Skip to main content

Before the Dirt Flies on the Triangle Expressway

A recent news report indicated that there has been a delay in starting construction of the Triangle Expressway, the future toll portion of the 540 loop around Raleigh and connector between I-40 in Research Triangle park and 540. They blamed it on some permitting issues (maybe there now too close to NCDOT and inheriting their working traits). This gave me some time to take some 'before' photos at least along the corridor of the future Triangle Parkway that will run between I-40 and what is now the Davis Drive exit on NC 540. Starting at the northern end, or beginning:
This is current NC 147 South before it takes the curve to end at Alexander Drive. The Parkway will go straight and the connection to Alexander will be eliminated. If you see the gravel on the left, this was the only sign of construction I saw along the corridor. The following photos show the ending of NC 147 at Alexander that will be removed:
The stoplight at Alexander with signage common in Research Triangle Park. You can reach NC 54 and Davis Drive going to the right.
The soon to be late connection to the Durham freeway as it appears heading SW on Alexander.

Another look at the only new Parkway related construction I saw heading North on NC 147:
This may have been dug up to aide survey teams. The Parkway will cut across the photo probably starting near the I-40 sign and to its rear.

Heading on NC 540 West, the only signs of impending construction are new orange signs:
These signs are just beyond the exit ramp for the Exit 69, NC 54.
According to these signs the construction zone will begin just before the current Davis Drive exit ramp. The current access to Davis Drive will be changed and access will become part of the Triangle Parkway interchange built between the current off- and on-ramps.
This is the large open gap (about 1/2 mile) between the current ramps from Davis Drive is for use as part of the continuation of the Triangle Expressway onto NC 540 west as part of the continuation of the Triangle Expressway.
From the 'End Construction' sign you can see beyond the NC 55 exit sign, it appears, for now anyway, construction on this end anyway will concentrate on building the Triangle Parkway and not the Western Wake Freeway, the extension of NC 540.

As if there's any more evidence no construction has started:
This is the western end of NC 540. The site of the August groundbreaking can be seen on the left side. The access road and the ceremonial dirt put up next to where the stage was built still sitting there.

Finally here's where traffic on NC 55 will access the toll route west, then south toward Apex:
I will be back to this area, once the constant Turnpike Authority phrase "Construction could start in the next couple weeks" rings true.

Comments

brett said…
i've seen several times that the current end of 147 at alexander dr will be closed when the freeway is extended. but what if they did this instead: 1) close the northbound lanes entirely; 2) leave the southbound lanes open as an exit from 147 south to alexander dr.; 3) construct an entrance ramp from alexander dr. to 147 south at the current intersection; 4) construct an exit/entrance pair (entrance being a long loop) to and from northbound 147 to 54, maybe with the ramps ending at the intersection with park circle dr. 1/4 mile east of where 54 passes over 147. the latter may be too close to i-40 to be safe but the former shouldn't be a problem, eh? has anyone thought of this idea before? it could help mobility around not only south durham but also that section of rtp and keep maybe a small amount of traffic off of i-40.
Anonymous said…
Anyone here know whether they're going to reconstruct the exit from South NC 147 to East I-40 to a flyover and right entrance instead of the horrid left entrance? Or would that be in conflict with the nearby Davis Drive exit?
Anonymous said…
This comment has been removed by a blog administrator.

Popular posts from this blog

Grand Loop Road of Yellowstone National Park

  Grand Loop Road is a 140 mile loop highway which traverses the interior of Yellowstone National Park.  Grand Loop Road connects all of the major attractions and geological features of Yellowstone National Park along with the entrance roads.  Grand Loop Road is a seasonal highway and despite some conjecture never has been part of the US Route System.   Part 1; the history of Grand Loop Road The majority of history pertaining to Grand Loop Road was taken from the below National Park Service article: Historic Roads - Yellowstone National Park (U.S. National Park Service) (nps.gov) Yellowstone was declared the first National Park of the United States on March 1st, 1872.  The first real highway to access Yellowstone National Park came in 1873 when a tolled facility was constructed from Bozeman, Montana via Yankee Jim Canyon to Mammoth Hot Springs.  Numerous attempts were made to fund construction of roadway infrastructure during the early years of Yellows...

The last 1956-63 era California Sign State Route Spade?

Along southbound California State Route 170 (the Hollywood Freeway Extension) approaching the Hollywood Freeway/Ventura Freeway interchange a white California State Route 134 Sign State Route Spade can be observed on guide sign.  These white spades were specifically used during the 1956-63 era and have become increasingly rare.  This blog is intended to serve as a brief history of the Sign State Route Spade.  We also ask you as the reader, is this last 1956-63 era Sign State Route Spade or do you know of others?  Part 1; the history of the California Sign State Route Spade Prior to the Sign State Route System, the US Route System and the Auto Trails were the only highways in California signed with reassurance markers.  The creation of the US Route System by the American Association of State Highway Officials during November 1926 brought a system of standardized reassurance shields to major highways in California.  Early efforts to create a Sign State Route ...

California State Route 70; the Feather River Highway

From 2017 through to early 2019 I drove the majority of the California State Route 70; the Feather River Highway from CA 89 southwest to CA 99. CA 70 is an approximately 178.5 mile state highway which starts at US 395 near the Nevada State Line and travels west through the Feather River Canyon to CA 99.  CA 70 is often referred to as the Feather River Highway" given it's close association with the river.  Historically CA 70 was previously signed as US 40A and CA 24.  The Legislative Routes prior to the 1964 California Highway Renumbering that made up the current route of CA 70 are as follows: -  Legislative Route Number 21 from US 395 westward to Oroville. -  LRN 87 from Oroville south to Marysville. -  LRN 232 from Marysville to the current junction with CA 99.  CA 70 was even dual signed with CA 99 into Sacramento on what was LRN 232 for a time. The change from US 40A/LRN 21/LRN 87/LRN 232 can be seen by comparing the 1963 State Highway Ma...