Skip to main content

I-73/I-74 Year in Review 2015

While the year was fairly quiet for both I-73 and I-74 in North Carolina, with only continued construction and no new segment openings, there were some positive signs that funding had been found to accelerate several projects over the next several years.

I-73

Work continued on the I-73 projects in the Greensboro area. The US 220 widening from the Haw River had both good news and bad news. The good news was the project surpassed the 50% completion mark during 2015, with the percentage finished reaching 56.5% at the end of the year. The bad news was that the project was supposed to be 92% complete. Therefore, NCDOT finally faced the facts of the delay in the work and pushed back the completion date from the end of 2016 to June 2017. The additional work on revamping the NC 68 interchange at the northern end of the project should be completed around the same time. Here's a couple photos from last January showing progress approaching the of the future interchange with US 158  and NC 65, courtesy of AARoads Forum member, Strider:

Work is also proceeding on building the I-73 Connector from PTI Airport to US 220 at the Haw River. That project is 45.4% complete and slightly ahead of schedule. The official completion date, however, was pushed back from April to October 2017. Work also started in September on the upgrade of the Bryan Blvd. interchange with the Greensboro Loop (I-840). That project was 22.9% complete at the end of November and should be completed by March 2017. Here's a couple photos taken by Strider this past August of the construction of I-73 along NC 68:

While here's a view of the I-73 roadbed heading east toward US 220:

Meanwhile, at the other end of I-73, work is continuing on the first segment of the I-73/I-74 Rockingham Bypass. The work to bring US 220 up to interstate standards south of Ellerbe is now 33.6% complete as of December 22. The project, however is supposed to be 47% complete, and the delay has pushed back the projected completion date to March 2018 from October 2017. There may be some good news about funding the remainder of the project. A source who visited with an NCDOT project engineer said NCDOT may fund the work next year. It is unclear whether this is due to a new budget formula that is accelerating some I-74 projects (see below) or that the project will be funded in next years Draft STIP document which will cover 2018 to 2027.

I-74

Work continued in 2015 on building the Eastern half of the Winston-Salem Northern Beltway, which started in the fall of 2014. Work constructing the route from Business 40/US 421/NC 150 to US 158 was 14.5% complete as of December 22. A bad sign, however, is that this is already behind schedule, projected to be 18.6% complete and the projected completion date has already been pushed back to April 2019 from October 2018. Here's a couple photos of the construction as seen from Business 40, courtesy of J. Austin Carter:

NC Governor McCrory announced in November 2015 that the NCDOT budget formula had been changed, preventing the legislature from taking money from the transportation fund for other projects. As part of the announcement, the governor indicated money had been found to accelerate several high profile road projects, including the Winston-Salem Beltway. If approved by the NCDOT Board in January, funding would granted to the remaining segments of the Beltway, currently unfunded west of US 311 and not projected to start construction until after 2025. It is unclear at this time, however, when construction would now start on these now funded segments.

The budget changes also led the NCDOT to fund several other transportation projects in the 2016-2025 STIP, previously not projected to start until 2026 or later. Among these was the project to upgrade US 74 to interstate standards from the eastern end of the Rockingham Bypass to the currently signed section of I-74 east of the Bus. 74/Alt. 74 interchange in Robeson County (which would included the once I-74 signed Laurinburg Bypass). If approved by the Board, work would start in 2022. It is perhaps that given that the completion of this segment would mean the I-73/I-74 Bypass segment would be the missing link in a completed I-74 between Winston-Salem and Laurinburg, that NCDOT is to fund that work next year.

2016 is supposed to be another slow year with continued construction of the projects listed above, but perhaps, like this year, there will be some surprises along the way.

Comments

Bob Malme said…
Forgot to mention, to keep up with the latest I-73/I-74 news feel free to visit my website: http://www.gribblenation.net/i7374nc/index.html
Napoleon Reese said…
When are some new stuff coming soon?

Popular posts from this blog

Ghost Town Tuesday; Vineland, Florida; the town killed by Disney

Vineland is a small ghost town located in southwest Orange County, Florida near the junction of Florida State Road 535 and Interstate 4.  Vineland is somewhat unique due to it largely being squeezed out of existence by Lake Buena Vista which is the company town where Disney World is located. Vineland was founded in the late 1800s as Englewood.  The town name of Englewood changed to Orange Center in 1911 before finally assuming the name Vineland in 1924.  Much like the rest of Orange County the community of Vineland was centered around Citrus Grove.  In the case of Vineland said orange groves were centered around Ruby Lake. The end of Vineland came as the Disney Corporation began purchasing parcels of citrus grove land to build Lake Buena Vista.  Vineland fell into a sharp decline in the 1960s but the community managed to continue to exist to modern times.  Much of the street grid of Vineland still exists east of FL 535 but most of the original structures are either gone or falle

Old NY 10 and Goodman Mountain in the Adirondacks

  Old highway alignments come in all shapes and sizes, as well as taking some different forms after their lifespan of serving cars and trucks has ended. In the case of an old alignment of what was NY 10 south of Tupper Lake, New York, part of the old road was turned into part of a hiking trail to go up Goodman Mountain. At one time, the road passed by Goodman Mountain to the east, or Litchfield Mountain as it was known at the time. As the years passed, sometime around 1960, the part of NY 10 north of Speculator became part of NY 30, and remains that way today from Speculator, past Indian Lake and Tupper Lake and up to the Canadian Border. At one time, the highway was realigned to pass the Goodman Mountain to the west, leaving this stretch of road to be mostly forgotten and to be reclaimed by nature. During the summer of 2014, a 1.6 mile long hiking trail was approved the Adirondack Park Agency to be constructed to the summit of the 2,176 foot high Goodman Mountain. For the first 0.9 mi

Oregon State Highway 58

  Also known as the Willamette Highway No. 18, the route of Oregon State Highway 58 (OR 58) stretches some 86 miles between US 97 north of Chemult and I-5 just outside of Eugene, Oregon. A main route between the Willamette Valley region of Oregon with Central Oregon and Crater Lake National Park, the highway follows the Middle Fork Willamette River and Salt Creek for much of its route as it makes its way to and across the Cascades, cresting at 5,138 feet above sea level at Willamette Pass. That is a gain of over 4,500 in elevation from where the highway begins at I-5. The upper reaches of OR 58 are dominated by the principal pinnacle that can sometimes be seen from the highway, Diamond Peak, and three nearby lakes, Crescent, Odell and Waldo (Oregon's second largest lake). OR 58 is chock full of rivers, creeks, mountain views, hot springs and waterfalls within a short distance from the highway. OR 58 was numbered as such by the Oregon State Highway Department in 1940. OR 58 is a del