Final Progress Report on I-74/US 311 Freeway for 2009

Made my last trip of 2009 to check out progress on the construction of the I-74/US 311 freeway from High Point to Randleman during midday today (12/12). Based on the NCDOT's Construction Progress Report there hasn't been much going on along the Business 85 to Cedar Square Road segment the last two months as far as percentage complete goes, now up to about 81% complete at the end of November compared to 78% in September. There has been, however, some noticeable progress on the two remaining bridge projects as well on some of the roadway itself.

Going West to East (or North to South depending on which route you prefer) the first stop is the Baker Road bridge. Work has been completed on the bridge decks as you can see here (yes, they were working on Saturday, making up for bad weather maybe):
The bridge is capable of supporting traffic, as the truck driving across it shows here:
You can see they still have to connect the bridge to the pre-exisiting alignment of Baker Road and build the bridge walls and railings before being open to traffic. This could happen before the end of the year if the weather cooperates.
They are still working on getting the road down to grade south of the bridge and will start north when the bridge is opened and the temporary roadway to the north can be demolished.

Jackson Lake Bridge. Not much progress here west of the bridge, as you can see they still don't have a westbound roadway here, still just piles of dirt:
The roadway to the east toward the Kersey Valley bridge, however, is basically complete and can support contractor traffic as you can see below:
Kersey Valley Road area. Again little progress here. Some more excavation has been done to the roadway west of the bridge:
Notice less construction equipment and machinery present than last month by the graded slopes going eastbound. The view of the roadway between Kersey Valley and I-85 shows more work is needed:
Most of the depressions are filled with water which, due to today's cold temperatures, had turned to ice. They are going to have to wait until this dries up to proceed.

The I-85 interchange. Some progress here, if you look behind the flyover bridge (the farthest) you'll notice the top of an overhead sign structure for the I-85 exit that has been put up. A cantilevered overhead sign structure was also put up just north of the NC 62 bridge.
Another photo of the same area showing progress around the interchange offramp, it appears more grading has been done down toward the future eastbound roadway. And if you didn't notice before, the west wall to the flyover bridge has been completed:
Tuttle Road. There has been more progress in placing guardrails along this section. Looking west you can see there are now guardrails on both directions of the highway:
There is also now guardrail looking east/southbound:
It appears that there is an asphalt layer capable of carrying traffic now from just east of the I-85 interchange heading east almost to Cedar Square Road, with a few exceptions. Notice the truck below is heading the wrong way, but demonstrates it is possible to get to near Cedar Square Road (that would be easiest way off the freeway).
A closer look at the Tuttle Road bridge heading east:
The Cedar Square Road bridge and Interchange. Most of the progress in the last month has been made here. First, the bridge has been opened:
To the right is the old road alignment which will be access to Poole Road. (The connection has been made but the road was blocked by road closed signs, this wasn't preventing locals from making there way around them to access Cedar Square). Now crossing the bridge:
The bridge has 3 lanes, the center reserved for those wanting to make a left turn onto I-74 East, Which occurs just before where this photo was taken looking at the new intersection with US 311:
Second, progress on the on and offramps. For eastbound traffic these are opposite each other while the westbound ramps are on the south side of Cedar Square. Here's the progress being made on the westbound on/off ramps:
Here's a look on the progress of building the eastbound off ramp:
They still need to remove the old alignment of Cedar Square in the freeway's path before final grading and paving can be made.
Meanwhile all the construction equipment is at the end of the current road awaiting construction on the second part to complete the freeway to US 220:
US 311. Some additional clearing in the construction area, and the start of one of the on or offramps, but little else:
US 220. Some progress here in the appearance of a second center support in the median for the other flyover ramp:
Here's progress on the first flyover support, plus clearing on the northbound side:
The wider view of the construction area, heading northbound:
Progress on the future I-74 West Flyover ramp:
They are working also on expanding US 220 to 3 lanes (seen beyond the barrier) between Pineview Street and the existing US 311 exit:
Notice the polls for a new exit sign. These also appear elsewhere along US 220, not just in the I-74 construction area implying another project installing new exit signs, hopefully before the I-74 project is finished and with I-73 mileage based numbers.

My next trip will be after they open the new rest areas/visitor's centers near Seagrove on I-73/74 sometime in January (current completion date is 1/21/10). I'll let everyone know when they are open, in case anyone else wants to come along and tour them.

Comments

Popular posts from this blog

Yes, the color of your nearby fire hydrant matters...

...and here's why. You will find White, Red, Yellow and Violet colored fire hydrants pretty much everywhere.  But there's a reason for this - and it's because of the National Fire Protection Association (NFPA).  This association has issued guidelines for color coding standards for fire hydrants.  These color codes from the body of the hydrant, top of the hydrant, and in some municipalities the outlet caps are designed to allow fire fighters to know what type of system, water flow rate (Gallons Per Minute or GPM), and level of water pressure.  This guideline is known as NFPA 291 and is intended to be used universally throughout the United States. The NFPA guidelines are specific to the body and the top cap of the hydrant.  If a hydrant is WHITE or YELLOW - it means that it is connected to a public/municipal water system.  If a hydrant is RED - the hydrant is connected to a private system, typically a well.  These are most common in rural or unincorporated areas

Phase 1 of the California State Route 132 West Expressway (in the making since 1947)

On September 15, 2022, the Phase 1 of the California State Route 132 West Expressway opened in the city of Modesto from California State Route 99 west to North Dakota Avenue.  Phase 1 of the California State Route 132 West Expressway was built upon a corridor which was tentatively to designated to become the branching point for Interstate 5W in the 1947 concept of the Interstate Highway System.  The present California State Route 132 West Expressway corridor was adopted by the California Highway Commission on June 20, 1956.  Despite almost being rescinded during the 1970s the concept of the California State Route 132 West Expressway corridor lingered on for over half a century and became likely the oldest undeveloped right-of-way owned by California Transportation Commission.  Pictured above is the planned California State Route 132 freeway west of US Route 99 in Modesto as featured in the May/June 1962 California Highways & Public Works.   The history of the California State Route

Aptos Creek Road to the Loma Prieta ghost town site

Aptos Creek Road is a roadway in Santa Cruz County, California which connects the community of Aptos north to The Forest of Nisene Marks State Parks.  Aptos Creek Road north of Aptos is largely unpaved and is where the town site of Loma Prieta can be located.  Loma Prieta was a sawmill community which operated from 1883-1923 and reached a peak population of approximately three hundred.  Loma Prieta included a railroad which is now occupied by Aptos Creek Road along with a spur to Bridge Creek which now the Loma Prieta Grade Trail.  The site of the Loma Prieta Mill and company town burned in 1942.   Part 1; the history of Aptos Creek Road and the Loma Prieta town site Modern Aptos traces its origin to Mexican Rancho Aptos.  Rancho Aptos was granted by the Mexican Government in 1833 Rafael Castro.  Rancho Aptos took its name from Aptos Creek which coursed through from the Santa Cruz Mountains to Monterey Bay.  Castro initially used Rancho Aptos to raise cattle for their hides.  Following