Welcome to my latest annual review of the progress of building I-73, I-74 and other Future Interstate routes in North Carolina. 2018 saw the completion, for the time being, of the remaining I-73 construction projects, the expansion of I-74 construction, and the establishment of one new interstate route, I-285 between Lexington and Winston-Salem. I-73 Work was completed on the US 220 widening project between Summerfield and NC 68 in December 2017, however the route was not officially signed until March 2018. Completion of this segment extended I-73 northward about 4 miles just beyond NC 68. This will be the northern limits of the route for the time being. End I-73 sign approaching US 220 freeway end north of NC 68 At the southern end of state work too was completed, for now, on I-73 (and I-74) in the Rockingham area. The first section of the Rockingham Bypass, the upgrade of 3 miles of US 220 to Interstate Standards was completed in June 2018. The project includes a new exit...