Construction Update: Newburgh-Beacon Bridge deck replacement project reaches Important Milestone


The dual-span Newburgh-Beacon Bridge (Interstate 84) spans the Hudson River at Newburgh, NY

A major milestone has been reached in the ongoing project to replace the deck of the westbound span of the Newburgh-Beacon Bridge (Interstate 84) in Newburgh, NY. The New York State Bridge Authority (NYSBA) commenced this project in June 2020 in order to extend the useful service life of the westbound bridge by another 40 years while improving safety for travelers by upgrading bridge railings & parapets and expansion joints to modern design & operational standards. The entirety of the nearly 8,000 ft long deck is being removed down to the steel stringers and a new concrete deck will be cast and poured, complete with modified expansion joints and taller bridge parapets that meet modern interstate highway standards. Altogether, this project involves replacing about 350,000 square feet of deck space and is being executed in two distinct phases. The phase that was just completed in November (hence the “important milestone” headline…) saw the replacement of the southern half of the bridge deck in the manor described above. With this phase complete, contractors will now repeat the same process for the northern half of the deck in the coming year.

Westbound views while crossing the single open lane of the westbound Newburgh-Beacon Bridge in November 2021. Traffic crosses the bridge on the newly-complete southern half of rebuilt deck while work  proceeds on the northern half in the next year. Click on each photo to see a larger version.

As with any other major interstate highway/bridge project, the maintenance & protection of traffic has proven challenging for the client agency and its prime contractor. In order to fast track completion and provide as much contractor access to the westbound bridge deck as possible, a temporary two-way traffic pattern was implemented on the eastbound span of the bridge in a “two lanes per direction” configuration. The westbound bridge has largely been closed to all traffic during off-peak hours, however a single lane of traffic is allowed to cross this span during peak periods as it serves as an extended on-ramp for traffic entering the westbound interstate from Route 9D & Beacon. (During off-peak periods, this on-ramp traffic is funneled onto the two-way eastbound span traffic pattern.) This two-way traffic pattern on the eastbound bridge has also created an artificial and temporary traffic bottleneck, as the original configuration of the two spans allowed for three lanes of traffic per direction under normal conditions. Traffic backups related to this project can stretch several miles in either direction on a normal day and this situation is not helped by the fact that the lack of shoulders in this temporary traffic setup prevents disabled vehicles from moving out of travel lanes, which increases the likelihood of traffic jams and rubbernecking delays.


Eastbound views while crossing the eastbound span of the Newburgh-Beacon Bridge. The two-way traffic pattern has temporarily constrained the flow of traffic in the area; on the other hand, the implementation of cashless tolling and removal of the old toll plaza has been a positive development. Click on each photo to see a larger version.

Being built in parallel with this redecking project is the conversion of this bridge (and its sister bridges under NYSBA jurisdiction) to all-electronic toll collection; the tolling gantry located on the Beacon approach just upstream from the old toll plaza was built in the spring of 2021 and the cashless tolling system for this bridge went live in July. The old 1980-built toll plaza has been subsequently demolished in recent months and ongoing road works remain to be completed on the Beacon approach in the coming year. As a life-long resident of southern Dutchess County, NY (except for those few years I was in college out in Buffalo, NY), my single least-favorite toll plaza in the entire country (and I’ve been through a few…) was right here in Beacon. The plaza was a chronic source of traffic congestion at most times and on most days as there were no high-speed EZ-Pass (the electronic toll tag used/accepted by agencies around the northeastern U.S.) lanes and cars still had to nearly come to a stop in the EZ-Pass lanes the plaza did have since NYSBA used automated toll gates that impeded the flow of traffic through. All in all, this is a toll plaza I’m very pleased to see fade into history and this entire stretch of I-84 between Newburgh and Fishkill should move a lot quicker and smoother once this project is completed.


Assorted aerial views of the dual-span bridges including a look at construction progress on the westbound bridge deck and toll plaza reconstruction. Click on each photo to see a larger version.

The two-year, $101 million contract issued by NYSBA is being executed by a contracting outfit led by Yonkers Contracting Company of Yonkers, NY. Major construction & substantial completion, including finishing the remaining work for the new bridge deck, is expected for late 2022 with final completion & close-out of additional punchlist items planned for the first half of 2023. The completion of these final milestones will be welcome news to Hudson Valley (and also long-distance) travelers already tired of the traffic headaches associated with this project. While I’m no fan of sitting in stuck traffic due to construction, this is one of those projects I consider to be absolutely vital for the local and regional economy. This is the first major overhaul for this span of the bridge since the early 1980s and it’s a project that’s been postponed for several years already due to funding restrictions. I will be more than happy to put up with a little inconvenience now in exchange for having a fully functional safe and sound bridge for the next few decades.


Assorted aerial views of the dual-span bridges spanning the Hudson River at Newburgh, NY. Click on each photo to see a larger version.

How to Get There:




Comments

Popular posts from this blog

West Canyon Road (Snow Canyon State Park)

West Canyon Road is an approximately four-mile dirt service road located in Snow Canyon State Park.  West Canyon Road follows Snow Canyon from the Whiptail Trail to the northern State Park boundary and intersects numerous trailheads.   West Canyon Road was the original main road through Snow Canyon after it was designated as a Utah State Park in 1957 and opened to the public in 1962. Part 1; the history of West Canyon Road Snow Canyon is located in the Red Mountains north of the city of Ivins in Washington County, Utah.  Snow Canyon is one of many sandstone canyons located in the Red Mountains.  Part of the extinct Santa Clara Volcano punctured the Red Mountains via lava tubes. From approximately the year 200 to 1,250 the area around Snow Canyon was inhabited by the Ancestral Puebloans.  Mormon pioneers established Santa Clara south of Snow Canyon in 1854.  Local legend has it that the settlers discovered Snow Canyon in the 1850s while searching for m...

Indian Gulch Extension and the Indian Gulch ghost town site

Indian Gulch Extension is an approximately 6-mile-long rural highway corridor in the Sierra Nevada foothills of western Mariposa County.  Indian Gulch Extension begins at Indian Gulch Road near the namesake ghost town of Indian Gulch.  From the ghost town site Indian Gulch Extension extends southwesterly to the Merced County line where it becomes Waltz Road.   The former Gold Rush era community of Indian Gulch which was settled near Santa Cruz Mountain in 1849 and had standing structures until the early 1970s.  What is now Indian Gulch Extension was approved for construction by the Mariposa County Commissioners in 1862.  The purpose of the corridor was to provide Indian Gulch with a direct connection westward with the greater Stockton-Los Angeles Road.  The Stockton-Los Angeles Road would go onto define much of the Mariposa County and Merced County line.  Part 1; the history of Indian Gulch and Indian Gulch Extension Indian Gulch Road is named aft...

The reemergence of US Route 99 at the Ventura Freeway/Golden State Freeway interchange

During April 2023 a portion of the sign gantry on the eastbound Ventura Freeway (California State Route 134) approaching the Golden State Freeway (Interstate 5) fell.  The fallen portion of the sign gantry revealed a once covered US Route 99 shield.  The uncovered US Route 99 sign (blog cover courtesy Ian Ligget) is a 1956-63 era freeway specification US Route shield.  This blog will explore in brief how the Golden State Freeway was developed as US Route 99 and US Route 6 before becoming solely Interstate 5.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page Part 1; visiting the US Route 99 shield at the Ventura Freeway/Golden State Freeway Interchange As noted in the introduction the US Route 99 shield can be seen on the eastbound Ventura Freeway (California Sta...