First Tour of the TriEx in 2010

Adam Prince and I took a Sunday morning tour to check out construction of the Triangle Expressway, NC's first Toll Road. I had not been down to check progress since I first toured the area last fall. The TriEx (as the Turnpike Authority is trying to get potential users to call it) is made up of 2 parts: The Triangle Parkway (an extension of NC 147) and the Western Wake Freeway, an extension of NC 540 from NC 55 north of Apex to the NC 55 Bypass in Holly Springs.
Here's a map to help explain the two parts and to identify the locations where we went on this trip (map excerpt taken from NCTA 2009 Annual Report, p. 17):
We expected to see more progress on the Triangle Parkway than the Western Wake Freeway, but it turns out it was the exact opposite. The contractors (who are working under the name The Raleigh Durham Roadbuilders, very original) started tree cutting and landscaping at the northern end of the Triangle Parkway, starting where it will depart from the existing NC 147:
Above is a photo from the southbound lanes while below is a view going northbound:
The tree cutting and landscaping continues, but only as far as just south of the US EPA complex. Here's a view north from the end of the cutting back toward Hopson Road, which will have the one of the two interchanges on the parkway (the other being for Davis Drive, number 3 in the map above:
Here's a view from the overlook on the other side of the road:
The ground overlooking the above view will be used as part of building a bridge for the road/ parkway intersection. The dimensions of the bridge were marked by stakes like below:
This was on the west side of the Parkway right-of-way, a similar stake was marked on the east side. Here was some of the equipment doing preliminary work on the bridge:
There was no work going on here, in contrast to where we went next, the current end of NC 540 at Exit 66:
Notice the cars parked on the left for contractors doing work even on Sunday.
Now an indulgence:
A closeup of the Exit 66A gore sign. Since I'm partially responsible for the taped over number, and the map shows different interchange numbers, I thought I'd take a photo before 'my exit numbers' were possibly removed.
Now back to the overview of construction progress:
The crane truck seen two photos above. Where this equipment and road closed signs are, is where the groundbreaking took place last fall, not even the potted plants remain. Here's a view beyond the barriers:
Just in case you wanted to see an official sign as who is constructing the parkway:
You can tell their tree cutting is very environmental from the color of the highway and the flower in the middle of the logo (plus you can work on your Spanish).

We thought that there would not be much tree cutting and landscaping work for this part of the Expressway as for the Parkway. Turns out there was more. The clearing proceeds further south, over McCrimmon Parkway, just to the west of Panther Creek High School, and all the way to Carpenter Fire Station Road in Cary (that's just about where the purple NC 540 shield is in the map above, if you're not familiar with the area). We plan to go out again in late March to get the next update on construction. The NCTA still says the Triangle Parkway will be open in 2011.

Comments

Anonymous said…
Thank you for updating us, esp since the news and county don't seem to care to. Really wished they were further along.
Anonymous said…
Let's get some of the stimulus $$$ to build it quicker. We can surely use the 64 to US1 section as soon as possible. Every day I go against the traffic it will be great to see the fuel economy savings as folks avoid the traffic.
Anonymous said…
Well this week April 5-9 they have cleared Kitt Creek/540 to Davis, I imagine Davis to hopason next week for the Triangle parkway.
They are moving fast. Once those crews go in, they clear many acres a day.

Popular posts from this blog

Grand Loop Road of Yellowstone National Park

  Grand Loop Road is a 140 mile loop highway which traverses the interior of Yellowstone National Park.  Grand Loop Road connects all of the major attractions and geological features of Yellowstone National Park along with the entrance roads.  Grand Loop Road is a seasonal highway and despite some conjecture never has been part of the US Route System.   Part 1; the history of Grand Loop Road The majority of history pertaining to Grand Loop Road was taken from the below National Park Service article: Historic Roads - Yellowstone National Park (U.S. National Park Service) (nps.gov) Yellowstone was declared the first National Park of the United States on March 1st, 1872.  The first real highway to access Yellowstone National Park came in 1873 when a tolled facility was constructed from Bozeman, Montana via Yankee Jim Canyon to Mammoth Hot Springs.  Numerous attempts were made to fund construction of roadway infrastructure during the early years of Yellows...

The last 1956-63 era California Sign State Route Spade?

Along southbound California State Route 170 (the Hollywood Freeway Extension) approaching the Hollywood Freeway/Ventura Freeway interchange a white California State Route 134 Sign State Route Spade can be observed on guide sign.  These white spades were specifically used during the 1956-63 era and have become increasingly rare.  This blog is intended to serve as a brief history of the Sign State Route Spade.  We also ask you as the reader, is this last 1956-63 era Sign State Route Spade or do you know of others?  Part 1; the history of the California Sign State Route Spade Prior to the Sign State Route System, the US Route System and the Auto Trails were the only highways in California signed with reassurance markers.  The creation of the US Route System by the American Association of State Highway Officials during November 1926 brought a system of standardized reassurance shields to major highways in California.  Early efforts to create a Sign State Route ...

California State Route 70; the Feather River Highway

From 2017 through to early 2019 I drove the majority of the California State Route 70; the Feather River Highway from CA 89 southwest to CA 99. CA 70 is an approximately 178.5 mile state highway which starts at US 395 near the Nevada State Line and travels west through the Feather River Canyon to CA 99.  CA 70 is often referred to as the Feather River Highway" given it's close association with the river.  Historically CA 70 was previously signed as US 40A and CA 24.  The Legislative Routes prior to the 1964 California Highway Renumbering that made up the current route of CA 70 are as follows: -  Legislative Route Number 21 from US 395 westward to Oroville. -  LRN 87 from Oroville south to Marysville. -  LRN 232 from Marysville to the current junction with CA 99.  CA 70 was even dual signed with CA 99 into Sacramento on what was LRN 232 for a time. The change from US 40A/LRN 21/LRN 87/LRN 232 can be seen by comparing the 1963 State Highway Ma...