured as the blog cover is Tulare Lake from 19th Avenue in Kings County during early May 2023.  Tulare Lake can be seen near its maximum extent below on the 1876 P.Y. Baker Map of Tulare County .   Part 1; the history of Tulare Lake Tulare Lake is the largest remnant of Lake Corcoran.  Lake Corcoran once covered much of the entire Central Valley due to being it being located at a in natural low point from where mountain run-off would accumulate.  Lake Corcoran is thou

US Route 95 in California

US Route 95 within California exists within San Bernardino County and Riverside County.  US Route 95 within California is approximately 130 miles factoring multiplexes along Interstate 10 and Interstate 40.  US Route 95 in California begins at the Arizona state line along the Colorado River near Blythe in Riverside County.  US Route 95 follows the general course of the Colorado River north through the Sonoran Desert to the Mojave Desert towards Needles of San Bernadino County.  US Route 95 enters Nevada north of Interstate 40 and the historic alignment of US Route 66.  US Route 95 was extended to Blythe, California during July 1939.  Upon US Route 95 entering California during 1939 it overlapped and deleted much of the original California State Route 195.  US Route 95 was extended from Blythe into Arizona during June 1960.   Part 1; the history of US Route 95 in California The corridor of modern-day US Route 95 in California first came to prominence during the run-up to the creation of