Perdue offers I-485 financing plan, but many questions need to be answered first

Earlier today, Governor Perdue announced her plan to complete the Interstate 485 loop in the next five years. The plan is something called a design-build-finance plan, and it has yet to be used within North Carolina. However, there are a number of hurdles and loopholes within the plan

The term 'design-build' is familiar within North Carolina transportation projects. Design-build projects are where the builder also designs the overall project- often while the project is ongoing. One of North Carolina's first design-build projects was the Interstate 85 widening between miles 40-48.

'Design-build-finance' is where the contractor pays for some or all of the construction and then gets reimbursed by the state within a specified period of time. This method has been used elsewhere in the country including an Interstate 69 reconstruction project in Michigan.

The projected cost to complete the remaining five miles of I-485 is now roughly $340 million.

Under this plan, construction for I-485 will start next year and be completed by 2015. Plus, the governor's office emphasizes that money will not come from or delay other projects.

Sounds too good to be true right? The contractor pays for some of the construction, gets paid back by the state, no other projects get delayed.

Well, I need that Lee Corso photo again...because "Not so fast, my friend!"

First, the financing method. The contractor would pay $50 million of the $340 million to construct the highway. Well, first you have to find a construction firm that has $50 million in cash to finance the highway. And with troubles NCDOT has had with various construction companies over the past decade, that's not a guarantee.

Adam Froehlig, in a post to a national transportation forum, notes that this approach was tried for Minnesota's Crosstown Commons project but no construction firm placed a bid.

The $50 million that the construction company puts down for the highway would be paid back by the state over a 10 year period. Questions come from that too. What will the interest rate be...will the money owed to the construction company, somewhere between $5-6 million a year, impact financing other projects? With the state and the DOT in the red, will the state be able to pay it back over that period?

If the contractor is only paying $50 million or 14.7% of the costs, where is the other money coming from? The Governor's office says that no other project will be delayed. Well, according to the Charlotte Observer, the DOT's chief financial officer, Mark L. Foster, admits that the DOT is 'prioritizing' projects statewide, including I-485. If this is the case, then aren't other projects going to be delayed? Plus, when the missing five miles cost only $220 to construct - the state said they had no money to complete it. Now, they need to come up with $290 million - that's $70 million more than the original estimated cost - and suddenly NCDOT has the money.

The highway that most likely will be delayed is Interstate 295 in Fayetteville, which has the whipping boy for every other city in the state who has seen delays in their planned freeway loops.

Personally, I'd like to see where this $290 million will come from. Will the controversial equity formula be repealed? Will they try to sneak in tolls? Something just doesn't add up here.

There are other hurdles for the highway - specifically environmental concerns. Charlotte has had a growing ozone (ground level) issue and has been under the careful eye of the US Environmental Protection Agency. In fact, highway funding for Charlotte has been threatened to be cutoff if the metro area didn't improve air quality. Groups like the Southern Environmental Law Center will be certain to keep a close eye on this process.

Now what if this works?

Well, as the economy improves, more construction companies will be able to assist in financing similar projects. This could possibly speed up delayed projects and also eliminate future projects becoming toll roads.

So there could be a new opportunity for the future of North Carolina highways. However, this is a big test, and a lot of interested parties will be keeping their eye on how the final five miles of Interstate 485 eventually gets built. There is a lot riding on this project - not only politically for Governor Perdue - but on how other highway projects in North Carolina are built short and long term. It will be an interesting few months and years to see how this all unfolds.

Story Links:
I-485 plan: Tap builder cash ---Charlotte Observer
Gov. says work to finish I-485 will start in 2010 ---WBTV-TV
Governor says I-485 will be completed in five years ---WCNC-TV
Perdue unveils plan to complete Interstate 485 ---News14Carolina

Comments

This comment has been removed by a blog administrator.
Anonymous said…
This comment has been removed by a blog administrator.

Popular posts from this blog

West Canyon Road (Snow Canyon State Park)

West Canyon Road is an approximately four-mile dirt service road located in Snow Canyon State Park.  West Canyon Road follows Snow Canyon from the Whiptail Trail to the northern State Park boundary and intersects numerous trailheads.   West Canyon Road was the original main road through Snow Canyon after it was designated as a Utah State Park in 1957 and opened to the public in 1962. Part 1; the history of West Canyon Road Snow Canyon is located in the Red Mountains north of the city of Ivins in Washington County, Utah.  Snow Canyon is one of many sandstone canyons located in the Red Mountains.  Part of the extinct Santa Clara Volcano punctured the Red Mountains via lava tubes. From approximately the year 200 to 1,250 the area around Snow Canyon was inhabited by the Ancestral Puebloans.  Mormon pioneers established Santa Clara south of Snow Canyon in 1854.  Local legend has it that the settlers discovered Snow Canyon in the 1850s while searching for m...

Indian Gulch Extension and the Indian Gulch ghost town site

Indian Gulch Extension is an approximately 6-mile-long rural highway corridor in the Sierra Nevada foothills of western Mariposa County.  Indian Gulch Extension begins at Indian Gulch Road near the namesake ghost town of Indian Gulch.  From the ghost town site Indian Gulch Extension extends southwesterly to the Merced County line where it becomes Waltz Road.   The former Gold Rush era community of Indian Gulch which was settled near Santa Cruz Mountain in 1849 and had standing structures until the early 1970s.  What is now Indian Gulch Extension was approved for construction by the Mariposa County Commissioners in 1862.  The purpose of the corridor was to provide Indian Gulch with a direct connection westward with the greater Stockton-Los Angeles Road.  The Stockton-Los Angeles Road would go onto define much of the Mariposa County and Merced County line.  Part 1; the history of Indian Gulch and Indian Gulch Extension Indian Gulch Road is named aft...

The reemergence of US Route 99 at the Ventura Freeway/Golden State Freeway interchange

During April 2023 a portion of the sign gantry on the eastbound Ventura Freeway (California State Route 134) approaching the Golden State Freeway (Interstate 5) fell.  The fallen portion of the sign gantry revealed a once covered US Route 99 shield.  The uncovered US Route 99 sign (blog cover courtesy Ian Ligget) is a 1956-63 era freeway specification US Route shield.  This blog will explore in brief how the Golden State Freeway was developed as US Route 99 and US Route 6 before becoming solely Interstate 5.   This blog is part of the larger Gribblenation US Route 99 Page.  For more information pertaining to the other various segments of US Route 99 and it's three-digit child routes check out the link the below. Gribblenation US Route 99 Page Part 1; visiting the US Route 99 shield at the Ventura Freeway/Golden State Freeway Interchange As noted in the introduction the US Route 99 shield can be seen on the eastbound Ventura Freeway (California Sta...