As Adam indicated in his previous photo post, we were out Saturday (4/10) checking on the progress of the Triangle Expressway, the Future Toll portions of NC 540 and NC 147. The trip went in the opposite direction as before, so this progress report will start with...
1. The Western Wake Freeway (NC 540):
As seen from the current end of NC 540 looking west, there has been some substantial work on grading the road and the start of installing bridges since our last visit in February:
Both cement and steel bridge supports can be seen. They have piled the material needed for the next bridge project on the median between the unopened lanes of NC 540:
The first major road closure will occur tomorrow (4/12) as explained in this message sign:
McCrimmon Parkway will be closed as a bridge is put in to take the parkway over the freeway.
Here's a view of what they will have to remove:
The parkway is behind the guardrail. The photo was taken from the edge of the Panther Creek High School stadium access road. The stadium bleachers will have a good view of construction, and of the toll road traffic, after completion. Here's the view looking toward NC 55 from where the Parkway bridge will be constructed:
As you can see on the left, there has already been a start to landscaping the highway. The tracks to the right are how contractor vehicles enter and leave the roadbed (with drivers to busy to return a wave). The photo below looks the other direction, south of McCrimmon Parkway:
It appears they are starting bridge construction along the highway in the distance. The cement slab at bottom right is part of a culvert they are building, closeup photo below:
Since last February, construction, has proceeded across Carpenter Fire Station Road in Cary and further south toward US 64. The photo below is looking south along Carpenter...
Here's a view to the north:
As construction moves along, we have tried to find parking areas that are best to observe the construction. The newest one we found is the parking lot for the relatively new USA Baseball complex, here's a photo of the future toll road taken walking from the parking lot to within the toll road's right-of-way:
While most of the construction ends about here, around the curve behind the hill of dirt...
Clearing continues south past Green Level Road East where the contractor has cleared enough space for an office trailer and parking lot for employee vehicles. This is where the first interchange south of NC 55 will be built. The most interesting items in this area are that some houses have not been cleared but are apparently being used by the fire department for training exercises. Here's one that's been mostly burned down:
The tree clearing stops south of Green Level, a little more than a mile north of US 64, the next major route to be affected by the West Wake Freeway construction.

2. The Triangle Parkway (NC 147)
We saw less progress here than on the NC 540 portion, surprising, since this section is only 3 miles long and is supposed to be complete next year. There were some signs of progress at the southern end, as seen below from the current NC 540 Davis Drive offramp:
Some initial construction work and clearing has gone north of here. You can view additional clearing that has taken place south of Davis Drive as it curves back toward Hopson Road:
However, little progress can be seen to the north as viewed from the future Hopson Road bridge and interchange:
Which appears similar to the photos of the area taken in February, except that one of the construction trailers has been moved. A clue to the lack of progress may be seen south of Hopson...
Where currently the high-power electric transmission poles and lines appear to be in the future parkway's right-of-way. Whether this is according to schedule, or is due to a delay in talks with the power company, is not known. Any lag in progress here may threaten to delay the planned opening date of 2011.
They are making progress at the northern end where the current NC 147 meets its future pathway:
The grade has been cut down to meet the current roadway and it appears work on a culvert is starting where the two cranes are located. There is also construction starting along current NC 147 southbound by the I-40 interchange. I will try to find out whether there is any problems that would cause a delay in constructing the parkway before the next update in late May.

Comments

Popular posts from this blog

Grand Loop Road of Yellowstone National Park

  Grand Loop Road is a 140 mile loop highway which traverses the interior of Yellowstone National Park.  Grand Loop Road connects all of the major attractions and geological features of Yellowstone National Park along with the entrance roads.  Grand Loop Road is a seasonal highway and despite some conjecture never has been part of the US Route System.   Part 1; the history of Grand Loop Road The majority of history pertaining to Grand Loop Road was taken from the below National Park Service article: Historic Roads - Yellowstone National Park (U.S. National Park Service) (nps.gov) Yellowstone was declared the first National Park of the United States on March 1st, 1872.  The first real highway to access Yellowstone National Park came in 1873 when a tolled facility was constructed from Bozeman, Montana via Yankee Jim Canyon to Mammoth Hot Springs.  Numerous attempts were made to fund construction of roadway infrastructure during the early years of Yellows...

The last 1956-63 era California Sign State Route Spade?

Along southbound California State Route 170 (the Hollywood Freeway Extension) approaching the Hollywood Freeway/Ventura Freeway interchange a white California State Route 134 Sign State Route Spade can be observed on guide sign.  These white spades were specifically used during the 1956-63 era and have become increasingly rare.  This blog is intended to serve as a brief history of the Sign State Route Spade.  We also ask you as the reader, is this last 1956-63 era Sign State Route Spade or do you know of others?  Part 1; the history of the California Sign State Route Spade Prior to the Sign State Route System, the US Route System and the Auto Trails were the only highways in California signed with reassurance markers.  The creation of the US Route System by the American Association of State Highway Officials during November 1926 brought a system of standardized reassurance shields to major highways in California.  Early efforts to create a Sign State Route ...

California State Route 70; the Feather River Highway

From 2017 through to early 2019 I drove the majority of the California State Route 70; the Feather River Highway from CA 89 southwest to CA 99. CA 70 is an approximately 178.5 mile state highway which starts at US 395 near the Nevada State Line and travels west through the Feather River Canyon to CA 99.  CA 70 is often referred to as the Feather River Highway" given it's close association with the river.  Historically CA 70 was previously signed as US 40A and CA 24.  The Legislative Routes prior to the 1964 California Highway Renumbering that made up the current route of CA 70 are as follows: -  Legislative Route Number 21 from US 395 westward to Oroville. -  LRN 87 from Oroville south to Marysville. -  LRN 232 from Marysville to the current junction with CA 99.  CA 70 was even dual signed with CA 99 into Sacramento on what was LRN 232 for a time. The change from US 40A/LRN 21/LRN 87/LRN 232 can be seen by comparing the 1963 State Highway Ma...