Campus Parkway (Merced, California)

Campus Parkway is a 4.5-mile expressway corridor located in and around the city of Merced.  Campus Parkway spans from California State Route 99 to Yosemite Avenue and is part of the larger conceptual Campus Loop corridor.  The Campus Loop in full scale a series of planned roadways which if built will encircle Merced with an expressway grade beltway and permit easier access to the University of California-Merced campus.  Campus Parkway was completed in three phases in 2009, 2020 and 2022. 



Part 1; the history of Campus Parkway

The purpose of Campus Parkway is to enhance access to the campus of University of California-Merced (UC-Merced).  In full scale the corridor begins at California State Route 99 Exit 185 and extends 4.5 miles northward as a four-lane expressway to Yosemite Avenue.  The Campus Parkway corridor can be seen in contrast to the rest of the larger proposed Campus Loop which also includes Atwater-Merced Expressway. 


Currently access to the UC-Merced is mostly provided by way of substandard two-lane roadways.  The concept of a Merced campus as part of the University of California system was borne during the late 1980s and early 1990s due to increased Central Valley enrollment.  The University of California Board of Regents selected Merced for the planned new campus during May 1995.  Construction of the UC-Merced campus broke ground during October 2002 and would open for classes during September 2005.  

The Draft Environmental Impact Report for Campus Parkway was submitted via the provisions of the California Environmental Quality Act (CEQA) on April 22, 2005.  The corridor was planned as spanning from California State Route 99 north to Yosemite Parkway.  The project also included an overpass of overpass the Burlington North Santa Fe Railway and California State Route 140.  Access to California State Route 140 was proposed to be facilitated via a ramp structure.   


An initial affirmative Notice of Determination regarding Campus Parkway was issued by CEQA on December 26, 2006.  Further facets of the project were approved on September 26, 2007



Phase I of Campus Parkway included construction of the interchange with California State Route 99 and the roadway to Childs Avenue in 2009.  The Phase II corridor broke ground during early 2018 and was scheduled for completion during the first quarter of 2020.  Phase II would extend from Childs Avenue north to the ramp connecting to California State Route 140.  Phase II was funded by way of Senate Bill 1 Transportation Package.  Said bill allocated $100,000,000 in funding to Phase II and Phase III of the Campus Parkway project.  

Campus Parkway Phase II construction can be seen in a southward aerial photo facing towards California State Route 140 circa December 2018.  The connecting ramp to California State Route 140 can be seen on the left.  


Phase II construction can be seen in a January 2019 photo facing northward towards California State Route 140.  


The Phase II Campus Parkway completion dedication ceremony was held on February 3, 2020. 


Phase III of the Campus Parkway project broke ground shortly after completion of Phase II.  The Phase III corridor would extend the roadway from California State Route 140 north to the planned terminus at Yosemite Avenue.  Initial projections had Phase III opening to traffic during June 2023 but was ultimately completed ahead of schedule.  The Phase III dedication ceremony celebrating the completion of Campus Parkway was held on July 8, 2022 (photo Merced County Times). 




Part 2; a drive on Campus Parkway

Northbound Campus Parkway begins at California State Route 99 Exit 185 in the city of Merced.  The exit signage notes Campus Parkway to be the preferred access way to UC Merced.  




Campus Parkway turns northward and crosses over the Burlington North Santa Fe Railway and California State Route 140 at the Merced city limit.  State Highway access is permitted to the state highway via a connecting ramp signed as "Campus Parkway Access."










Campus Parkway passes through a roundabout at Olive Avenue.  The corridor continues northward to a terminus located at another roundabout found at Yosemite Avenue.  Beyond Yosemite Avenue local signage advises traffic to follow Lake Road to UC Merced.











Comments

Anonymous said…
That roundabout on Olive is spectacular, I regularly overtake on the approach and entry.

Popular posts from this blog

Crescent City Connection (New Orleans, LA)

The Crescent City Connection is a massive dual-span steel truss bridge that spans the lower Mississippi River at downtown New Orleans, about 95 river miles upstream from the mouth of the great river at the Head of Passes Light. If counted as a single bi-directional highway bridge, the parallel spans combine to form the single busiest bridge on the Mississippi River and its importance as a linchpin in the region’s transportation network cannot be overstated. While there have been various schemes over the years to construct bridges downriver from Algiers Point, this bridge has been the southernmost bridge on the Mississippi River since its initial construction in the 1950s. The years immediately following the end of World War II were a transformational period in the history of New Orleans. Already one of the great economic and cultural centers of the American Deep South, it was recognized at this time that major changes and improvements to the city’s transportation infrastructure would b...

Old US Route 99 through Tipton, Tulare, and Tagus Ranch

This summer I had a look into the alignment history of US Route 99 through the Tulare County communities of Tipton, Tulare, and Tagus Ranch.  While this slab below might seem like much it is one of the few remaining reminders of how US Route 99 was during the 1920s in Tulare County. This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page Part 1; the history of US Route 99 in Tipton, Tulare, and Tagus Ranch Tipton and Tulare were both founded in 1872 as sidings of the Southern Pacific Railroad.  The Southern Pacific Railroad laid the groundwork for development of southern San Joaquin Valley.  Previous to the Southern Pacific Railroad travel via wagon or foot in Central California tended to avoid San Joaquin Valley in favor of the Stockton-Los Angeles Road.  The Stockton Los Ange...

Former US Route 101 and California State Route 41 through Paso Robles

Paso Robles is a city located on the Salinas River of San Luis Obispo County, California.  As originally configured the surface alignments of US Route 101 and California State Route 41 converged in downtown Paso Robles.  US Route 101 originally was aligned through Paso Robles via Spring Street.  California State Route 41 entered the City of Paso Robles via Union Road and 13th Street where it intersected US Route 101 at Spring Street.  US Route 101 and California State Route 41 departed Paso Robles southbound via a multiplex which split near Templeton.   Pictured above is the cover of the September/October 1957 California Highways & Public Works which features construction of the Paso Robles Bypass.  Pictured below is the 1935 Division of Highways Map of San Luis Obispo County which depicts US Route 101 and California State Route 41 intersecting in downtown Paso Robles.   Part 1; the history of US Route 101 and California State Route 41 i...