Lehigh Tunnels Twin Tubing 1989-1991

On April 1, 1957, the 47 of the remaining 73 miles of the Pennsylvania Turnpike's Northeast Extension opened to traffic.  Included in the new highway was the 4,461 foot Lehigh Tunnel, a two lane tube through the Blue Mountain.  However by 1970, concerns over the levels of traffic through the 13 year old tunnel were growing.  Throughout the 1960's the Turnpike either twinned or bypassed the seven tunnels on the mainline system.  For over a decade, various proposals were introduced but tight economic times did not allow for proactive construction.  Finally, in 1985, Act 61 authorized new funding for the Pennsylvania Turnpike System.  The legislation approved funding for the twinning of the Lehigh Tunnels. Studies began almost immediately and construction began early in 1989.  Construction would last for nearly two and a half years, ending with the opening of the new facility on November 22, 1991.
 
Throughout the 32 months of construction, Bill Symons took photographs of the progress made.  He begins with an untouched south portal in 1989 to the tunnels a few weeks before opening in the fall of 1991. 

South Portal: 
Excavation work can be seen on this 1989 shot approaching the southern portal of the Lehigh Tunnel. (Bill Symons)
If you were heading northbound on PA 9 in 1989, you would not see much of any sign of construction work entering the tunnel.  This photo gives an excellent perspective of how the highway would narrow upon entering the tunnel. (Bill Symons)

Here is what the completed twin tubes look like nearly 20 years later.  (Doug Kerr, April 2007)

 North Portal:


Be sure to notice the change in the hillside from this photo in 1989 and the following two.  Excavation work has begun and the concrete superstructure is beginning to take form. (Bill Symons)

Substantial progress can be seen by the Autumn of 1990.  A wide double yellow line and guard rail is all that separates the opposite direction of traffic entering and exiting the tunnel. (Bill Symons)

The tunnel is near completion in this Fall 1991 photo.  The hillside has been landscaped and a cement slope and retaining wall has been built.  A temporary concrete barrier has also been placed to divide the then current north and southbound traffic.

Site Navigation:

Comments

Popular posts from this blog

Grand Loop Road of Yellowstone National Park

  Grand Loop Road is a 140 mile loop highway which traverses the interior of Yellowstone National Park.  Grand Loop Road connects all of the major attractions and geological features of Yellowstone National Park along with the entrance roads.  Grand Loop Road is a seasonal highway and despite some conjecture never has been part of the US Route System.   Part 1; the history of Grand Loop Road The majority of history pertaining to Grand Loop Road was taken from the below National Park Service article: Historic Roads - Yellowstone National Park (U.S. National Park Service) (nps.gov) Yellowstone was declared the first National Park of the United States on March 1st, 1872.  The first real highway to access Yellowstone National Park came in 1873 when a tolled facility was constructed from Bozeman, Montana via Yankee Jim Canyon to Mammoth Hot Springs.  Numerous attempts were made to fund construction of roadway infrastructure during the early years of Yellows...

The last 1956-63 era California Sign State Route Spade?

Along southbound California State Route 170 (the Hollywood Freeway Extension) approaching the Hollywood Freeway/Ventura Freeway interchange a white California State Route 134 Sign State Route Spade can be observed on guide sign.  These white spades were specifically used during the 1956-63 era and have become increasingly rare.  This blog is intended to serve as a brief history of the Sign State Route Spade.  We also ask you as the reader, is this last 1956-63 era Sign State Route Spade or do you know of others?  Part 1; the history of the California Sign State Route Spade Prior to the Sign State Route System, the US Route System and the Auto Trails were the only highways in California signed with reassurance markers.  The creation of the US Route System by the American Association of State Highway Officials during November 1926 brought a system of standardized reassurance shields to major highways in California.  Early efforts to create a Sign State Route ...

California State Route 70; the Feather River Highway

From 2017 through to early 2019 I drove the majority of the California State Route 70; the Feather River Highway from CA 89 southwest to CA 99. CA 70 is an approximately 178.5 mile state highway which starts at US 395 near the Nevada State Line and travels west through the Feather River Canyon to CA 99.  CA 70 is often referred to as the Feather River Highway" given it's close association with the river.  Historically CA 70 was previously signed as US 40A and CA 24.  The Legislative Routes prior to the 1964 California Highway Renumbering that made up the current route of CA 70 are as follows: -  Legislative Route Number 21 from US 395 westward to Oroville. -  LRN 87 from Oroville south to Marysville. -  LRN 232 from Marysville to the current junction with CA 99.  CA 70 was even dual signed with CA 99 into Sacramento on what was LRN 232 for a time. The change from US 40A/LRN 21/LRN 87/LRN 232 can be seen by comparing the 1963 State Highway Ma...